Demolition Permit in Payson, Utah
Required for demolition of structures in Payson. Fees differ for parcels of 1 acre or less versus larger parcels.
Verified 2026-07-03 · Source
When you need this permit
- Demolition of a structure or structures
- Compliance with PCC Title 10, Chapter 10.24 (Demolition)
Required documents
Check off what you have — your progress is saved on this device.
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition (Utility Disconnect Verification)
Utility disconnection verified before demolition per standard practice referenced in PCC Title 10.24.
- 2
Final
Site cleared and graded per approved demolition plan.
See the full Payson inspection guide — scheduling & re-inspection fees →
Tips
- Demolition fees scale by parcel size: a flat $500 base fee applies up to 1 acre, with an additional $300 per acre beyond that.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Payson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Payson
Demolition Permit in other cities
Compare demolition permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Payson project checklist
Describe your project once and get every permit, document, and fee it triggers in Payson — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →