Demolition Permit in Salt Lake City, Utah
Required for partial or complete demolition of structures in Salt Lake City, including utility disconnection and debris disposal.
Verified 2026-06-27 · Source
When you need this permit
- Complete demolition of any structure
- Partial demolition involving structural elements
- Removal of load-bearing walls
- Demolition of structures with asbestos or lead paint
Required documents
- Req
Demolition Application
Scope of demolition, structure details, and disposal plan
- Req
Asbestos Survey
NESHAP asbestos inspection for structures built before 1985
- Req
Utility Disconnect Confirmation
Proof that gas, electric, water, and sewer are disconnected
- Opt
Site Plan
Showing structure to be demolished, adjacent structures, and access
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Permit | Valuation-based per SLC building permit fee schedule | — |
| Demolition Landscaping Waiver Inspection | $163 (if waiver denied, applied to permit fee) | — |
| Plan Review | 65% of permit fee | — |
Review timeline
~3–10 business days
Typical estimate — confirm current times with the Salt Lake City building department
Inspection process
- 1
Pre-Demolition
Verify utility disconnects and asbestos clearance before work begins
- 2
Final/Site Clear
Site cleared, foundation removed or capped, erosion control in place
Tips
- Utilities must be disconnected by the utility company before demolition begins — Salt Lake City will verify.
- Structures built before 1985 require an asbestos survey before a demolition permit is issued.
- Notify neighbors and Salt Lake City at least 48 hours before demolition work starts.
- Demolition debris must go to an approved landfill — Salt Lake City may require a disposal receipt.
Frequently asked questions
- Do I need a permit to demolish a structure in Salt Lake City?
- Yes. Salt Lake City requires a demolition permit for all complete and partial structural demolitions. The permit ensures utilities are safely disconnected and hazardous materials like asbestos are properly handled.
- Do I need an asbestos test before demolition in Salt Lake City?
- Yes, for structures built before 1985. Federal NESHAP regulations require an asbestos inspection before demolition, and Salt Lake City enforces this as part of the permit process.
Sources & verification
Key facts verified against official sources. Last reviewed 2026-06-27.
- Salt Lake City Building Services — official building department
- Salt Lake City Consolidated Fee Schedule (Ord. 2025-34)
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Salt Lake City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Salt Lake City
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.