Change of Use / Certificate of Occupancy and Zoning Compliance in Provo, Utah
Provo does not publish a standalone 'Change of Use' permit or fee. Instead, Provo City Code § 14.01.090 ('Certificate of Occupancy and Zoning Compliance') makes it unlawful to occupy, or allow the occupancy of, any building or premises with a greater intensity of use or different occupancy than stated on its Certificate of Occupancy and Zoning Compliance, and requires that 'a new certificate shall be required at any time the occupancy of the building changes to a more intensive use.' This certificate is issued by the Provo Planning Commission, distinct from the Building Division's building-permit process. Where the change of use requires interior construction (egress, fire separation, MEP, accessibility, etc.), that work is permitted and billed separately under this file's Commercial Building Permit or Commercial Tenant Improvement / Tenant Finish Permit entries; this entry covers the occupancy/zoning-compliance-change mechanism itself.
Verified 2026-07-22 · Source
When you need this permit
- A new Certificate of Occupancy and Zoning Compliance is required any time the occupancy of a building changes to a more intensive use, or the number of occupants in an apartment/multiple residential building increases more than 5% above the number on the previously issued certificate (Provo City Code § 14.01.090(2))
- Application information must be submitted per § 14.01.090(3): for commercial, industrial, and institutional certificates — number of employees, off-street parking spaces for employees and for customers/visitors, number and type of restroom facilities, square footage used for each separate type of occupancy, and a signed owner/agent certification
- Zoning compliance should be confirmed with Development Services ((801) 852-6400) or via Provo's Zoning Map before selecting a new business location, per the city's Starting a Business guidance
- If the new use is classified as a conditional use in that zone, a separate Conditional Use Permit (Provo City Code § 14.02.040) is required in addition to the Certificate of Occupancy and Zoning Compliance
- Construction needed to accommodate the new use (egress, fire separation, MEP, accessibility) requires a separate Commercial Building Permit or Commercial Tenant Improvement Permit, reviewed under current code
- Occupying a building under a different or more-intensive occupancy than stated on its current Certificate is a misdemeanor and is declared a nuisance subject to abatement, per § 14.01.090(4)-(5)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Zoning Compliance Review
The Planning Commission reviews the use/occupancy information submitted under § 14.01.090(3) — employee count, parking, restroom facilities, and occupancy square footage for commercial/industrial/institutional uses — before issuing a new Certificate of Occupancy and Zoning Compliance.
- 2
Final / Certificate of Occupancy and Zoning Compliance Issuance
A new Certificate must be issued before the space may be occupied under its new use; if construction accompanied the change of use, this is coordinated with the Building Division's final inspection on the underlying building or tenant-improvement permit.
See the full Provo inspection guide — scheduling & re-inspection fees →
Tips
- Provo has no standalone 'change of use permit' — the operative mechanism is Provo City Code § 14.01.090: any change to a more intensive occupancy or use requires a NEW Certificate of Occupancy and Zoning Compliance from the Planning Commission before the space may be occupied.
- Occupying a building under a use or occupancy not listed on its current Certificate is a misdemeanor and a declared nuisance under § 14.01.090(4)-(5) — obtain the new Certificate before occupying.
- If the change of use requires interior construction (egress, fire separation, MEP, accessibility), that work needs its own Commercial Building Permit or Commercial Tenant Improvement Permit — there is no additional standalone 'change of use' fee beyond that valuation-based building-permit fee.
- Confirm zoning compliance with Development Services ((801) 852-6400) or Provo's Zoning Map before selecting a business location for the new use.
- If the new use is classified as a conditional use in that zone, budget for a separate $900.00 Conditional Use Permit (Provo City Code § 14.02.040) in addition to the Certificate of Occupancy and Zoning Compliance.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Provo building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Provo
Change of Use / Certificate of Occupancy and Zoning Compliance in other cities
Compare change of use / certificate of occupancy and zoning compliance fees across Utah →
Look up this fee in a different city →
Now live
Build your Provo project checklist
Describe your project once and get every permit, document, and fee it triggers in Provo — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →