EV Charger / EVSE Permit — Unincorporated Kane County, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://kane.utah.gov/165/Building-Department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Unincorporated Kane County, Utah
Kane County does not publish a distinct EV charger, EVSE, or electric vehicle charging station permit or fee. The Kane County Building Department FAQ (kane.utah.gov) confirms electrical work such as meter base installation and electrical panel replacement requires a permit and engineering review, and the county has no standalone Electrical Permit type separate from the general Building Permit — meaning a new dedicated EV charger circuit is processed and fee-assessed under the same valuation-based Building Permit (based on ICC Current Valuation Data plus a 25% plan check fee and 1% state education fee). The county's 2026 Schedule of Fees resolution (R 2026-1) is a scanned document without a machine-readable text layer, so a distinct EV-specific fee line, if one exists, could not be confirmed.
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
- New dedicated electrical circuit and/or panel capacity to serve the charger — treated as electrical work requiring a permit per the Kane County Building Department FAQ
- Compliance with the 2023 National Electrical Code (NEC) as adopted statewide by Utah Code § 15A-2-103(1)(g)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Inspection
Verification of the new circuit, panel capacity, and grounding for the EV charger installation, performed under the general Building Permit inspection process.
See the full Unincorporated Kane County inspection guide — scheduling & re-inspection fees →
Tips
- Kane County has no separate EV-charger or standalone Electrical permit type — EV charger circuit installations (e.g., meter base or panel work) are processed under the general valuation-based Building Permit, per the Kane County Building Department FAQ.
- Electrical work is flagged by the county as requiring engineering review — confirm scope and fee with the Building Department at (435) 644-4985 before applying.
- Kane County's 2026 Schedule of Fees resolution (R 2026-1) is a scanned PDF without extractable text, so it could not be checked for a distinct EV-charger fee line; this matches the treatment already documented for solar panel installs on the county's residential-building-permit entry.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Kane County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Kane County
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →