Skip to main content
PermitBase

Residential Building Permit in North Logan, Utah

Required for new single-family residential construction and any structure over 200 sq ft in North Logan. Must be preceded by a Zoning Clearance (Step 1) before the Building Permit (Step 2) can be requested. Fee is valuation-based under the 1997 Uniform Building Code Table No. 3-A, adjusted annually by CPI, per North Logan Municipal Code § 9-205 and the city's Master Fee Schedule.

Verified 2026-07-08 · Source

When you need this permit

  • New single-family residential construction, or any structure over 200 sq. ft.
  • Zoning Clearance (Step 1) must be obtained first via the CivicReview portal before a Building Permit application can be submitted — applies to primary structures, accessory structures, agricultural structures, signs, fences, pools, or retaining walls over 3 feet in height
  • Written application accompanied by 2 sets of plans and specifications stating the specific nature of construction, per NLMC § 9-203
  • Soils Hazard Mitigation Plan required if the site's NRCS soils rating is 'very limited,' per NLMC § 9-206
  • Concrete inspection required for curb, gutter, and sidewalk work, with at least 24-hour advance notice

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026), citing North Logan Municipal Code § 9-205: 'The Treasurer shall collect a fee for the Building Permit from the applicant in an amount in accordance with Table No. 3-A of the Uniform Building Code.' A down payment is due at application: Single Family Home $50; permits where the total fee is likely to be less than $100.00, $0 down payment.
As established in the 1997 Uniform Building Code (Table No. 3-A), adjusted annually by the CPI
Combined Electrical, Mechanical, Plumbing Permit FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section (current as of 5/5/2026).
27.5% of the Building Permit Fee
Road Impact Fee (Single Family Detached)North Logan Master Fee Schedule, 'Building Permit Fees' section — Road Impact Fee table, Residential (per housing unit), citing the North Logan Impact Fee Analysis report dated June 25, 2024.
$2,432 per housing unit
Water Impact Fee (3/4-inch meter, standard residential)North Logan Master Fee Schedule, 'Building Permit Fees' section — Water Impact Fee table by meter size.
$4,841 per meter
Residential Sewer Impact Fee (Single Family Residential)North Logan Master Fee Schedule, 'Building Permit Fees' section — Residential Sewer Impact Fee table, varies by service area.
$6,697 (North Service Area) or $4,039 (South Service Area)
Parks & Trails Impact Fee (Residential)North Logan Master Fee Schedule, 'Building Permit Fees' section.
$5,315 per household/housing unit
Logan City Imposed Wastewater Treatment Impact Fee (LCIWTIF) — Single Family UnitNorth Logan Master Fee Schedule, 'Building Permit Fees' section, per Resolution 25-02 (2/19/2025); collected by North Logan and remitted per agreement with Logan City for wastewater treatment capacity.
$2,433.00 per unit (1 ERU multiplier)
Water Meter FeeNorth Logan Master Fee Schedule, 'Building Permit Fees' section; cost verified by the Public Works Department.
Direct market cost of meter and supplies, plus $60.00 installation fee

Review timeline

Plan reviewNorth Logan’s published plan-review target
17–17 business days

How long did your Residential Building Permit permit actually take in North Logan?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Site/Foundation Inspections

    Standard trade inspections administered by the Building Official; inspection scheduling contact (435) 563-6507 ext. 25, per North Logan's official Building Department contact page.

  2. 2

    Concrete Inspection (Curb, Gutter, Sidewalk)

    Required on all issued building permits; contact Ryan Vanweerd, (435) 752-1310, at least 24 hours before pouring concrete, per North Logan's official Building Department page.

  3. 3

    Framing, Electrical, Mechanical, Plumbing

    Trade inspections scheduled through the CityInspect portal or by phone, (435) 563-6507 ext. 25.

  4. 4

    Final Inspection

    Final inspection required for Certificate of Occupancy issuance; scheduled through the CityInspect portal or Building Official contact.

See the full North Logan inspection guide — scheduling & re-inspection fees →

Tips

  • North Logan uses a strict two-step process: Zoning Clearance MUST be granted before a Building Permit application can even be submitted — apply for Zoning Clearance via the CivicReview portal (app.civicreview.com) first, then upload the approval letter to the CityInspect portal (nlogan.cityinspect.com) for the Building Permit.
  • North Logan's Chief Building Official, Darrin Hancey, also serves as Hyde Park City's Chief Building Official — both cities share the same phone number, (435) 563-6507, and Hancey's email is darrin.h@hpcutah.gov. Despite this shared staffing arrangement, North Logan issues its own permits independently through its own CityInspect portal and does not route permits through Hyde Park or Cache County — Cache County's own Building Department confirms it does not issue permits for incorporated cities including North Logan.
  • Electrical, GenerLink, Mechanical, Plumbing, and Repair permits are exempt from the Zoning Clearance requirement and can be applied for directly.
  • A separate Encroachment Permit (via CivicReview) is required for any work within the public right-of-way.
  • North Logan requires 24-hour advance notice before any concrete pour for curb, gutter, or sidewalk work.

Frequently asked questions

North Logan requires a residential building permit for: New single-family residential construction, or any structure over 200 sq. ft.; Zoning Clearance (Step 1) must be obtained first via the CivicReview portal before a Building Permit application can be submitted — applies to primary structures, accessory structures, agricultural structures, signs, fences, pools, or retaining walls over 3 feet in height; Written application accompanied by 2 sets of plans and specifications stating the specific nature of construction, per NLMC § 9-203; Soils Hazard Mitigation Plan required if the site's NRCS soils rating is 'very limited,' per NLMC § 9-206; Concrete inspection required for curb, gutter, and sidewalk work, with at least 24-hour advance notice. If your project isn't listed, confirm with North Logan City Building Department at (435) 752-1310 before starting work.

Per North Logan Municipal Code § 9-205 and the city's Master Fee Schedule, the Building Permit fee is valuation-based under the 1997 Uniform Building Code Table No. 3-A, adjusted annually by CPI. In addition to the base permit fee, a Combined Electrical/Mechanical/Plumbing fee of 27.5% of the Building Permit Fee applies, plus impact fees for roads ($2,432 for a single-family detached unit), water ($4,841 for a standard 3/4-inch meter), sewer ($6,697 or $4,039 depending on service area), parks & trails ($5,315), and the Logan City-imposed wastewater treatment impact fee ($2,433 per unit).

North Logan does not publish its own plan-review turnaround time. Under Utah Code § 10-20-909, North Logan must screen the application for completeness within 3 business days, then complete the plan review of a one- or two-family dwelling within 14 business days after the screening period ends — a statutory ceiling of 17 business days total.

You'll need: Zoning Clearance Application; Building Permit Application (CityInspect); 2 Sets of Plans and Specifications. Depending on your project, North Logan may also ask for: Owner/Builder Certification Form. See the required-documents checklist on this page for details on each.

North Logan requires 4 inspection(s) for a residential building permit, in order: Site/Foundation Inspections, Concrete Inspection (Curb, Gutter, Sidewalk), Framing, Electrical, Mechanical, Plumbing, Final Inspection. Schedule each through North Logan City Building Department ((435) 752-1310).

Apply through North Logan City Building Department at 2525 North 600 East, North Logan, UT 84341. Phone: (435) 752-1310, email: Mary@northlogancity.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.northlogancity.gov/building.

North Logan, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — North Logan Municipal Code § 9-401 adopts 'the building codes, adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(a), the 2024 IBC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here. Because NLMC § 9-401 is a blanket cross-reference to the state's adopted edition rather than a hardcoded year, North Logan's local ordinance tracks the statute automatically — no city ordinance amendment was needed for this transition. North Logan's own Building Codes & Design Criteria page links directly to the State Adopted Codes list rather than publishing a separate local list, and states 'there are no local amendments for North Logan' (live-checked 2026-07-16, unchanged).; 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 statewide transition. Adopted per NLMC § 9-401's blanket adoption of state-adopted building codes.; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized in NLMC Title 9, added here per statute.; 2024 International Plumbing Code (IPC) — NLMC § 9-600/§ 9-701 adopts 'the Uniform Plumbing Code, currently adopted by State of Utah'; per Utah Code § 15A-2-103(1)(d), the 2024 IPC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here (blanket cross-reference tracks the statute automatically).; 2024 International Mechanical Code (IMC) — NLMC § 9-705 adopts the mechanical code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(e), the 2024 IMC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.; 2024 International Fuel Gas Code (IFGC) — NLMC § 9-702 adopts the fuel gas code 'as adopted by the State of Utah'; per Utah Code § 15A-2-103(1)(f), the 2024 IFGC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — NLMC § 9-707 adopts the energy conservation code 'as adopted by State of Utah'; per Utah Code § 15A-2-103(1)(h), the 2024 IECC is CURRENT statewide as of 7/1/2026, superseding the 2021 edition previously listed here.; 2023 National Electrical Code (NEC) — REMAINS CURRENT; NLMC § 9-500/§ 9-501 adopts 'the electrical code, adopted by the State of Utah'; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 statewide transition.; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); not itemized as its own section in NLMC Title 9, added here per statute since North Logan's own materials omit it (covered generally by NLMC § 9-401's blanket building-code adoption).; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not itemized as its own section in NLMC Title 9, added here per statute since North Logan's own materials omit it.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. North Logan's Building Codes & Design Criteria page (northlogancity.gov/building) was live-checked 2026-07-16: it still links generically to the state's 'State Adopted Codes' list rather than itemizing edition years itself, and still states 'there are no local amendments for North Logan' — no page-vs-statute lag was found because the page (like NLMC Title 9's own text) defers entirely to the state's current list rather than asserting specific years.. Local amendments apply — see the North Logan overview page for the full list.

Yes. North Logan requires a two-step process: Step 1 is a Zoning Clearance (required for primary structures, accessory structures, agricultural structures, signs, fences, pools, or retaining walls over 3 feet), applied for via the CivicReview portal. Only after Zoning Clearance is granted can the Step 2 Building Permit be requested via the CityInspect portal — required for any structure over 200 sq ft.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Logan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.