Change of Use / Occupancy Permit — Unincorporated Daggett County, Utah · Requirements sheet
Reviewed 2026-07-22 · Source: https://www.daggettcounty.gov/DocumentCenter/View/7814
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Occupancy Permit in Unincorporated Daggett County, Utah
Unincorporated Daggett County does not publish a standalone 'change of use' or 'certificate of occupancy' application among its roughly 25 published permit forms. Instead, County Code § 8-9-23 (Occupancy Permits, Chapter 9 - Supplementary and Qualifying Regulations) establishes a general, county-wide occupancy-permit requirement: land, buildings, and premises in any zone may be used only for the purposes permitted in that zone, the Building Inspector must inspect the premises and determine the use meets zoning requirements before issuing the occupancy permit, and — critically — 'such a permit shall also be required whenever the character or use of any building or land is proposed to be changed from one use to another use,' independent of whether any new construction is involved. For new construction, this occupancy/CO step is already folded into the Residential and Commercial Building Permit entries in this dataset (both require a complete contractor list before a Certificate of Occupancy is issued, and County Code § 8-7-8.D separately requires a Certificate of Occupancy for Planned Unit Developments upon completion). This entry documents the broader, freestanding version of the mechanism — a pure change of use in an existing building with no construction — for which the county publishes no dedicated application form, checklist, or fee; verified directly from the county's own Title 8 ordinance text.
Reviewed 2026-07-22 · Source
When you need this permit
- Any change in 'the character or use of any building or land ... from one use to another use' per County Code § 8-9-23, whether or not new construction is involved
- New construction: an occupancy permit/Certificate of Occupancy is required upon completion, issued after the Building Inspector confirms the completed structure meets zoning and (for Planned Unit Developments specifically) the approved development plan per County Code § 8-7-8.D
- Existing building/premises: the property owner may submit a written request for an occupancy permit covering any lawful use existing on the ordinance's effective date, including a nonconforming use, per County Code § 8-9-23
- A change from one NONCONFORMING use to another nonconforming use is further restricted under County Code § 8-10-8: it is treated as a conditional use requiring Planning Commission review, and the new use may not be more intensive than the most recent existing legal nonconforming use
- The Building Inspector must inspect the premises and determine it meets applicable zoning-district requirements before issuing the occupancy permit
Required documents
Check off what you have — your progress is saved on this device.
Fee schedule
Review timeline
Inspection process
- 1
Occupancy / Use Compliance Inspection
Building Inspector inspects the premises and determines whether the proposed use meets the zoning-district requirements before issuing the occupancy permit (County Code § 8-9-23).
See the full Unincorporated Daggett County inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated 'change of use' or 'certificate of occupancy' application among the roughly 25 permit forms Daggett County publishes (Applications page re-checked 2026-07-22) — the county's actual mechanism is County Code § 8-9-23's general Occupancy Permit requirement, triggered any time a building or land's use changes.
- For new construction, don't file this separately — the Certificate of Occupancy is already issued as the final step of the Residential or Commercial Building Permit once the contractor list is submitted and the Final inspection is passed.
- Converting an existing building to a different use with no construction involved is the scenario most likely to need this mechanism on its own; start with a written request to Planning & Zoning (435-784-3218 ext. 230) since no standard form is published.
- Changing from one nonconforming use to another nonconforming use is a special case — County Code § 8-10-8(C) requires Planning Commission conditional-use approval, and the new use cannot be more intensive than the property's existing legal nonconforming use.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Daggett County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Daggett County
Change of Use / Occupancy Permit in other cities
Compare change of use / occupancy permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Daggett County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Daggett County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →