Conditional Use Permit — Business Occupancy in Price, Utah

Unlike the Carbon County-administered building permit process (which folds a 'change of occupancy' into its generic building-permit definition with no separate fee), Price City's own Planning and Zoning Permit Fee Schedule publishes a genuinely distinct, separately-priced permit category specifically for occupying an existing building with a business use: the 'Conditional Use Permit — Business Occupancy' track, priced separately from the City's 'Conditional Use Permit — Development' track used for new construction/site development. This is the real change-of-use mechanism in Price: when a business (a new tenant, or an existing tenant changing its use) occupies a building, Price City Community Development Services reviews and prices that occupancy separately from any building-permit work, and ties it into the City's Business License process.

Verified 2026-07-20 · Source

When you need this permit

  • A business occupying an existing building within Price City limits, where the proposed use requires a Conditional Use Permit under the zoning ordinance -- reviewed by Community Development Services (Room 201, 435-636-3184)
  • Completion of the Price City Business License application process (185 E. Main, Room 202) alongside or before the Conditional Use Permit, since the Business License guide states a business will be 'notified by Community Development Services' if a conditional use permit is required
  • Passed building and/or fire inspection where required -- the Business License guide states 'all commercial businesses require an inspection'
  • If the business is relocating from one Price City location to another, the same Business Occupancy review applies again: 'This may require a new building and/or fire inspection. A new Conditional Use Permit may also be required.'

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Conditional Use Permit — Business Occupancy, Concept Approval
Price City Planning and Zoning Permit Fee Schedule, as adopted, effective 1-1-2026 (priceutah.gov/uploads/1/1/9/7/119716550/2026_planning_and_zoning_permit_fee_schedule.pdf): 'Conditional Use Permit… Show full citationPrice City Planning and Zoning Permit Fee Schedule, as adopted, effective 1-1-2026 (priceutah.gov/uploads/1/1/9/7/119716550/2026_planning_and_zoning_permit_fee_schedule.pdf): 'Conditional Use Permit ($150 total fee through final) -- Business Occupancy... A. Concept Approval $75.00.' The PDF's columns misalign when copy-pasted, so read the figures from the page as published.
75.00 dollars
Conditional Use Permit — Business Occupancy, Preliminary and Final Approval
Same source, table row 'B. Preliminary and Final Approval $75.00' -- combined with the Concept Approval fee, this totals 150.00 dollars through final approval, exactly as labeled in the fee… Show full citationSame source, table row 'B. Preliminary and Final Approval $75.00' -- combined with the Concept Approval fee, this totals 150.00 dollars through final approval, exactly as labeled in the fee schedule's own '$150 total fee through final' heading for the Business Occupancy track. This is a materially different (lower) fee than the City's separate 'Conditional Use Permit -- Development' track, which totals 250.00 dollars through final ($100 Concept + $150 Preliminary/Final).
75.00 dollars
Zoning Verification LetterSame fee schedule: 'Zoning Verification*... Normal Processing -- 1 week $100.00' and 'Expedited: within 2 business days or less... $100.00 additional fee + fee above = $200.00.'
100.00 dollars normal processing (1 week); 200.00 dollars total for expedited processing (2 business days or less)
Commercial Business License Fee (annual, separate from the CUP)
Price City Business License Information guide (priceutah.gov/uploads/1/1/9/7/119716550/-_business_license_info_-_how_to_guide_-.pdf): 'The business license fee for a commercial location is $100.00… Show full citationPrice City Business License Information guide (priceutah.gov/uploads/1/1/9/7/119716550/-_business_license_info_-_how_to_guide_-.pdf): 'The business license fee for a commercial location is $100.00 per calendar year and the Conditional Use Permit fee is $100.00 (varies).' Note this guide's own CUP figure (100.00 dollars, described as approximate/'varies') is superseded here by the more precise, currently-effective Planning and Zoning Permit Fee Schedule figure of 150.00 dollars total for the Business Occupancy CUP track.
100.00 dollars per calendar year

Review timeline

Plan reviewPrice’s published plan-review target
7–14 business days

How long did your Conditional Use Permit — Business Occupancy permit actually take in Price?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building and/or Fire Inspection

    Required for all commercial businesses per the Business License Information guide; scheduled at the time of application submission at 185 E. Main, Room 202.

See the full Price inspection guide — scheduling & re-inspection fees →

Tips

  • Price City's own Conditional Use Permit fee schedule (effective 1-1-2026) splits CUPs into two distinct tracks with different total prices: 'Development' (250.00 dollars total through final) and 'Business Occupancy' (150.00 dollars total through final) -- confirm which track applies; a change-of-use / new-tenant scenario should use the cheaper Business Occupancy track, not the Development track.
  • Carbon County's own Building & Planning Department -- which handles Price City's actual building permits -- has NO published fee or process specifically for change of use or certificate of occupancy; its Commercial and Industrial Structures Packet (carbon.utah.gov) contains zero mentions of 'occupancy' or 'change of use.' The real change-of-use mechanism in Price City runs through the City's OWN Planning and Zoning office and Business License process, not through the County building department.
  • If your business relocates from one address to another within Price City, expect to repeat this same Business Occupancy review -- the City's Business License guide states a move 'may require a new building and/or fire inspection' and 'a new Conditional Use Permit may also be required.'

Frequently asked questions

Price requires a conditional use permit — business occupancy for: A business occupying an existing building within Price City limits, where the proposed use requires a Conditional Use Permit under the zoning ordinance -- reviewed by Community Development Services (Room 201, 435-636-3184); Completion of the Price City Business License application process (185 E. Main, Room 202) alongside or before the Conditional Use Permit, since the Business License guide states a business will be 'notified by Community Development Services' if a conditional use permit is required; Passed building and/or fire inspection where required -- the Business License guide states 'all commercial businesses require an inspection'; If the business is relocating from one Price City location to another, the same Business Occupancy review applies again: 'This may require a new building and/or fire inspection. A new Conditional Use Permit may also be required.'. If your project isn't listed, confirm with Carbon County Building & Planning Department (Building Division) — serves Price City; Price City itself has NO independent building-permit function at (435) 636-3260 (Building Division main line / Administrative Assistant); (435) 636-3261 (Director of Building & Planning) before starting work.

In Price, the published Conditional Use Permit — Business Occupancy, Concept Approval is: 75.00 dollars. Additional published fees: Conditional Use Permit — Business Occupancy, Preliminary and Final Approval — 75.00 dollars; Zoning Verification Letter — 100.00 dollars normal processing (1 week); 200.00 dollars total for expedited processing (2 business days or less); Commercial Business License Fee (annual, separate from the CUP) — 100.00 dollars per calendar year. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

A straightforward business license with no required inspection can be mailed in approximately 7-10 days. The Business License guide states the full process, including any required inspection, 'can take up to two weeks' -- longer if a Conditional Use Permit's Concept-then-Preliminary/Final stages are required, since no specific day-count is published for those stages.

You'll need: Conditional Use Permit Application — Business Occupancy track; Price City Business License Application. Depending on your project, Price may also ask for: Zoning Verification Letter (optional but commonly used). See the required-documents checklist on this page for details on each.

Price requires 1 inspection(s) for a conditional use permit — business occupancy, in order: Building and/or Fire Inspection. Schedule each through Carbon County Building & Planning Department (Building Division) — serves Price City; Price City itself has NO independent building-permit function ((435) 636-3260 (Building Division main line / Administrative Assistant); (435) 636-3261 (Director of Building & Planning)).

Apply through Carbon County Building & Planning Department (Building Division) — serves Price City; Price City itself has NO independent building-permit function at 751 East 100 North, Suite 2600, Price, UT 84501. Phone: (435) 636-3260 (Building Division main line / Administrative Assistant); (435) 636-3261 (Director of Building & Planning), email: planning@carbon.utah.gov. Office hours: Mon–Thu 8:00 AM – 5:00 PM, Fri 8:00 AM – 3:00 PM (Building Department-specific hours per the county's own Building Permits FAQ; distinct from general County Administration hours of Mon–Fri 8:00 AM – 5:00 PM). Official information: https://www.carbon.utah.gov/service/building-permits/.

Price, Utah has adopted: GOVERNING LAW: Utah Code § 15A-2-103 (le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), version effective 7/1/2026 (amended by Ch. 47, 2026 General Session), sets the statewide-mandatory construction code suite — Utah Code § 15A-1-204 binds 'the state and each political subdivision,' which includes Carbon County as the compliance agency serving Price City (Price has no independent building-permit authority; see localAmendments). Carbon County's own Building Permits page ('What codes are enforced?' FAQ) still displays the pre-7/1/2026 edition list; State law governs regardless of the page's lag; each line below states current law first, then the county's as-published (stale or omitted) text.; 2024 International Building Code (IBC), including Appendix J — per Utah Code § 15A-2-103(1)(a), effective 7/1/2026. Carbon County's Building Permits FAQ still lists '2021 International Building Code, including Appendix J' (live re-check 2026-07-16).; 2021 International Residential Code (IRC), including Appendix Q — per Utah Code § 15A-2-103(1)(b)/(c); this edition did NOT change in the 7/1/2026 flip. Matches Carbon County's FAQ, which lists '2021 International Residential Code, 2021-Appendix Q of 2021 IRC' (live re-check 2026-07-16).; 2024 International Plumbing Code (IPC) — per Utah Code § 15A-2-103(1)(d), effective 7/1/2026. Carbon County's FAQ still lists '2021 IPC' (live re-check 2026-07-16).; 2024 International Mechanical Code (IMC) — per Utah Code § 15A-2-103(1)(e), effective 7/1/2026. Carbon County's FAQ still lists '2021 IMC' (live re-check 2026-07-16).; 2024 International Fuel Gas Code (IFGC) — per Utah Code § 15A-2-103(1)(f), effective 7/1/2026. Carbon County's FAQ still lists '2021 IFGC' (live re-check 2026-07-16).; 2023 National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g); this edition did NOT change in the 7/1/2026 flip. Carbon County's FAQ still lists '2020 NEC' (live re-check 2026-07-16) — this is a PRE-EXISTING discrepancy that predates and is unrelated to the 2026-07-01 code-cycle flip (the 2023 NEC has been state law since before this project's original 2026-07-08 review); reported here as-published rather than corrected.; 2024 International Energy Conservation Code (IECC), one statewide edition (no residential/commercial split) — per Utah Code § 15A-2-103(1)(h), effective 7/1/2026. Not mentioned anywhere on Carbon County's Building Permits FAQ, Building Department page, or Building Information/Resources page as of live re-check 2026-07-16; added here as a statute-sourced omission (applies statewide regardless of county publication), not fabricated.; 2024 International Existing Building Code (IEBC) — per Utah Code § 15A-2-103(1)(i), effective 7/1/2026. Not mentioned on any Carbon County page reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — per Utah Code § 15A-2-103(1)(n), effective 7/1/2026. Not mentioned on any Carbon County page reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Modular Building Institute (MBI) Standards 1200 and 1205 — per Utah Code § 15A-2-103(1)(o), statewide-mandated for modular units. Not mentioned on any Carbon County page reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; No International Fire Code (IFC) entry: § 15A-2-103 does not adopt the IFC — it is separately governed under Title 15A Chapter 5, outside the scope of this section. Carbon County's FAQ does not list an IFC edition either, so there is no mis-citation to correct here.. Local amendments apply — see the Price overview page for the full list.

Yes. Price City's Planning and Zoning Permit Fee Schedule (effective 1-1-2026) publishes a distinct 'Conditional Use Permit -- Business Occupancy' track, totaling 150.00 dollars through final approval (75.00 dollars Concept Approval plus 75.00 dollars Preliminary and Final Approval) -- separately priced from the 250.00-dollar 'Development' CUP track used for new construction. This runs alongside the City's Business License process (100.00 dollars/year for a commercial location), administered by Community Development Services (435-636-3184), not through Carbon County's building department.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Price building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Price's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Price yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Price lands. Privacy.