Skip to main content
PermitBase

Combined Electrical, Mechanical, Plumbing Permit in North Logan, Utah

Required for standalone electrical, mechanical, or plumbing work in North Logan not part of a new residential building permit. Exempt from the Zoning Clearance requirement and can be applied for directly. Fee is calculated as a percentage of what the corresponding Building Permit Fee would be. EV charger/EVSE installation is electrical work and falls under this combined Electrical, Mechanical, Plumbing Permit; North Logan's Master Fee Schedule does not publish a separate EV-charger fee line item.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical, mechanical, or plumbing work performed independently of new construction
  • Exempt from Zoning Clearance (Step 1) — apply directly for the permit
  • Subject to the adopted 2023 NEC (electrical), 2024 IMC (mechanical), and 2024 IPC (plumbing) per North Logan Municipal Code Title 9

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Combined Electrical, Mechanical, Plumbing Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026). The underlying Building Permit Fee is calculated per the 1997 Uniform Building Code Table No. 3-A valuation table, adjusted annually by CPI, per North Logan Municipal Code § 9-205.
27.5% of the Building Permit Fee

Review timeline

Plan review
Not published — contact the department

How long did your Combined Electrical, Mechanical, Plumbing Permit permit actually take in North Logan?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Trade Inspection (Electrical/Mechanical/Plumbing)

    Scheduled through the CityInspect portal or by phone, (435) 563-6507 ext. 25, per North Logan's official Building Department contact page.

See the full North Logan inspection guide — scheduling & re-inspection fees →

Tips

  • Electrical, GenerLink, Mechanical, Plumbing, and Repair permits are the specific categories exempted from North Logan's Zoning Clearance requirement, per the city's official Building Department page.
  • A PV System Plan Check Worksheet is separately available on North Logan's Building Department page for photovoltaic system installations.
  • EV charger (EVSE) installations do not have a distinct permit type or fee in North Logan — apply for this combined Electrical, Mechanical, Plumbing Permit as you would for any other standalone electrical work.

Frequently asked questions

No. North Logan's official Building Department page lists Electrical, GenerLink, Mechanical, Plumbing, and Repair permits as exempt from the Zoning Clearance (Step 1) requirement — these can be applied for directly through the CityInspect portal.

In North Logan, the published Combined Electrical, Mechanical, Plumbing Permit Fee is: 27.5% of the Building Permit Fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

North Logan does not publish a plan-review timeline for this permit. Contact North Logan City Building Department at (435) 752-1310 for current turnaround.

You'll need: Building Permit Application (CityInspect). See the required-documents checklist on this page for details on each.

North Logan requires 1 inspection(s) for a combined electrical, mechanical, plumbing permit, in order: Trade Inspection (Electrical/Mechanical/Plumbing). Schedule each through North Logan City Building Department ((435) 752-1310).

Apply through North Logan City Building Department at 2525 North 600 East, North Logan, UT 84341. Phone: (435) 752-1310, email: Mary@northlogancity.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.northlogancity.gov/building.

North Logan, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — North Logan Municipal Code § 9-401 adopts 'the building codes, adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(a), the 2024 IBC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here. Because NLMC § 9-401 is a blanket cross-reference to the state's adopted edition rather than a hardcoded year, North Logan's local ordinance tracks the statute automatically — no city ordinance amendment was needed for this transition. North Logan's own Building Codes & Design Criteria page links directly to the State Adopted Codes list rather than publishing a separate local list, and states 'there are no local amendments for North Logan' (live-checked 2026-07-16, unchanged).; 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 statewide transition. Adopted per NLMC § 9-401's blanket adoption of state-adopted building codes.; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized in NLMC Title 9, added here per statute.; 2024 International Plumbing Code (IPC) — NLMC § 9-600/§ 9-701 adopts 'the Uniform Plumbing Code, currently adopted by State of Utah'; per Utah Code § 15A-2-103(1)(d), the 2024 IPC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here (blanket cross-reference tracks the statute automatically).; 2024 International Mechanical Code (IMC) — NLMC § 9-705 adopts the mechanical code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(e), the 2024 IMC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.; 2024 International Fuel Gas Code (IFGC) — NLMC § 9-702 adopts the fuel gas code 'as adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(f), the 2024 IFGC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — NLMC § 9-707 adopts the energy conservation code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(h), the 2024 IECC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.; 2023 National Electrical Code (NEC) — REMAINS CURRENT; NLMC § 9-500/§ 9-501 adopts 'the electrical code, adopted by the State of Utah'; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 statewide transition.; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); not itemized as its own section in NLMC Title 9, added here per statute since North Logan's own materials omit it (covered generally by NLMC § 9-401's blanket building-code adoption).; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not itemized as its own section in NLMC Title 9, added here per statute since North Logan's own materials omit it.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. North Logan's Building Codes & Design Criteria page (northlogancity.gov/building) was live-checked 2026-07-16: it still links generically to the state's 'State Adopted Codes' list rather than itemizing edition years itself, and still states 'there are no local amendments for North Logan' — no page-vs-statute lag was found because the page (like NLMC Title 9's own text) defers entirely to the state's current list rather than asserting specific years.. Local amendments apply — see the North Logan overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Logan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.