Skip to main content
PermitBase

Commercial Tenant Improvement / Tenant Finish Permit in Unincorporated Daggett County, Utah

Unincorporated Daggett County does NOT publish a separate tenant-improvement/tenant-finish permit application, fee, or checklist. The county's own Commercial Building Permit Application is a single 'COMMERCIAL BUILDING PERMIT APPLICATION' form whose 'Type of Improvement' checkbox lists 'New Building, Addition, Remodel, Demo, Pre-Manufactured Building, Moving' as the options. File a tenant-improvement or tenant-finish project on that same application, checking 'Remodel' or 'Addition' as applicable; it is reviewed against the same Commercial Building Plans Checklist and subject to the same fee/deposit mechanism as new commercial construction. No Daggett-specific tenant-improvement or tenant-finish document, fee line, or process distinct from this general commercial application is published on daggettcounty.gov.

Reviewed 2026-08-02 · Source

When you need this permit

  • Tenant improvement / tenant finish work within an existing commercial building, filed by checking 'Remodel' (or 'Addition,' as applicable) under 'Type of Improvement' on the county's single Commercial Building Permit Application — Daggett County does not publish a separate tenant-improvement-specific application
  • Site plan meeting County Code § 8-2-3 definitions
  • Three 24x36 sets of building plans drawn to scale; at least one wet-stamped by a Utah-licensed architect and engineer
  • Plans must show type of construction (IBC 2015 Ch. 6), occupancy type (IBC 2015 Ch. 3), and occupant load (IBC 2015 § 1004) as cited in the county's own commercial plans checklist
  • Plans must be stamped by the Fire Chief (who retains one set) before the Building Official will issue the permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Application Deposit
The Daggett County Commercial Building Permit application confirms a nonrefundable deposit is required and credited to the final plan-check total, but does not state the dollar figure for any… Show full citationThe Daggett County Commercial Building Permit application confirms a nonrefundable deposit is required and credited to the final plan-check total, but does not state the dollar figure for any commercial sub-type including tenant improvement — contact Planning & Zoning (435-784-3218 ext. 230) to confirm. County Code § 8-3-4.M (codelibrary.amlegal.com) confirms the FINAL fee is legally IBC-valuation-based rather than a flat figure, but is silent on deposit amounts. A Board-of-County-Commissioners fee-schedule resolution is the mechanism that would set such a figure (confirmed to exist for PUD/subdivision fees per County Code § 8-7-10), but no applicable resolution appears among the 45 documents in the county's '2018-2019 Ordinances & Resolutions' index (daggettcounty.gov/515) — most of those documents are scanned images, and the one readable resolution is an unrelated Dutch John utility-rate resolution. No commercial/TI deposit dollar figure is published; this fee remains partial.
Not separately published for commercial or tenant-improvement work (residential deposit schedule is $200 accessory / $600 dwelling; no commercial or TI-specific dollar figure is stated on the public application form)
State SurchargeConsistent with the surcharge stated on the county's residential permit packet; the commercial application does not separately restate this but no evidence it differs for tenant-improvement work
1% of permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Unincorporated Daggett County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete placement — footings, forms, reinforcing steel (if the tenant-finish scope includes any foundation/slab work)

  2. 2

    Rough-In (MEP)

    Plumbing, mechanical, and electrical rough-in before concealment

  3. 3

    Framing

    After framing and fire-resistance-rated construction elements are in place

  4. 4

    Final

    After all permitted work is complete, prior to occupancy/Certificate of Occupancy

See the full Unincorporated Daggett County inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate tenant-improvement or tenant-finish application in unincorporated Daggett County — use the same Commercial Building Permit Application and check 'Remodel' or 'Addition' under 'Type of Improvement.'
  • Commercial plans require sign-off from BOTH the Fire Chief and the Planning & Zoning Department before a permit is issued, even for interior-only tenant-finish scopes — budget extra time for the fire review step.
  • The county's own Commercial Building Plans Checklist states it is 'not all-inclusive' and that individual projects may require different information, so a tenant-finish project's document list will typically be a subset of the full new-construction checklist (e.g., no footing/foundation detail needed for a purely interior remodel).

Frequently asked questions

Unincorporated Daggett County requires a commercial tenant improvement / tenant finish permit for: Tenant improvement / tenant finish work within an existing commercial building, filed by checking 'Remodel' (or 'Addition,' as applicable) under 'Type of Improvement' on the county's single Commercial Building Permit Application — Daggett County does not publish a separate tenant-improvement-specific application; Site plan meeting County Code § 8-2-3 definitions; Three 24x36 sets of building plans drawn to scale; at least one wet-stamped by a Utah-licensed architect and engineer; Plans must show type of construction (IBC 2015 Ch. 6), occupancy type (IBC 2015 Ch. 3), and occupant load (IBC 2015 § 1004) as cited in the county's own commercial plans checklist; Plans must be stamped by the Fire Chief (who retains one set) before the Building Official will issue the permit. If your project isn't listed, confirm with Daggett County Planning & Zoning / Building Department at 435-784-3218 ext. 230 (Planning & Zoning — Carrie Poulsen); 435-784-3222 ext. 230 (alternate listing); Building Inspector Matt Tate: 435-219-7545 / 435-247-2799 before starting work.

In Unincorporated Daggett County, the published Application Deposit is: Not separately published for commercial or tenant-improvement work (residential deposit schedule is $200 accessory / $600 dwelling; no commercial or TI-specific dollar figure is stated on the public application form). Additional published fees: State Surcharge — 1% of permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Daggett County does not publish a plan-review timeline for this permit. Contact Daggett County Planning & Zoning / Building Department at 435-784-3218 ext. 230 (Planning & Zoning — Carrie Poulsen); 435-784-3222 ext. 230 (alternate listing); Building Inspector Matt Tate: 435-219-7545 / 435-247-2799 for current turnaround.

You'll need: Commercial Building Permit Application; Commercial Building Plans Checklist Package; Fire Chief Stamp; Complete List of Contractors. See the required-documents checklist on this page for details on each.

Unincorporated Daggett County requires 4 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: Foundation, Rough-In (MEP), Framing, Final. Schedule each through Daggett County Planning & Zoning / Building Department (435-784-3218 ext. 230 (Planning & Zoning — Carrie Poulsen); 435-784-3222 ext. 230 (alternate listing); Building Inspector Matt Tate: 435-219-7545 / 435-247-2799).

Apply through Daggett County Planning & Zoning / Building Department at Daggett County Courthouse, 95 North 100 West (also listed as 95 North 1st West), P.O. Box 219, Manila, UT 84046. Phone: 435-784-3218 ext. 230 (Planning & Zoning — Carrie Poulsen); 435-784-3222 ext. 230 (alternate listing); Building Inspector Matt Tate: 435-219-7545 / 435-247-2799, email: cpoulsen@daggettcounty.gov. Office hours: Monday–Wednesday, 9:00 AM–1:00 PM and 1:00 PM–5:00 PM (closed holidays), per Daggett County Planning and Zoning page. Official information: https://www.daggettcounty.gov/496/Applications.

Unincorporated Daggett County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — legally controlling in unincorporated Daggett County per Utah Code § 15A-2-103(1)(a), in force statewide since July 1, 2026 and binding on counties per § 15A-1-204. HISTORY / COUNTY LAG: Daggett County's own Commercial Building Permit plans checklist still expressly cites the long-superseded 2015 IBC by section ('Type of construction (required) IBC 2015 Chapter 6', 'Occupancy type (required) IBC 2015 Chapter 3', 'Occupant load (required) IBC 2015 Section 1004') — re-confirmed by direct PDF fetch 2026-07-16; see NOTE below.; 2021 International Residential Code (IRC), including Appendix AQ — legally controlling in unincorporated Daggett County per Utah Code § 15A-2-103(1)(b) and (1)(c); the IRC edition was NOT changed by the July 1, 2026 statewide amendment and remains the 2021 edition. HISTORY / COUNTY LAG: Daggett County's own Residential Building Permit packet still expressly cites the long-superseded 2015 IRC ('SECTION R109 OF THE 2015 INTERNATIONAL RESIDENTIAL CODE REQUIRES THAT YOU HAVE INSPECTION DURING CONSTRUCTION', with the full R109.1 series inspection text reproduced in the county's own packet) — see NOTE below.; Utah Code § 15A-2-103 sets the statewide-adopted baseline: the 2024 editions of the IBC, IPC, IMC, IFGC, IECC and IEBC, plus the residential provisions of the 2024 ISPSC, are in force statewide effective July 1, 2026, alongside the 2021 IRC and the 2023 NEC (both unchanged). Under § 15A-1-204 this baseline binds counties as well as municipalities. Daggett County's own public permit packets — residential and commercial — still cite the 2015 IBC/IRC by section number, and the Commercial Building Permit Plans Checklist also cites the 2015 IMC for mechanical design (IMC § 312) and duct sizing (IMC § 603). The statewide edition under § 15A-2-103 is the legally controlling one, so design to it and expect the county's handouts to reference the older editions.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide in force (Daggett County's own permit forms do not name a specific NEC edition). Local amendments apply — see the Unincorporated Daggett County overview page for the full list.

No. The county's Commercial Building Permit Application itself lists 'Remodel' and 'Addition' as options under 'Type of Improvement' on the same form used for new commercial construction. Tenant improvement / tenant finish work is filed and reviewed through this single combined commercial process; the county publishes no distinct tenant-improvement fee, checklist, or application.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-08-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Daggett County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated Daggett County.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Unincorporated Daggett County's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Unincorporated Daggett County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Unincorporated Daggett County lands. Privacy.