Change of Use Permit (Business License Relocation / New Occupancy Review) in North Logan, Utah

North Logan does not publish a single, distinctly-named 'Change of Use Permit.' A direct fetch of the city's own Business License Department page (northlogancity.gov/business-license) and North Logan Municipal Code (NLMC) Title 8, Regulation Of Business, confirms the functional mechanism instead: NLMC § 8-111 requires 'a separate license must be obtained for each separate place of business,' and each license 'authorize[s] the licensee to engage only in the business licensed thereby at the location or in the manner designated' — meaning a business relocating to a different building/tenant space, or changing its use, must file a new Business License Application (Form B-3) at the new location/use rather than transfer the old one (licenses are non-transferable per NLMC § 8-109 and § 8-413). Form B-3's 'Building Code Compliance Information' section (building use, square footage, fire sprinkler status, number of exits/stories, whether construction/remodeling is occurring) functions as North Logan's use/occupancy screening in place of a separate zoning-compliance certificate. Certain business types require an additional Conditional Use Permit from the Planning Commission per NLMC § 8-505 (child care over 8 children, licensed group child care, beauty/barber shops with more than 3 practitioners, instruction groups exceeding 4 students/class, and all short-term rentals per NLMC § 12C-517), a distinct $350.00 fee per the Master Fee Schedule's Misc. Development Fees section. Where the change of use requires construction to accommodate the new occupancy, that construction is billed under this file's commercial-building-permit or commercial-tenant-improvement-permit entries (including the Zoning Clearance question left open in the latter) — those fees are not duplicated here. No certificate-of-occupancy or change-of-use ordinance provision was found anywhere in NLMC Title 9 (Building And Construction) — a full-text check of that title for 'occupancy'/'occupant' returned only one unrelated match (§ 9-503, utility disconnection notice to a building's 'owner or occupant'). NLMC Title 12 (Land Use) was replaced in its entirety by Ordinance 25-11 and is still being codified online as of this research (2026-07-22), so a distinct Title 12C zoning/use-change provision cannot be ruled out, but is not independently confirmed.

Verified 2026-07-22 · Source

When you need this permit

  • A business relocating to a different building or tenant space in North Logan, or changing its use/occupancy, must file a new Business License Application (Form B-3) for that specific location — per NLMC § 8-111, a separate license is required for each separate place of business, and per NLMC § 8-109/§ 8-413 an existing license cannot be assigned or transferred to a new location or use
  • Form B-3's Building Code Compliance Information section must be completed, disclosing building use, square footage, fire sprinkler status, number of exits/stories, age of building, and whether construction or remodeling is being done
  • A Conditional Use Permit from the Planning Commission is required for specific business types regardless of location change, per NLMC § 8-505: child care for more than 8 children, licensed group child care, beauty/barber shops with more than 3 practitioners, instruction to groups exceeding 4 students per class, and all short-term rental units (per NLMC § 12C-517)
  • If the new use requires construction or remodeling (Form B-3 item 11), the applicant must separately obtain the applicable Building Permit or Commercial Tenant Improvement permit documented elsewhere in this file

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Commercial Business License — Initial (Class 1, up to 90,000 sq. ft.)North Logan Master Fee Schedule, 'Business License Fees' section (current as of 5/5/2026): 'Commercial Class 1: <or= 90,000 sq.ft. — Initial License $150.00 base* (includes up to One-Hour Fire Inspection).' Applies to a new or relocating/use-changing business at a new location, since NLMC § 8-111 treats each location as requiring its own license.
$150.00 base (includes up to a one-hour Fire Inspection)
Commercial Business License — Initial (Class 2, over 90,000 sq. ft. and/or large manufacturer)North Logan Master Fee Schedule, 'Business License Fees' section: 'Commercial Class 2: > 90,000 sq.ft. and/or Large manufacturer — Initial License $200.00 base* (includes up to Three-Hour Fire Inspection).'
$200.00 base (includes up to a three-hour Fire Inspection)
Home Occupation License — Initial (Class 1 / Class 2)North Logan Master Fee Schedule, 'Business License Fees' section. A 'Home Exempt' tier (no public access) requires no license and no fee.
Class 1 (no or very limited client access): $75.00 base; Class 2 (more regular client access): $135.00 base (includes up to a one-hour Fire Inspection)
Conditional Use PermitNorth Logan Master Fee Schedule, 'Development Fees' section, 'Misc. Development Fees' table (fetched 2026-07-22): 'Conditional Use Permit $350.00.' Required only for the specific business types listed in NLMC § 8-505.
$350.00
Zoning ClearanceNorth Logan Master Fee Schedule, 'Development Fees' section, 'Misc. Development Fees' table. Scoped by North Logan's own Land Use Applications page to 'the construction or modification of any permanent structure or permanent improvement' — applicable only where a change of use is accompanied by such construction/modification, not to an interior-only occupancy change with no structural work.
$125.00
Added Fee for Fire Inspection (beyond the bundled amount)North Logan Master Fee Schedule, 'Business License Fees' section, 'Additional Fees': 'Added Fee for Fire Inspection: Add $75.00 per half hour.'
$75.00 per additional half hour
Hazardous Materials FeeNorth Logan Master Fee Schedule, 'Business License Fees' section, 'Additional Fees': 'Hazard Materials Fee: Add $20.00.' Applies if Form B-3's hazardous-materials checkboxes are triggered by the new use.
$20.00

Review timeline

Plan reviewNorth Logan’s published plan-review target
14–21 business days

How long did your Change of Use Permit (Business License Relocation / New Occupancy Review) permit actually take in North Logan?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Inspection (bundled into Business License fee)

    A one-hour (Class 1) or three-hour (Class 2/Home Class 2) Fire Inspection is included in the Initial Business License fee per the North Logan Master Fee Schedule; additional time is billed at $75.00 per half hour.

  2. 2

    Conditional Use Permit Review (Planning Commission)

    Required only for the specific business types listed in NLMC § 8-505; reviewed and approved by the Planning Commission, which meets the Thursday following a City Council meeting per the Community Development Department page.

See the full North Logan inspection guide — scheduling & re-inspection fees →

Tips

  • North Logan has no separate 'Change of Location' or 'Change of Use' fee category like some neighboring cities — a business moving to a new building or tenant space simply files a new Business License Application (Form B-3) for that location, since NLMC § 8-111 requires a distinct license per 'separate place of business' and NLMC § 8-109/§ 8-413 make licenses non-transferable.
  • Check NLMC § 8-505 before assuming no extra review is needed: child care (over 8 children), licensed group child care, beauty/barber shops with more than 3 practitioners, group instruction exceeding 4 students per class, and all short-term rentals require a separate $350.00 Conditional Use Permit from the Planning Commission regardless of whether the business is new or relocating.
  • If the new occupancy requires any construction or remodeling (Form B-3 explicitly asks this), budget for the separate commercial-building-permit or commercial-tenant-improvement-permit process documented elsewhere in this file — the Business License fee alone does not cover that work.
  • North Logan Municipal Code Title 12 (Land Use) was replaced in its entirety by Ordinance 25-11 and remains only partially codified online as of 2026-07-22 — confirm with the Community Development Department, (435) 752-1310 ext. 105, whether a newer Title 12C provision addresses change-of-use zoning review before relying solely on the business-license mechanism described here.

Frequently asked questions

North Logan requires a change of use permit (business license relocation / new occupancy review) for: A business relocating to a different building or tenant space in North Logan, or changing its use/occupancy, must file a new Business License Application (Form B-3) for that specific location — per NLMC § 8-111, a separate license is required for each separate place of business, and per NLMC § 8-109/§ 8-413 an existing license cannot be assigned or transferred to a new location or use; Form B-3's Building Code Compliance Information section must be completed, disclosing building use, square footage, fire sprinkler status, number of exits/stories, age of building, and whether construction or remodeling is being done; A Conditional Use Permit from the Planning Commission is required for specific business types regardless of location change, per NLMC § 8-505: child care for more than 8 children, licensed group child care, beauty/barber shops with more than 3 practitioners, instruction to groups exceeding 4 students per class, and all short-term rental units (per NLMC § 12C-517); If the new use requires construction or remodeling (Form B-3 item 11), the applicant must separately obtain the applicable Building Permit or Commercial Tenant Improvement permit documented elsewhere in this file. If your project isn't listed, confirm with North Logan City Building Department at (435) 752-1310 before starting work.

It depends on the business classification: a Commercial Class 1 business (90,000 sq. ft. or less) pays a $150.00 Initial License fee (includes up to a one-hour Fire Inspection); Commercial Class 2 (over 90,000 sq. ft. or a large manufacturer) pays $200.00 (up to a three-hour Fire Inspection); Home Class 1 pays $75.00 and Home Class 2 pays $135.00. If the specific business type requires a Conditional Use Permit under NLMC § 8-505, add $350.00. If construction is needed to fit out the new use, a separate Building Permit or Commercial Tenant Improvement permit fee also applies, per this file's other permit entries.

North Logan's published plan-review target for a change of use permit (business license relocation / new occupancy review) is 14–21 business days.

You'll need: Business License Application (Form B-3). Depending on your project, North Logan may also ask for: Conditional Use Permit Application; Self-Inspection Worksheet. See the required-documents checklist on this page for details on each.

North Logan requires 2 inspection(s) for a change of use permit (business license relocation / new occupancy review), in order: Fire Inspection (bundled into Business License fee), Conditional Use Permit Review (Planning Commission). Schedule each through North Logan City Building Department ((435) 752-1310).

Apply through North Logan City Building Department at 2525 North 600 East, North Logan, UT 84341. Phone: (435) 752-1310, email: Mary@northlogancity.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.northlogancity.gov/building.

North Logan, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — North Logan Municipal Code § 9-401 adopts 'the building codes, adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(a), the 2024 IBC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here. Because NLMC § 9-401 is a blanket cross-reference to the state's adopted edition rather than a hardcoded year, North Logan's local ordinance tracks the statute automatically — no city ordinance amendment was needed for this transition. North Logan's own Building Codes & Design Criteria page links directly to the State Adopted Codes list rather than publishing a separate local list, and states 'there are no local amendments for North Logan' (live-checked 2026-07-16, unchanged).; 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 statewide transition. Adopted per NLMC § 9-401's blanket adoption of state-adopted building codes.; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized in NLMC Title 9, added here per statute.; 2024 International Plumbing Code (IPC) — NLMC § 9-600/§ 9-701 adopts 'the Uniform Plumbing Code, currently adopted by State of Utah'; per Utah Code § 15A-2-103(1)(d), the 2024 IPC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here (blanket cross-reference tracks the statute automatically).; 2024 International Mechanical Code (IMC) — NLMC § 9-705 adopts the mechanical code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(e), the 2024 IMC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.; 2024 International Fuel Gas Code (IFGC) — NLMC § 9-702 adopts the fuel gas code 'as adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(f), the 2024 IFGC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — NLMC § 9-707 adopts the energy conservation code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(h), the 2024 IECC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.; 2023 National Electrical Code (NEC) — REMAINS CURRENT; NLMC § 9-500/§ 9-501 adopts 'the electrical code, adopted by the State of Utah'; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 statewide transition.; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); not itemized as its own section in NLMC Title 9, added here per statute since North Logan's own materials omit it (covered generally by NLMC § 9-401's blanket building-code adoption).; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not itemized as its own section in NLMC Title 9, added here per statute since North Logan's own materials omit it.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. North Logan's Building Codes & Design Criteria page (northlogancity.gov/building) was live-checked 2026-07-16: it still links generically to the state's 'State Adopted Codes' list rather than itemizing edition years itself, and still states 'there are no local amendments for North Logan' — no page-vs-statute lag was found because the page (like NLMC Title 9's own text) defers entirely to the state's current list rather than asserting specific years.. Local amendments apply — see the North Logan overview page for the full list.

Not as a single named product. North Logan Municipal Code § 8-111 requires a separate Business License for each separate place of business, and § 8-109/§ 8-413 make licenses non-transferable, so a business relocating or changing its use in North Logan files a new Business License Application (Form B-3) for the new location. A full search of NLMC Title 9 (Building And Construction) for 'occupancy'/'occupant' found no dedicated certificate-of-occupancy-for-existing-buildings provision. Certain business types (per NLMC § 8-505) additionally require a $350.00 Conditional Use Permit from the Planning Commission.

Sources & verification

Verified against official sources. Last reviewed 2026-07-22.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Logan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.