Gillette building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Gillette, Wyoming.
Verified 2026-07-01 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- City Hall, 201 E. 5th St., 2nd Floor, Gillette, WY 82716
- Phone
- (307) 686-5260
- Office hours
- Mon–Fri (contact department for current hours); permits/plans/licenses/inspections managed via EnerGov Self Service online portal (registration required)
- Website
- Official site
Published scheduling rules
- Call the Inspection Line before 7:00 a.m. to get a same-day inspection; field inspectors are generally in the office 8–9 a.m. and 1–2 p.m. (Residential Building Permit (New Construction))
- CCFD inspection scheduling requires at least 48 hours advance notice (call (307) 682-5319); published CCFD construction-inspection types for sprinkler work include "sprinkler rough in" and "sprinkler hydro" (Fire Sprinkler System Permit)
- CCFD inspection scheduling requires at least 48 hours advance notice (call (307) 682-5319) (Fire Alarm System Permit)
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Open Hole Letter / Footing
Open Hole Letter sent to Building Inspection before footing inspection; soils engineer verification of footing/foundation type on file; rebar tied before concrete pour
- 2
Foundation Wall
After forms and rebar tied, before concrete placed
- 3
Damp-Proofing / Drain Tile
Before backfill placed around foundation or crawl space walls
- 4
Underground Plumbing
After all underground waste/vent/water piping installed and under test, before backfill/concrete
- 5
Sill Plate
When sill plate and sill seal are bolted in place, before floor system installed
- 6
Rough Plumbing / Rough Electric / Rough Mechanical / Gas
After respective waste/vent/water piping, wiring/boxes, venting/ductwork, and gas piping are installed and (for gas) under air test
- 7
Exterior Vapor Barrier, Windows & Doors Flashing, Rough Framing
After rough MEP/gas inspections complete, roofing done, framing and fire blocking complete, structure weather-tight
- 8
Insulation
After framing, before drywall on walls (sprayed ceiling insulation inspected at final)
- 9
Sewer and Water
After sewer and water lines installed, before backfill
- 10
Final / Certificate of Occupancy
Prior to moving furnishings into the building; tap fees must be paid when the permit is issued
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation
Footings/foundation before concrete pour, per soils engineer verification
- 2
Framing
Structural framing per applicable district's Accessory Structure setback/height standards
- 3
MEP Rough-In
Mechanical, electrical, plumbing rough-ins before walls closed
- 4
Final
All work complete, ready for occupancy
Applies to: Commercial Tenant Improvement / Commercial Building Permit
- 1
Foundation / Footing
Per stamped structural plans, before concrete pour
- 2
Rough MEP / Fire
Electrical, plumbing, mechanical, and fire suppression rough-in before walls closed
- 3
Final — Building Inspection
All work complete per approved plans
- 4
TCO / CO
Temporary Certificate of Occupancy or Certificate of Occupancy issued by Building Inspection after Council acceptance of utilities (if applicable) and FLC (Final Location Certificate) submittal to Planning/GIS
Applies to: Plumbing Permit
- 1
Underground Plumbing
After under-ground waste, vent, and water piping installed and pressure tested, before backfill/concrete
- 2
Rough Plumbing
After all waste, vent, and water piping installed, before walls closed
- 3
Sewer and Water
After sewer and water service lines installed, before backfill
- 4
Final
All fixtures connected, ready for occupancy
Applies to: Residential Addition / Remodel Permit
- 1
Footing / Foundation (if new footings)
Before concrete pour, per soils engineer verification
- 2
Rough Plumbing / Electric / Mechanical / Gas
Before walls closed
- 3
Rough Framing
After rough MEP/gas complete and structure weather-tight
- 4
Final
All work complete per approved plans
Applies to: Basement Finish Permit
- 1
Rough Plumbing / Rough Electric / Rough Mechanical
Before walls closed
- 2
Rough Framing
After rough MEP/gas inspections complete, framing and fire blocking complete
- 3
Final
All work complete per approved plans
Applies to: Deck Permit
- 1
Footing
Before concrete pour — verify 42-inch minimum depth and post footing dimensions
- 2
Framing
Ledger board attachment/flashing, joist hangers, post/beam connections
- 3
Final
Completed deck per approved plans
Applies to: Electrical Permit
- 1
Temporary Electric Service
After installation of the temporary meter base post with an approved means of grounding; may be installed by a licensed contractor or the homeowner
- 2
Rough Electric
After all wiring and boxes are installed, before walls closed
- 3
Final
All devices installed, system energized, before Certificate of Occupancy
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
After all venting and ductwork installed, before walls closed
- 2
Gas
After gas piping installed, supported, and under air test
- 3
Final
Equipment operational, combustion air and venting verified
Applies to: Solar PV Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before cover
- 2
Final — Structural/Racking
Panel mounting, racking attachment, roof penetration sealing verified
- 3
Final — Electrical
All connections, inverter, and interconnection point verified
Applies to: Demolition Permit
- 1
Pre-Demolition Utility Disconnects
Verification that electrical service line is disconnected and plumbing is capped off at the street before demolition
- 2
Final
Site cleared, lot restored per code requirements
Applies to: EV Charger / EVSE Permit
- 1
Rough Electric
EVSE circuit wiring and boxes installed, before walls closed
- 2
Final
EVSE unit installed, circuit energized and verified
Applies to: Fire Sprinkler System Permit
- 1
Sprinkler Rough-In
CCFD construction inspection of sprinkler piping before concealment, per CCFD's published inspection-type list; schedule at least 48 hours in advance via (307) 682-5319
- 2
Sprinkler Hydro (Hydrostatic Test)
CCFD hydrostatic pressure test of the completed sprinkler system, per CCFD's published inspection-type list
Final inspection only: Certificate of Occupancy / Change of Use, Fire Alarm System Permit, Roofing Permit (Reroof), Sign Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Gillette building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Gillette building permits
Get alerts for Gillette
We'll email you when Gillette's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.