EV Charger / EVSE Permit in Price, Utah

EV charger/EVSE installation for property within Price City limits falls under Carbon County's standard building permit process (Carbon County Building & Planning Department issues all building permits for Price City — Price City has no independent building-permit function; see the residential-building-permit entry's department/localAmendments notes). Carbon County's official Building Permits page (carbon.utah.gov/service/building-permits/) lists 'Altering electrical, gas, or plumbing systems' among the reasons a permit is required under its 'When do I need a permit?' FAQ, with no EV-charger-specific or electric-vehicle mention found anywhere on carbon.utah.gov as of a direct check on 2026-07-20. No dollar-amount valuation-based fee table (for building permits generally, let alone EV/electrical specifically) could be located on Carbon County's official website after an exhaustive search — matching the same fee-table gap already documented for Price's other Carbon-County-administered permit types in this dataset. Per the zero-tolerance data policy, this entry is left with fees:[] and confidence:'partial' rather than fabricated or borrowed from a non-Carbon-County source.

Reviewed 2026-07-20 · Source

When you need this permit

  • Any owner or owner's authorized agent who intends to erect/install/enlarge/alter/repair/remove/convert/replace an electrical system (including EV charger/EVSE circuits) must first apply to Carbon County's Building Department and obtain the required permit
  • Proof of city zoning approval required for property within Price City limits, in addition to the county building/electrical permit — per both Price City's own Planning & Zoning page and Carbon County's Building Permits FAQ
  • New dedicated electrical circuit and/or panel capacity to serve the charger, regulated by the statewide-adopted 2023 National Electrical Code (Utah Code § 15A-2-103(1)(g))

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan reviewPrice’s published plan-review target
0–14 business days

How long did your EV Charger / EVSE Permit permit actually take in Price?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Utility Connections

    Electrical inspection of the new EV charger circuit and panel work; power connection verification, per Carbon County's standard inspection sequence.

  2. 2

    Final Inspection

    Call at least 24-72 hours in advance to schedule inspections at (435) 636-3260.

See the full Price inspection guide — scheduling & re-inspection fees →

Tips

  • Price City has no building-permit process of its own — EV charger/EVSE permits for property within Price City limits are applied for at Carbon County's Building & Planning Office (751 E 100 N, Suite 2600, Price, UT 84501) or online at carbon.utah.gov, not at Price City Hall.
  • Carbon County's Building Permits page lists 'Altering electrical, gas, or plumbing systems' as a reason a permit is required, with no distinct EV-charger or electric-vehicle category found anywhere on the county's site.
  • Carbon County could not be confirmed to publish a dollar-amount valuation-based fee table for building or electrical permits anywhere on its official website — contact the Building Department directly at (435) 636-3260 or planning@carbon.utah.gov for a current fee quote before applying. Re-chased again 2026-07-23 (Wayback CDX sweep, Business License page/Ordinance 281 trace, Utah PMN full-text search API) with no new figure found — see this jurisdiction's residential-building-permit localAmendments for the full 2026-07-23 chase log; this is a county-wide gap, not specific to EV charger permits.
  • Property within Price City limits still needs a separate city zoning sign-off from Price City's own Planning & Zoning office (435-636-3184) before or alongside the county electrical permit.

Frequently asked questions

Price requires an ev charger / evse permit for: Any owner or owner's authorized agent who intends to erect/install/enlarge/alter/repair/remove/convert/replace an electrical system (including EV charger/EVSE circuits) must first apply to Carbon County's Building Department and obtain the required permit; Proof of city zoning approval required for property within Price City limits, in addition to the county building/electrical permit — per both Price City's own Planning & Zoning page and Carbon County's Building Permits FAQ; New dedicated electrical circuit and/or panel capacity to serve the charger, regulated by the statewide-adopted 2023 National Electrical Code (Utah Code § 15A-2-103(1)(g)). If your project isn't listed, confirm with Carbon County Building & Planning Department (Building Division) — serves Price City; Price City itself has NO independent building-permit function at (435) 636-3260 (Building Division main line / Administrative Assistant); (435) 636-3261 (Director of Building & Planning) before starting work.

Price's published plan-review target for an ev charger / evse permit is 0–14 business days.

You'll need: Building Permit Application; Proof of City Zoning Approval. See the required-documents checklist on this page for details on each.

Price requires 2 inspection(s) for an ev charger / evse permit, in order: Utility Connections, Final Inspection. Schedule each through Carbon County Building & Planning Department (Building Division) — serves Price City; Price City itself has NO independent building-permit function ((435) 636-3260 (Building Division main line / Administrative Assistant); (435) 636-3261 (Director of Building & Planning)).

Apply through Carbon County Building & Planning Department (Building Division) — serves Price City; Price City itself has NO independent building-permit function at 751 East 100 North, Suite 2600, Price, UT 84501. Phone: (435) 636-3260 (Building Division main line / Administrative Assistant); (435) 636-3261 (Director of Building & Planning), email: planning@carbon.utah.gov. Office hours: Mon–Thu 8:00 AM – 5:00 PM, Fri 8:00 AM – 3:00 PM (Building Department-specific hours per the county's own Building Permits FAQ; distinct from general County Administration hours of Mon–Fri 8:00 AM – 5:00 PM). Official information: https://www.carbon.utah.gov/service/building-permits/.

Price, Utah has adopted: GOVERNING LAW: Utah Code § 15A-2-103 (le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), version effective 7/1/2026 (amended by Ch. 47, 2026 General Session), sets the statewide-mandatory construction code suite — Utah Code § 15A-1-204 binds 'the state and each political subdivision,' which includes Carbon County as the compliance agency serving Price City (Price has no independent building-permit authority; see localAmendments). Carbon County's own Building Permits page ('What codes are enforced?' FAQ) still displays the pre-7/1/2026 edition list; re-checked live 2026-07-16, page text is byte-identical to the 2026-07-08 fetch ('2021 International Building Code, including Appendix J 2021 International Residential Code 2021-Appendix Q of 2021 IRC 2021 IPC, 2021 IMC, 2021 IFGC, 2020 NEC'). State law governs regardless of the page's lag; each line below states current law first, then the county's as-published (stale or omitted) text.; 2024 International Building Code (IBC), including Appendix J — per Utah Code § 15A-2-103(1)(a), effective 7/1/2026. Carbon County's Building Permits FAQ still lists '2021 International Building Code, including Appendix J' (live re-check 2026-07-16).; 2021 International Residential Code (IRC), including Appendix Q — per Utah Code § 15A-2-103(1)(b)/(c); this edition did NOT change in the 7/1/2026 flip. Matches Carbon County's FAQ, which lists '2021 International Residential Code, 2021-Appendix Q of 2021 IRC' (live re-check 2026-07-16).; 2024 International Plumbing Code (IPC) — per Utah Code § 15A-2-103(1)(d), effective 7/1/2026. Carbon County's FAQ still lists '2021 IPC' (live re-check 2026-07-16).; 2024 International Mechanical Code (IMC) — per Utah Code § 15A-2-103(1)(e), effective 7/1/2026. Carbon County's FAQ still lists '2021 IMC' (live re-check 2026-07-16).; 2024 International Fuel Gas Code (IFGC) — per Utah Code § 15A-2-103(1)(f), effective 7/1/2026. Carbon County's FAQ still lists '2021 IFGC' (live re-check 2026-07-16).; 2023 National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g); this edition did NOT change in the 7/1/2026 flip. Carbon County's FAQ still lists '2020 NEC' (live re-check 2026-07-16) — this is a PRE-EXISTING discrepancy that predates and is unrelated to the 2026-07-01 code-cycle flip (the 2023 NEC has been state law since before this project's original 2026-07-08 review); reported here as-published rather than corrected.; 2024 International Energy Conservation Code (IECC), one statewide edition (no residential/commercial split) — per Utah Code § 15A-2-103(1)(h), effective 7/1/2026. Not mentioned anywhere on Carbon County's Building Permits FAQ, Building Department page, or Building Information/Resources page as of live re-check 2026-07-16; added here as a statute-sourced omission (applies statewide regardless of county publication), not fabricated.; 2024 International Existing Building Code (IEBC) — per Utah Code § 15A-2-103(1)(i), effective 7/1/2026. Not mentioned on any Carbon County page reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — per Utah Code § 15A-2-103(1)(n), effective 7/1/2026. Not mentioned on any Carbon County page reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; Modular Building Institute (MBI) Standards 1200 and 1205 — per Utah Code § 15A-2-103(1)(o), statewide-mandated for modular units. Not mentioned on any Carbon County page reviewed as of live re-check 2026-07-16; added as a statute-sourced omission.; No International Fire Code (IFC) entry: § 15A-2-103 does not adopt the IFC — it is separately governed under Title 15A Chapter 5, outside the scope of this section. Carbon County's FAQ does not list an IFC edition either, so there is no mis-citation to correct here.. Local amendments apply — see the Price overview page for the full list.

No. Price City has no independent building-permit function. EV charger/EVSE installation for property within Price City limits is permitted through Carbon County's Building & Planning Department as standard electrical work — there is no distinct EV-charger permit type or fee published by the county.

No dollar-amount fee for EV charger/electrical permits could be located on Carbon County's official website after an exhaustive search (matching the same gap documented for Price's other Carbon-County-administered permit types in this dataset). Contact the Building Department at (435) 636-3260 or planning@carbon.utah.gov for a current fee quote.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Price building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.