Solar PV Permit (Alternative Energy) — Lewistown, Montana · Requirements sheet
Verified 2026-07-20 · Source: https://bsd.dli.mt.gov/building-codes-permits/permit-applications/electrical-permits/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit (Alternative Energy) in Lewistown, Montana
Required for installation of rooftop or ground-mounted solar photovoltaic systems within Lewistown city limits. Because Lewistown holds Montana DLI certification for Building (B) permits only, the electrical interconnection component is issued directly by the Montana DLI Building Codes Bureau in Helena as a Residential Electrical Permit with its 'Alternative Energy Source' add-on fee, not by the City of Lewistown. A structural/racking Building Permit is separately issued by the City for the mounting scope.
Verified 2026-07-20 · Source
When you need this permit
- Electrical interconnection requires a state-issued Residential (or Commercial) Electrical Permit from the Montana DLI Building Codes Bureau — Lewistown does not hold electrical certification, so the City cannot issue this permit itself
- The state Residential Electrical Permit application includes a distinct 'Alternative Energy Source' add-on fee (solar, wind, or hydro), charged in addition to the base electrical work fee selected on the same application (e.g., a service/panel or change-of-service fee)
- Structural/racking work (roof-mount or ground-mount) requires a City of Lewistown Building Permit, reviewed against the City's 2021 IBC/IRC adoption (effective September 1, 2022) via the standard multi-department internal review
- Apply for the electrical component in accordance with Title 50, Chapter 60, Section 604, MCA and ARM 24.301.431
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical (state inspector)
Conduit runs, wire sizing, and disconnect placement before cover, per the 2020 NEC as adopted statewide
- 2
Framing/Structural (city inspector, if a Building Permit applies)
Racking and roof-penetration/structural attachment inspection prior to cover
- 3
Final
Final electrical inspection (state) and final building inspection (city) as applicable
See the full Lewistown inspection guide — scheduling & re-inspection fees →
Tips
- Because Lewistown is Building-certified only, a rooftop solar installation involves TWO separate permitting tracks: a state-issued Electrical Permit (Montana DLI Building Codes Bureau, Helena) for the interconnection, and a city-issued Building Permit (City of Lewistown) for the racking/structural scope.
- The state Electrical Permit's $65 Alternative Energy Source add-on fee is charged ON TOP OF the base electrical work fee you select on the same application — it is not a standalone flat solar fee.
- No published city fee table exists for the structural/racking Building Permit component — call the Building Department, (406) 535-1776, for a current quote before budgeting a project.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lewistown building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Lewistown
Solar PV Permit (Alternative Energy) in other cities
Compare solar pv permit (alternative energy) fees across Montana →
Look up this fee in a different city →