Electrical, Mechanical & Plumbing Permit — Cottonwood Heights, Utah · Requirements sheet
Verified 2026-07-13 · Source: https://www.cottonwoodheights.utah.gov/doing-business/fee-schedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electrical, Mechanical & Plumbing Permit in Cottonwood Heights, Utah
Covers standalone or combined electrical, mechanical, and plumbing work. Cottonwood Heights charges each trade at a flat 5% of the base building permit fee when applied for together with the building permit; if applied for separately, the fee instead follows the IBC fee schedule. EV charger/EVSE installation is electrical work and falls under this general Electrical, Mechanical & Plumbing Permit; the city's official Fee Schedule page (live-checked 2026-07-19) publishes no separate EV-specific line item or process.
Verified 2026-07-13 · Source
When you need this permit
- Electrical, mechanical, or plumbing work regulated statewide by the 2024 IPC / 2024 IMC / 2024 IFGC (Utah Code § 15A-2-103(1)(d)/(e)/(f), effective 7/1/2026) and the 2023 NEC (§ 15A-2-103(1)(g), unchanged); the city's own Building Codes and Standards page still lists the 2021 IPC/IMC/IFGC and 2020 NEC as of live-check 2026-07-16, but the statute controls
- Online application via the city's iWorq Building Permit Application portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Scheduled Field Inspections
Requested online via the 'Inspection Requests/Details' portal; numeric-only permit number entry (no dashes). No same-day or weekend inspections.
Tips
- Bundling electrical/mechanical/plumbing work with the main building permit application is cheaper (5% of base fee each) than applying for them separately (full IBC valuation-based schedule) — and only the bundled path is documented as going through the same 7-business-day-target plan review process.
- Cottonwood Heights' Codes and Standards page notes: tinted primer is required on all HVAC PVC joints — a specific local inspection requirement.
- Installing a home or commercial EV charger (EVSE) requires this same Electrical, Mechanical & Plumbing Permit — there is no separate EV-charger permit or fee category published by the city.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cottonwood Heights building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Cottonwood Heights
Electrical, Mechanical & Plumbing Permit in other cities
Compare electrical, mechanical & plumbing permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Cottonwood Heights project checklist
Describe your project once and get every permit, document, and fee it triggers in Cottonwood Heights — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.