Residential Building Permit in Unincorporated Daggett County, Utah
Required for new residential construction (stick-built or manufactured), additions, remodels, demolition, and moving of residential structures in unincorporated Daggett County, per County Code § 8-3-4. Issued by the Daggett County Planning & Zoning office; inspections performed by the county Building Inspector.
Verified 2026-07-08 · Source
When you need this permit
- New single-family dwelling construction (stick-built or manufactured home on private lot or in a park)
- Additions, remodels, or demolition of a residential structure
- Accessory structures over 200 square feet (structures under 200 sq ft are exempt per County Code § 8-6A-1A / IRC R105.2)
- Detailed site plan showing north point, lot lines, existing structures/easements, proposed construction, motor vehicle access, and (if not on public sewer) an approved septic system drawing
- Authorization from Daggett County Planning and Zoning Commission confirming zoning/setback compliance
- Water/Sewer Connection or Wastewater Permit Verification Form signed by the applicable provider (no permit issues without this)
- Complete list of licensed contractors (or Owner/Builder Certification if self-performing) required before Certificate of Occupancy is issued Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
After piers/poles set or trenches/basement areas excavated, forms erected, and reinforcing steel placed and supported — prior to placing concrete (2015 IRC R109.1.1, reproduced in county packet)
- 2
Plumbing, Mechanical, Gas, and Electrical Rough-In
Prior to covering/concealment, before fixtures or appliances are set, and prior to framing inspection (2015 IRC R109.1.2)
- 3
Frame and Masonry
After roof, masonry, framing, fire stopping, draft stopping, and bracing are in place, and after plumbing/mechanical/electrical rough inspections are approved (2015 IRC R109.1.4)
- 4
Final
After all permitted work is complete and prior to occupancy (2015 IRC R109.1.6)
See the full Unincorporated Daggett County inspection guide — scheduling & re-inspection fees →
Tips
- Contact the Building Inspector (Matt Tate, 435-219-7545 or 435-247-2799) directly to schedule inspections — at least 24 hours notice is required, and it is the permit holder's responsibility to schedule all necessary inspections.
- An approved inspection is required every 180 days from issuance or the permit becomes null and void; construction must commence within 180 days of issuance, and the project must be completed within 2 years (a 6-month extension can be requested from Planning & Zoning).
- Snow load requirements vary sharply by area: Manila and Browns Park 30 lbs, Dutch John and Clay Basin 40 lbs, Pines 80 lbs. Wind load is 90 mph county-wide; Seismic Zone C.
- No building permit will be approved without a signed Water/Sewer Connection or Wastewater Permit Verification Form — wastewater permits and fees for septic systems are handled directly by TriCounty Health District (435-790-5375 or 435-247-1177), not the county building office.
- A building permit refund of up to 80% may be requested within 90 days of approval, provided work has not yet started; determined at the Building Official's discretion.
- Basements: lateral sewer line depth is the property owner's responsibility — if the existing line is not deep enough to serve a basement, the owner must install any needed pumps or equipment.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Daggett County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Daggett County
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Daggett County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Daggett County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →