EV Charger / Electric Vehicle Charging Station Permit — Village of Los Ranchos de Albuquerque, New Mexico · Requirements sheet
Verified 2026-07-23 · Source: https://www.bernco.gov/planning/building-services/electrical-2/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / Electric Vehicle Charging Station Permit in Village of Los Ranchos de Albuquerque, New Mexico
The Village of Los Ranchos de Albuquerque does not run its own electrical permitting program -- as with Building Permits on MRGCD Tracts (per Village ordinance Sec. 9.4.2(L)), electrical work is permitted and inspected by Bernalillo County Planning & Development Services, Building Services Division, under the 2020 National Electrical Code and 2020 NM State Electrical Code. Bernalillo County's Electrical page lists dedicated required-inspection types for Solar System and Generator/Alternative Back-up System installations, but has no equivalent dedicated 'EV Charger' or 'EVSE' inspection type or fee line -- a Level 2 home EV charger circuit is inspected under the County's general Rough In and Final electrical inspection categories, with the permit fee charged per Bernalillo County's own Administrative Resolution 25-2009 itemized electrical fee schedule (Table 3-B) -- a per-component charge, not a valuation-based one, and not a single flat dollar figure for 'EV charger' specifically.
Verified 2026-07-23 · Source
When you need this permit
- Electrical work must be performed by a New Mexico-licensed electrical contractor (or a homeowner who has passed the Bernalillo County Homeowners Electrical Exam, $25.00 exam fee) and permitted through Bernalillo County Planning & Development Services
- Reviewed against the 2020 National Electrical Code and 2020 NM State Electrical Code, plus Bernalillo County's enforcement of PNM's serving-utility guidelines
- No dedicated 'EV Charger' or 'EVSE' required-inspection type exists on the County's published Electrical inspections list (unlike 'Solar System' and 'Generator', which do have their own dedicated inspection types) -- an EV charger circuit is inspected under the general 'Rough In' and 'Final' categories
- Permit fee is charged per Bernalillo County Administrative Resolution 25-2009, Table 3-B (Electrical Permit Fees) -- a $23.50 administrative charge applicable to all electrical permit applications, plus itemized per-component charges; no line item is specifically labeled 'EV Charger' or 'EVSE'
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Bernalillo County Code of Ordinances, Ch. Show full citationHide
Bernalillo County Code of Ordinances, Ch. 10 (Buildings and Building Regulations): 'The fee for each permit shall be as set forth by Administrative Resolution with the approval of the Bernalillo County Commission.' The Administrative Resolution referenced by Ch. 10 is Bernalillo County Administrative Resolution 25-2009, 'A Resolution Establishing the Permit Fee Schedules Required by the Uniform Administrative Code' — not linked from bernco.gov/planning/building-services/electrical-2/, the Residential Permit Packet PDF, the Download Permit Tables, or the Public Works Fee Schedule, but published at bernco.gov/planning/building-services/permit-fees-res-25-2009/ (PDF at bernco.gov/planning/wp-content/uploads/sites/58/2021/04/BuildingFees.pdf). Its TABLE 3-B ELECTRICAL PERMIT FEES states verbatim: '1. Administrative charge applicable to all application for permits (EXCEPTION: re-inspection fees)......$23.50 each' and, among itemized components, '7. Outlet: 30 amp or over including panels......$4.00 each' and '8. Residential Fixed Appliances (30 amps or over)............. $4.00 each.' No line item is specifically labeled 'EV Charger' or 'EVSE' -- which of these two $4.00 per-item lines (or both, e.g. outlet plus a sub-panel) governs a given EV charger installation is not independently confirmed; confirm the exact line-item classification and total with Bernalillo County Planning & Development Services, (505) 314-0350, at time of application.Review timeline
Inspection process
- 1
Rough In
Interior and exterior wiring in walls inspected before cover by finished walls, per Bernalillo County's required electrical inspections list
- 2
Final
Installation of all devices and fixtures complete, verified by a Bernalillo County ICC-certified electrical inspector before energizing
Tips
- Electrical permits for Los Ranchos properties go to Bernalillo County Planning & Development Services, not the Village -- the Village does not run its own electrical permitting or inspection program.
- Unlike Solar System and Generator installations, which have their own dedicated required-inspection categories on Bernalillo County's Electrical page, an EV charger circuit has no dedicated inspection type -- expect it to be inspected under the general Rough In and Final categories.
- The County's electrical fee is itemized per component under Administrative Resolution 25-2009 (Table 3-B) -- a $23.50 administrative charge plus $4.00 per applicable outlet/appliance line item -- rather than a single flat 'EV charger' rate, so contact Bernalillo County Planning & Development Services, (505) 314-0350, to confirm which line item(s) apply to your specific installation before applying.
- If your EV charger project also requires a Village-level review (e.g., if paired with a new structure), check with Village Hall (505-344-6582) about whether an additional Village permit (fence, pool, etc.) or Zone Review is triggered separately from the County electrical permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Village of Los Ranchos de Albuquerque building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Village of Los Ranchos de Albuquerque's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Village of Los Ranchos de Albuquerque yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Village of Los Ranchos de Albuquerque lands. Privacy.
Other permits in Village of Los Ranchos de Albuquerque
EV Charger / Electric Vehicle Charging Station Permit in other cities
Compare ev charger / electric vehicle charging station permit fees across New Mexico →
Look up this fee in a different city →
Related guides
Now live
Build your Village of Los Ranchos de Albuquerque project checklist
Describe your project once and get every permit, document, and fee it triggers in Village of Los Ranchos de Albuquerque — in one checklist. Free, for any city and any number of projects.
Get started →