Required for new single-family residential construction and residential remodels regulated by the adopted 2021 IRC/IBC suite. Cottonwood Heights uses a single valuation-based fee structure (no separate flat-fee table) administered by its contracted Building Official.

Verified 2026-07-03 · Source

When you need this permit

  • New residential dwelling construction or residential remodel regulated by the adopted 2021 IRC/IBC
  • Online application only, submitted via the city's iWorq-based Building Permit Application portal
  • Building plans uploaded with the application — the city will not accept an application without accompanying plans (oversized plans emailed directly to the permits team)
  • Zoning and setbacks compliance per the city's published Zoning and Setbacks standards

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeCottonwood Heights official Fee Schedule page, 'Community and economic development > Building fees (code title 15)': 'Building permit fee — 100% of the building valuation data table from the most current version of the international building code (IBC) adopted in Utah.'
100% of the building valuation data table from the most current IBC edition adopted in Utah
Plan Review Fee (residential)Cottonwood Heights official Fee Schedule page: 'Plan review fee (residential) — 65% of base building permit.'
65% of base building permit fee

Review timeline

Plan reviewCottonwood Heights’s published plan-review target
Up to 7 business days

How long did your Residential Building Permit (New Dwelling / Remodel) permit actually take in Cottonwood Heights?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Scheduled Field Inspections

    Requested online via the city's 'Inspection Requests/Details' portal (permit number entered without dashes — numeric-only). Next-day inspections must be requested by 3 p.m. the prior business day. The city does not offer same-day or weekend inspections.

Tips

  • Applications are online-only via the city's iWorq portal — no paper/in-person applications accepted.
  • Once payment is submitted, initial processing and distribution to reviewers can take 5 to 7 business days before the 7-business-day (target) / 14-business-day (state-code ceiling) plan review clock effectively starts.
  • No same-day or weekend inspections are offered; next-day inspection requests must be submitted by 3 p.m. the prior business day.
  • The city's contracted Building Official is James Short of Sunrise Engineering (801-550-1837) — Cottonwood Heights does not use an in-house city employee as its Building Official.

Frequently asked questions

Cottonwood Heights requires a residential building permit (new dwelling / remodel) for: New residential dwelling construction or residential remodel regulated by the adopted 2021 IRC/IBC; Online application only, submitted via the city's iWorq-based Building Permit Application portal; Building plans uploaded with the application — the city will not accept an application without accompanying plans (oversized plans emailed directly to the permits team); Zoning and setbacks compliance per the city's published Zoning and Setbacks standards. If your project isn't listed, confirm with Cottonwood Heights Community and Economic Development (CED) — Building Permit Division, staffed by a contracted Building Official (James Short, Sunrise Engineering) at 801-944-7062 before starting work.

In Cottonwood Heights, the published Building Permit Fee is: 100% of the building valuation data table from the most current IBC edition adopted in Utah. Additional published fees: Plan Review Fee (residential) — 65% of base building permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the city's official Building Permit Application Process page, the city 'strives to complete the first plan review within 7 business days,' though high permit volume can extend this. Utah state code allows up to 14 business days per review cycle, with additional time if a special review (e.g. third-party review) is required.

You'll need: Residential Checklist – New Construction; Residential Remodel Checklist. Depending on your project, Cottonwood Heights may also ask for: Owner-Builder Certification / DOPL Owner Builder Form. See the required-documents checklist on this page for details on each.

Cottonwood Heights requires 1 inspection(s) for a residential building permit (new dwelling / remodel), in order: Scheduled Field Inspections. Schedule each through Cottonwood Heights Community and Economic Development (CED) — Building Permit Division, staffed by a contracted Building Official (James Short, Sunrise Engineering) (801-944-7062).

Apply through Cottonwood Heights Community and Economic Development (CED) — Building Permit Division, staffed by a contracted Building Official (James Short, Sunrise Engineering) at 2277 E Bengal Blvd, Cottonwood Heights, UT 84121. Phone: 801-944-7062. Office hours: City Hall regular business hours (specific daily hours not published on the Building Permits or Codes and Standards pages as of the dates verified below); contact 801-944-7060 (codes/standards) or 801-944-7062 (permits) to confirm.. Official information: https://www.cottonwoodheights.utah.gov/city-services/building-permits/.

Cottonwood Heights, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a), superseding the 2021 IBC. Cottonwood Heights' own Building Codes and Standards page, live-checked 2026-07-16, still lists '2021 International Building Code' verbatim — the city's page has NOT been updated to reflect the 7/1/2026 statewide flip. The statute controls regardless of the city page's lag.; 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did NOT change this edition in the 7/1/2026 amendment. Matches the city's Building Codes and Standards page (live-checked 2026-07-16: '2021 International Residential Code').; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized on the city's own Building Codes and Standards page, added here per statute.; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e), superseding the 2021 IMC. The city's Building Codes and Standards page still lists '2021 International Mechanical Code' — live-checked 2026-07-16, confirming lag. The statute controls.; 2024 International Fuel Gas Code (IFGC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(f), superseding the 2021 IFGC. The city's Building Codes and Standards page still lists '2021 International Fuel Gas Code' — live-checked 2026-07-16, confirming lag. The statute controls.; 2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d), superseding the 2021 IPC. The city's Building Codes and Standards page still lists '2021 International Plumbing Code' — live-checked 2026-07-16, confirming lag. The statute controls.; 2023 National Electrical Code (NEC) — statewide-mandatory edition per Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 amendment (the 2023 NEC baseline predates this code cycle). The city's Building Codes and Standards page lists '2020 National Electric Code' — one edition behind the statewide-mandatory floor, confirmed still unchanged via live-check 2026-07-16. Per Utah Code § 15A-1-204 (statewide-mandatory construction code), the 2023 NEC governs regardless of the city's own page.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT as of 7/1/2026 per Utah Code § 15A-2-103(1)(h) (no residential/commercial split under current law), superseding the 2018 IECC. The city's Building Codes and Standards page still lists '2018 international energy conservation code' — live-checked 2026-07-16, confirming lag (this was already one edition behind the pre-7/1/2026 2021 IECC baseline other Salt Lake County cities used, and is now two editions behind current). The statute controls.; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); not listed on the city's own Building Codes and Standards page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not listed on the city's own Building Codes and Standards page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.; Modular Building Institute (MBI) Standards 1200 and 1205 — statewide per Utah Code § 15A-2-103(1)(o); not listed on the city's own Building Codes and Standards page, added here per statute.; 2018 International Fire Code (IFC), with Utah state amendments — per the city's official Building Codes and Standards page (live-checked 2026-07-16, unchanged). NOTE: the IFC is NOT among the codes adopted by Utah Code § 15A-2-103 (Title 15A Chapter 2, State Construction Code) — Utah's Fire Code is separately adopted under Title 15A Chapter 5, State Fire Code Act; left as published by the city, no statutory edition change applies via § 15A-2-103.; 2017 ANSI ICC A117.1 Accessible and Usable Buildings and Facilities (referenced on the codes page as '2017 ANSI ADA CODE') — per the city's official Building Codes and Standards page, live-checked 2026-07-16, unchanged.; 2009 ANSI A117.1 Standard for Accessible and Usable Buildings and Facilities — also separately listed on the same official codes page (both 2017 and 2009 editions appear on the city's current list; reproduced verbatim rather than reconciled, since only the city's own text is authoritative here). Live-checked 2026-07-16, unchanged.; 2015 Uniform Code for the Abatement of Dangerous Buildings — per the city's official Building Codes and Standards page, live-checked 2026-07-16, unchanged.; Cottonwood Heights Code of Ordinances (local amendments to the above, referenced but not separately itemized on the Codes and Standards page) — see localAmendments below.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. The city's Building Codes and Standards page (cottonwoodheights.utah.gov/city-services/building/codes-and-standards) was live-checked 2026-07-16 via real-browser navigation and confirmed still lagging — it verbatim lists 2021 IBC/IMC/IFGC/IPC/IRC, 2020 National Electric Code, and 2018 IECC, and omits IEBC and ISPSC entirely. The statewide statute controls over the city's un-updated page; the prior version of this array presented the city's stale figures as simply 'the city's own page controls' without flagging that the statute itself had moved past them — this entry corrects that.. Local amendments apply — see the Cottonwood Heights overview page for the full list.

Cottonwood Heights contracts its Building Official function to Sunrise Engineering; James Short is listed as the Contracted Building Official (801-550-1837) on the city's official Building Permits staff listing.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cottonwood Heights building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.