Solar Distributed Generation (Solar PV) Permit — Payson, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.paysonutah.gov/308/Distributed-Generation
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Distributed Generation (Solar PV) Permit in Payson, Utah
Required for residential and commercial solar photovoltaic and other distributed-generation (net-metered) electric installations in Payson. This is a genuinely distinct, dedicated program — Payson operates its own municipal electric utility (Payson Power) and requires solar installations to go through the city's own Distributed Generation Program: a dedicated application form co-signed by the contractor, property owner, Power Department, and Building Official, plus a separate interconnection application fee, in addition to the standard valuation-based Building Permit. Payson's own Distributed Generation informational page cites the governing ordinance as 'Payson City Code, Chapter 4, Section 4.24.060, Distributed Generation Program'; the program's own PDF text (paysonutah.gov/DocumentCenter/View/158) is internally numbered as 'Chapter 13.06, Distributed Generation Program' — both citations are reported as published, since the discrepancy could not be independently resolved and is likely a recodification artifact.
Verified 2026-07-19 · Source
When you need this permit
- Completed Building Permit application, including the property serial number
- Solar Distributed Generation Program application form, completed with system specifications (type of class: Residential 1-10 kW or Commercial 10-25 kW, installed capacity, module/inverter manufacturer and model, array location, disconnect switch location, battery/generator backup status) and signed by the contractor and property owner
- Property owner must acknowledge receipt of a copy of the Distributed Generation Program Ordinance, per the application form's signature block
- Site/Facility Layout Diagram and Facility One-Line Diagram
- Net Meter Agreement
- Hard copy of the permit application, plans, specs, net metering documents, plus an electronic submittal on a flash drive or similar
- Nameplate generating capacity may not exceed 10 kW for Residential or 25 kW for Commercial systems, per Payson City Code § 13.06.010 (Purpose and Scope)
- Applicant must furnish and install a UL-approved safety disconnect switch, visible-break type, in a metal enclosure securable by padlock, located adjacent to the utility meter and accessible to utility personnel at all times (waivable only if the applicant's equipment performs internal physical disconnection to the utility's satisfaction)
- Compliance with NEC, NESC, IEEE 1547-2003, UL 1741, and IEEE 929-2000 (Recommended Practice for Utility Interface of Photovoltaic Systems) for inverter-based systems
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Power Meter / System Check
Public Works is automatically notified when a solar permit is received; a Payson Power representative checks the power meter and system, per the city's official Distributed Generation page.
- 2
Final Inspection
Scheduled with Development Services with at least 24 hours' advance notice; Development Services office hours are Monday–Thursday, 7:30 AM–6:00 PM, per the city's official Distributed Generation page.
See the full Payson inspection guide — scheduling & re-inspection fees →
Tips
- Payson operates its own municipal electric utility (Payson Power) — solar installations require sign-off from both the Building Official AND the Power Department on the same Distributed Generation Program Form, not just a standard building/electrical permit.
- The $100.00 interconnection application fee is non-refundable and is paid together with the net meter cost, per the program ordinance.
- System size is capped at 10 kW nameplate capacity for Residential and 25 kW for Commercial — larger systems do not qualify under this program as published.
- Net metering is a strict true-up each billing cycle with no banking of energy — excess generation is paid at the feed-in tariff rate rather than carried forward, per Distributed Generation Program § 13.05.050(1)(a).
- The property owner must sign an acknowledgment of having received a copy of the Distributed Generation Program Ordinance — this is a separate signature line from the contractor's certification on the same form.
- Applications are accepted first-come, first-served up to the capacity limit of the local circuit or distribution system — a request can be rejected in writing if it does not comply with the program's technical rules.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Payson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Payson
Solar Distributed Generation (Solar PV) Permit in other cities
Compare solar distributed generation (solar pv) permit fees across Utah →
Look up this fee in a different city →