EV Charger / EVSE Permit — Unincorporated Daggett County, Utah · Requirements sheet
Verified 2026-07-23 · Source: https://www.daggettcounty.gov/DocumentCenter/View/10646/Permit-application-electrical-mechanical-plumbing-buildint-permit-2019docm---pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Unincorporated Daggett County, Utah
Daggett County publishes no distinct EV charger / EVSE permit or fee. A home or commercial EV charger installation (new circuit) is electrical work and is covered under the county's combined Electrical, Mechanical, and Plumbing Permit — check the 'Electrical' box on that single application form — but the county publishes no fee schedule for this permit at all, and does not name EV chargers, EVSE, or charging stations anywhere in its permit materials.
Verified 2026-07-23 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential, commercial, or agricultural property in unincorporated Daggett County
- New dedicated 240V circuit and/or panel capacity to serve the charger, checked as 'Electrical' scope on the combined permit application
- Residential work may be self-performed by the owner ('SELF (IF RESIDENTIAL)' option); commercial/agricultural work requires a licensed contractor Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Before covering or concealment.
- 2
Final
After work complete, before use/occupancy.
See the full Unincorporated Daggett County inspection guide — scheduling & re-inspection fees →
Tips
- A home EV charger install (new circuit) is covered under Daggett County's combined Electrical, Mechanical, and Plumbing Permit — check the 'Electrical' box on the application. The county does not publish a distinct EV-charger permit, checklist, or fee.
- No fee amount is published for the combined Electrical, Mechanical, and Plumbing Permit at all — confirm current pricing directly with the county before applying, since neither this nor the general trade permit publishes a dollar figure.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Daggett County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Daggett County
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →