Commercial Building Permit in Cottonwood Heights, Utah

Required for new commercial construction in Cottonwood Heights, administered by a contracted Building Official (Sunrise Engineering). The building permit fee is 100% of the IBC building valuation data table — the same method used for residential — and the non-residential plan review fee is 65% of the base building permit fee, matching the residential rate.

Verified 2026-07-19 · Source

When you need this permit

  • New commercial construction, per the city's New Commercial Checklist
  • Design-professional (architect) stamp required for spaces 3,000 sq ft or larger, or for structural changes, per state law
  • Geotechnical report and structural footing/foundation plan
  • Signed site-plan mylar with Engineering/Water/Storm Water sign-off
  • Fire Marshal-approved sprinkler plans where applicable

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 7 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeCottonwood Heights official Fee Schedule page, 'Community and economic development > Building fees (code title 15)': 'Building permit fee — 100% of the building valuation data table from the most current version of the international building code (IBC) adopted in Utah.'
100% of the building valuation data table from the most current IBC edition adopted in Utah
Plan Review Fee (Non-Residential)Cottonwood Heights official Fee Schedule page: 'Plan review fee (non-residential) — 65% of base building permit.' Same rate as the residential plan review fee.
65% of base building permit fee
Electrical, Mechanical, and Plumbing FeesCottonwood Heights official Fee Schedule page: 'Electrical, mechanical and plumbing fees — Each is 5% of base building permit fee when applying with the building permit. If you apply separately, fee follows the IBC schedule.'
5% each of the base building permit fee when applied with the building permit
Zoning Review — Commercial Building PermitCottonwood Heights Fee Schedule, Zoning review section: 'Commercial building permit review — $150' (vs. $75 for residential building permit review).
$150

Review timeline

Plan reviewCottonwood Heights’s published plan-review target
Up to 7 business days

How long did your Commercial Building Permit permit actually take in Cottonwood Heights?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Scheduled Field Inspections

    Requested online via the city's 'Inspection Requests/Details' portal (permit number entered without dashes). Next-day inspections must be requested by 3 p.m. the prior business day; no same-day or weekend inspections.

Tips

  • The city strives to complete the first commercial plan review within 7 business days (Utah state code allows up to 14); the New Commercial Checklist separately states second reviews are completed within 10 business days, with the applicant responsible for the actual staff cost of any subsequent reviews.
  • Non-residential plan review is billed at the same 65% rate as residential in Cottonwood Heights — there is no commercial premium on that line item, but a separate $150 Commercial Building Permit zoning-review fee applies (vs. $75 for residential).
  • New commercial construction requires a geotechnical report, structural footing/foundation plan, and signed site-plan mylar — items the lighter-weight tenant-improvement checklist does not require.

Frequently asked questions

Cottonwood Heights requires a commercial building permit for: New commercial construction, per the city's New Commercial Checklist; Design-professional (architect) stamp required for spaces 3,000 sq ft or larger, or for structural changes, per state law; Geotechnical report and structural footing/foundation plan; Signed site-plan mylar with Engineering/Water/Storm Water sign-off; Fire Marshal-approved sprinkler plans where applicable. If your project isn't listed, confirm with Cottonwood Heights Community and Economic Development (CED) — Building Permit Division, staffed by a contracted Building Official (James Short, Sunrise Engineering) at 801-944-7062 before starting work.

Cottonwood Heights charges $150 for commercial building permit zoning review, compared to $75 for residential building permit review, per the city's official Fee Schedule page.

The city's New Commercial Checklist states second reviews are completed within 10 business days, with the applicant responsible for the actual staff cost of any subsequent reviews — separate from the general first-review target of 7 business days (up to a 14-business-day state-code ceiling) stated on the main Building Permits page.

You'll need: Code Analysis Table; Electrical, Mechanical, and Plumbing Plan Details; ADA-Dimensioned Plans; Wall Sections and Fire-Rated Assembly Details; Geotechnical Report; Structural Footing/Foundation Plan; Signed Site-Plan Mylar (Engineering/Water/Storm Water). Depending on your project, Cottonwood Heights may also ask for: Design Professional Stamp (Architect); Stucco ICC Report; Fire Marshal-Approved Sprinkler Plans. See the required-documents checklist on this page for details on each.

Cottonwood Heights requires 1 inspection(s) for a commercial building permit, in order: Scheduled Field Inspections. Schedule each through Cottonwood Heights Community and Economic Development (CED) — Building Permit Division, staffed by a contracted Building Official (James Short, Sunrise Engineering) (801-944-7062).

Apply through Cottonwood Heights Community and Economic Development (CED) — Building Permit Division, staffed by a contracted Building Official (James Short, Sunrise Engineering) at 2277 E Bengal Blvd, Cottonwood Heights, UT 84121. Phone: 801-944-7062. Office hours: City Hall regular business hours (specific daily hours not published on the Building Permits or Codes and Standards pages as of the dates verified below); contact 801-944-7060 (codes/standards) or 801-944-7062 (permits) to confirm.. Official information: https://www.cottonwoodheights.utah.gov/city-services/building-permits/.

Cottonwood Heights, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a), superseding the 2021 IBC. Cottonwood Heights' own Building Codes and Standards page, live-checked 2026-07-16, still lists '2021 International Building Code' verbatim — the city's page has NOT been updated to reflect the 7/1/2026 statewide flip. The statute controls regardless of the city page's lag.; 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did NOT change this edition in the 7/1/2026 amendment. Matches the city's Building Codes and Standards page (live-checked 2026-07-16: '2021 International Residential Code').; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized on the city's own Building Codes and Standards page, added here per statute.; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e), superseding the 2021 IMC. The city's Building Codes and Standards page still lists '2021 International Mechanical Code' — live-checked 2026-07-16, confirming lag. The statute controls.; 2024 International Fuel Gas Code (IFGC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(f), superseding the 2021 IFGC. The city's Building Codes and Standards page still lists '2021 International Fuel Gas Code' — live-checked 2026-07-16, confirming lag. The statute controls.; 2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d), superseding the 2021 IPC. The city's Building Codes and Standards page still lists '2021 International Plumbing Code' — live-checked 2026-07-16, confirming lag. The statute controls.; 2023 National Electrical Code (NEC) — statewide-mandatory edition per Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 amendment (the 2023 NEC baseline predates this code cycle). The city's Building Codes and Standards page lists '2020 National Electric Code' — one edition behind the statewide-mandatory floor, confirmed still unchanged via live-check 2026-07-16. Per Utah Code § 15A-1-204 (statewide-mandatory construction code), the 2023 NEC governs regardless of the city's own page.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT as of 7/1/2026 per Utah Code § 15A-2-103(1)(h) (no residential/commercial split under current law), superseding the 2018 IECC. The city's Building Codes and Standards page still lists '2018 international energy conservation code' — live-checked 2026-07-16, confirming lag (this was already one edition behind the pre-7/1/2026 2021 IECC baseline other Salt Lake County cities used, and is now two editions behind current). The statute controls.; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); not listed on the city's own Building Codes and Standards page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not listed on the city's own Building Codes and Standards page (live-checked 2026-07-16), added here per statute since the city's own materials omit it entirely.; Modular Building Institute (MBI) Standards 1200 and 1205 — statewide per Utah Code § 15A-2-103(1)(o); not listed on the city's own Building Codes and Standards page, added here per statute.; 2018 International Fire Code (IFC), with Utah state amendments — per the city's official Building Codes and Standards page (live-checked 2026-07-16, unchanged). NOTE: the IFC is NOT among the codes adopted by Utah Code § 15A-2-103 (Title 15A Chapter 2, State Construction Code) — Utah's Fire Code is separately adopted under Title 15A Chapter 5, State Fire Code Act; left as published by the city, no statutory edition change applies via § 15A-2-103.; 2017 ANSI ICC A117.1 Accessible and Usable Buildings and Facilities (referenced on the codes page as '2017 ANSI ADA CODE') — per the city's official Building Codes and Standards page, live-checked 2026-07-16, unchanged.; 2009 ANSI A117.1 Standard for Accessible and Usable Buildings and Facilities — also separately listed on the same official codes page (both 2017 and 2009 editions appear on the city's current list; reproduced verbatim rather than reconciled, since only the city's own text is authoritative here). Live-checked 2026-07-16, unchanged.; 2015 Uniform Code for the Abatement of Dangerous Buildings — per the city's official Building Codes and Standards page, live-checked 2026-07-16, unchanged.; Cottonwood Heights Code of Ordinances (local amendments to the above, referenced but not separately itemized on the Codes and Standards page) — see localAmendments below.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. The city's Building Codes and Standards page (cottonwoodheights.utah.gov/city-services/building/codes-and-standards) was live-checked 2026-07-16 via real-browser navigation and confirmed still lagging — it verbatim lists 2021 IBC/IMC/IFGC/IPC/IRC, 2020 National Electric Code, and 2018 IECC, and omits IEBC and ISPSC entirely. The statewide statute controls over the city's un-updated page; the prior version of this array presented the city's stale figures as simply 'the city's own page controls' without flagging that the statute itself had moved past them — this entry corrects that.. Local amendments apply — see the Cottonwood Heights overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cottonwood Heights building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter