EV Charger / EVSE Permit — Kanab, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://kanab.utah.gov/2152/Building-Department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Kanab, Utah
Kanab has no distinct EV charger/EVSE permit type or fee, and no standalone electrical-trade permit line at all. The 2024 Kanab City Adopted Consolidated Fee Schedule contains zero mentions of 'EV,' 'electric vehicle,' 'charging station,' or 'EVSE.' A residential EV charger install is expected to route through the same general Building Permit and its ICC Building Valuation Data Tool fee formula as standard electrical work.
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
- New dedicated electrical circuit and/or panel/service capacity upgrade to serve the charger
- Complete application (see documents) submitted via the CityInspect online portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Scheduled Inspection (Electrical)
Inspections require at least 24 hours' notice and are scheduled within 3 business days after the request is received. Scheduled by calling the Building Department at 435-644-2534.
See the full Kanab inspection guide — scheduling & re-inspection fees →
Tips
- Kanab has no distinct EV charger/EVSE permit type or fee — the 2024 Kanab City Adopted Consolidated Fee Schedule was fetched and searched directly (2026-07-20) and contains zero mentions of 'EV,' 'electric vehicle,' 'charging station,' or 'EVSE.'
- Kanab also has no standalone electrical-trade permit line — a residential EV charger install is expected to route through the same general Building Permit and its ICC Building Valuation Data Tool fee formula as standard electrical work; confirm directly with the Building Department (435-644-2534) before budgeting.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kanab building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Kanab
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →