Gillette building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Gillette, Wyoming.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
City Hall, 201 E. 5th St., 2nd Floor, Gillette, WY 82716
Phone
(307) 686-5260
Office hours
Mon–Fri (contact department for current hours); permits/plans/licenses/inspections managed via EnerGov Self Service online portal (registration required)

Published scheduling rules

  • Call the Inspection Line before 7:00 a.m. to get a same-day inspection; field inspectors are generally in the office 8–9 a.m. and 1–2 p.m. (Residential Building Permit (New Construction))
  • CCFD inspection scheduling requires at least 48 hours advance notice (call (307) 682-5319); published CCFD construction-inspection types for sprinkler work include "sprinkler rough in" and "sprinkler hydro" (Fire Sprinkler System Permit)
  • CCFD inspection scheduling requires at least 48 hours advance notice (call (307) 682-5319) (Fire Alarm System Permit)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Open Hole Letter / Footing

    Open Hole Letter sent to Building Inspection before footing inspection; soils engineer verification of footing/foundation type on file; rebar tied before concrete pour

  2. 2

    Foundation Wall

    After forms and rebar tied, before concrete placed

  3. 3

    Damp-Proofing / Drain Tile

    Before backfill placed around foundation or crawl space walls

  4. 4

    Underground Plumbing

    After all underground waste/vent/water piping installed and under test, before backfill/concrete

  5. 5

    Sill Plate

    When sill plate and sill seal are bolted in place, before floor system installed

  6. 6

    Rough Plumbing / Rough Electric / Rough Mechanical / Gas

    After respective waste/vent/water piping, wiring/boxes, venting/ductwork, and gas piping are installed and (for gas) under air test

  7. 7

    Exterior Vapor Barrier, Windows & Doors Flashing, Rough Framing

    After rough MEP/gas inspections complete, roofing done, framing and fire blocking complete, structure weather-tight

  8. 8

    Insulation

    After framing, before drywall on walls (sprayed ceiling insulation inspected at final)

  9. 9

    Sewer and Water

    After sewer and water lines installed, before backfill

  10. 10

    Final / Certificate of Occupancy

    Prior to moving furnishings into the building; tap fees must be paid when the permit is issued

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings/foundation before concrete pour, per soils engineer verification

  2. 2

    Framing

    Structural framing per applicable district's Accessory Structure setback/height standards

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Commercial Tenant Improvement / Commercial Building Permit

  1. 1

    Foundation / Footing

    Per stamped structural plans, before concrete pour

  2. 2

    Rough MEP / Fire

    Electrical, plumbing, mechanical, and fire suppression rough-in before walls closed

  3. 3

    Final — Building Inspection

    All work complete per approved plans

  4. 4

    TCO / CO

    Temporary Certificate of Occupancy or Certificate of Occupancy issued by Building Inspection after Council acceptance of utilities (if applicable) and FLC (Final Location Certificate) submittal to Planning/GIS

Applies to: Plumbing Permit

  1. 1

    Underground Plumbing

    After under-ground waste, vent, and water piping installed and pressure tested, before backfill/concrete

  2. 2

    Rough Plumbing

    After all waste, vent, and water piping installed, before walls closed

  3. 3

    Sewer and Water

    After sewer and water service lines installed, before backfill

  4. 4

    Final

    All fixtures connected, ready for occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing / Foundation (if new footings)

    Before concrete pour, per soils engineer verification

  2. 2

    Rough Plumbing / Electric / Mechanical / Gas

    Before walls closed

  3. 3

    Rough Framing

    After rough MEP/gas complete and structure weather-tight

  4. 4

    Final

    All work complete per approved plans

Applies to: Basement Finish Permit

  1. 1

    Rough Plumbing / Rough Electric / Rough Mechanical

    Before walls closed

  2. 2

    Rough Framing

    After rough MEP/gas inspections complete, framing and fire blocking complete

  3. 3

    Final

    All work complete per approved plans

Applies to: Deck Permit

  1. 1

    Footing

    Before concrete pour — verify 42-inch minimum depth and post footing dimensions

  2. 2

    Framing

    Ledger board attachment/flashing, joist hangers, post/beam connections

  3. 3

    Final

    Completed deck per approved plans

Applies to: Electrical Permit

  1. 1

    Temporary Electric Service

    After installation of the temporary meter base post with an approved means of grounding; may be installed by a licensed contractor or the homeowner

  2. 2

    Rough Electric

    After all wiring and boxes are installed, before walls closed

  3. 3

    Final

    All devices installed, system energized, before Certificate of Occupancy

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    After all venting and ductwork installed, before walls closed

  2. 2

    Gas

    After gas piping installed, supported, and under air test

  3. 3

    Final

    Equipment operational, combustion air and venting verified

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final — Structural/Racking

    Panel mounting, racking attachment, roof penetration sealing verified

  3. 3

    Final — Electrical

    All connections, inverter, and interconnection point verified

Applies to: Demolition Permit

  1. 1

    Pre-Demolition Utility Disconnects

    Verification that electrical service line is disconnected and plumbing is capped off at the street before demolition

  2. 2

    Final

    Site cleared, lot restored per code requirements

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electric

    EVSE circuit wiring and boxes installed, before walls closed

  2. 2

    Final

    EVSE unit installed, circuit energized and verified

Applies to: Fire Sprinkler System Permit

  1. 1

    Sprinkler Rough-In

    CCFD construction inspection of sprinkler piping before concealment, per CCFD's published inspection-type list; schedule at least 48 hours in advance via (307) 682-5319

  2. 2

    Sprinkler Hydro (Hydrostatic Test)

    CCFD hydrostatic pressure test of the completed sprinkler system, per CCFD's published inspection-type list

Gillette building permits

Get alerts for Gillette

We'll email you when Gillette's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.