Required for demolition of structures in Payson. Fees differ for parcels of 1 acre or less versus larger parcels.

Verified 2026-07-03 · Source

When you need this permit

  • Demolition of a structure or structures
  • Compliance with PCC Title 10, Chapter 10.24 (Demolition)

Required documents

Check off what you have — your progress is saved on this device.

    Fee schedule

    Demolition (<= 1 acre)Payson City Fee Schedule (6/30/2025), p.4: 'Demolition <= 1 acre — $500.00.'
    $500.00
    Demolition (> 1 acre) — Base FeePayson City Fee Schedule (6/30/2025), p.4: 'Demolition > 1 acre — Base Fee — $500.00.'
    $500.00
    Demolition (> 1 acre) — Each Additional AcrePayson City Fee Schedule (6/30/2025), p.4: 'Each Additional acre (in addition to base) — $300.00.'
    $300.00 (in addition to base fee)

    Review timeline

    Plan review
    Not published — contact the department

    How long did your Demolition Permit permit actually take in Payson?

    Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

    Inspection process

    1. 1

      Pre-Demolition (Utility Disconnect Verification)

      Utility disconnection verified before demolition per standard practice referenced in PCC Title 10.24.

    2. 2

      Final

      Site cleared and graded per approved demolition plan.

    See the full Payson inspection guide — scheduling & re-inspection fees →

    Tips

    • Demolition fees scale by parcel size: a flat $500 base fee applies up to 1 acre, with an additional $300 per acre beyond that.

    Frequently asked questions

    Payson requires a demolition permit for: Demolition of a structure or structures; Compliance with PCC Title 10, Chapter 10.24 (Demolition). If your project isn't listed, confirm with Payson City Building Department (Development Services) at 801-465-5200 before starting work.

    Payson charges a $500.00 base demolition fee for parcels of 1 acre or less. For parcels larger than 1 acre, the $500.00 base fee applies plus $300.00 for each additional acre.

    Payson does not publish a plan-review timeline for this permit. Contact Payson City Building Department (Development Services) at 801-465-5200 for current turnaround.

    Payson requires 2 inspection(s) for a demolition permit, in order: Pre-Demolition (Utility Disconnect Verification), Final. Schedule each through Payson City Building Department (Development Services) (801-465-5200).

    Apply through Payson City Building Department (Development Services) at 439 W. Utah Ave, Payson, UT 84651. Phone: 801-465-5200. Office hours: Monday–Thursday, 7:30 AM – 6:00 PM, per paysonutah.gov/334/Building-Permits-Inspections and the Residential Building Permit Minimum Submittal Requirements document (paysonutah.gov/DocumentCenter/View/453/Residential-Building-Permit-Submittal-Requirements), both fetched 2026-07-03. No department email address is published on the Building Permits & Inspections page.. Official information: https://www.paysonutah.gov/334/Building-Permits-Inspections.

    Payson, Utah has adopted: Payson City Code (PCC) Title 10, Chapter 10.04 ('Technical Construction Codes Adoption', PCC 10.04.040) adopts 'the technical construction codes' by reference for building, plumbing, electrical, and mechanical construction, without restating specific IBC/IRC/IMC/IPC/IECC/NEC edition years in the ordinance text itself — per the recodified Payson City Municipal Code (s3-us-west-2.amazonaws.com/municipalcodeonline.com-new/payson/ordinances/documents/1653339554_05-18-2022-D%20Recodified%20Municipal%20Code.pdf, Title 10.04, fetched 2026-07-03). This is consistent with Utah's Title 15A State Construction and Fire Codes Act model, under which every incorporated Utah city is automatically a compliance agency enforcing the state-adopted code suite; Payson's own ordinance text references 'the State Construction Code' and 'technical construction codes' generically rather than citing specific edition years.; International Fire Code (IFC), 2009 edition, is explicitly named with its year in Payson's own code: PCC 9.04.010 'Adoption Of International Fire Code' states the adopted code is 'marked and designated as the International Fire Code, including Appendix Chapters B, C, D, II, I & J (see International Fire Code 101.2.1, 2009 edition)' — per the same recodified Municipal Code document, Title 9.04, fetched 2026-07-03. NOTE: this 2009 IFC citation is the only explicit code-edition year found anywhere in Payson's own currently-published municipal code text; it substantially predates the 2021 IBC/IRC/2023 NEC statewide baseline described in Utah Code Title 15A and may reflect a stale, un-updated ordinance section rather than the code editions actually enforced today. Reported as-published rather than corrected, per grounded-data policy of not inventing a fact the city's own source does not state.; International Residential Code (IRC) — referenced generically ('in accordance with the requirements of the International Residential Code, as adopted') in PCC Title 10 without a stated edition year, per the same recodified Municipal Code document, fetched 2026-07-03.; International Building Code (IBC) — referenced generically ('the International Building Code as adopted by the State of Utah') in PCC Title 10 without a stated edition year, per the same recodified Municipal Code document, fetched 2026-07-03.; International Plumbing Code (IPC) — referenced generically ('The International Plumbing Code as adopted and amended by the State of Utah') in PCC Title 10 without a stated edition year, per the same recodified Municipal Code document, fetched 2026-07-03.; National Electrical Code (NEC) — referenced generically ('National Electrical Code, and all fittings and materials used in such installations') in PCC Title 10 without a stated edition year, per the same recodified Municipal Code document, fetched 2026-07-03.. Local amendments apply — see the Payson overview page for the full list.

    Sources & verification

    Verified against official sources. Last reviewed 2026-07-03.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Payson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.