Solar Panel Permit — Salt Lake City, Utah · Requirements sheet
Verified 2026-06-29 · Source: https://www.slcdocs.com/govt/cfs.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Panel Permit in Salt Lake City, Utah
Required for installation of rooftop or ground-mounted solar photovoltaic systems in Salt Lake City. SLC charges a flat fee by system size in kW, distinct from the standard valuation-based building permit fee.
Verified 2026-06-29 · Source
When you need this permit
- Rooftop solar panel installation
- Ground-mounted solar array installation
- Battery storage system installation (requires separate electrical permit for wiring)
- Electrical service upgrade for solar interconnection
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
See the full Salt Lake City inspection guide — scheduling & re-inspection fees →
Tips
- Salt Lake City has a fixed-rate solar permit fee schedule (by system kW), not the standard valuation-based building permit fee — the Ord. 2025-34 fee schedule lists four size tiers.
- Rocky Mountain Power interconnection approval is required before the system can be energized — obtain this in parallel with the SLC permit.
- The 2023 NEC (adopted statewide) governs solar electrical installations; confirm fire department access pathway requirements with SLC Building Services.
- A separate electrical permit may be required for the wiring/inverter portion depending on project scope — confirm with SLC Building Services at (801) 535-7155.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Salt Lake City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Salt Lake City
Solar Panel Permit in other cities
Compare solar panel permit fees across Utah →
Look up this fee in a different city →