Gillette building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Gillette, Wyoming.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
City Hall, 201 E. 5th St., 2nd Floor, Gillette, WY 82716
Phone
(307) 686-5260
Office hours
Mon–Fri (contact department for current hours); permits/plans/licenses/inspections managed via EnerGov Self Service online portal (registration required)

Published scheduling rules

  • Call the Inspection Line before 7:00 a.m. to get a same-day inspection; field inspectors are generally in the office 8–9 a.m. and 1–2 p.m. (Residential Building Permit (New Construction))
  • CCFD inspection scheduling requires at least 48 hours advance notice (call (307) 682-5319); published CCFD construction-inspection types for sprinkler work include "sprinkler rough in" and "sprinkler hydro" (Fire Sprinkler System Permit)
  • CCFD inspection scheduling requires at least 48 hours advance notice (call (307) 682-5319) (Fire Alarm System Permit)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Open Hole Letter / Footing

    Open Hole Letter sent to Building Inspection before footing inspection; soils engineer verification of footing/foundation type on file; rebar tied before concrete pour

  2. 2

    Foundation Wall

    After forms and rebar tied, before concrete placed

  3. 3

    Damp-Proofing / Drain Tile

    Before backfill placed around foundation or crawl space walls

  4. 4

    Underground Plumbing

    After all underground waste/vent/water piping installed and under test, before backfill/concrete

  5. 5

    Sill Plate

    When sill plate and sill seal are bolted in place, before floor system installed

  6. 6

    Rough Plumbing / Rough Electric / Rough Mechanical / Gas

    After respective waste/vent/water piping, wiring/boxes, venting/ductwork, and gas piping are installed and (for gas) under air test

  7. 7

    Exterior Vapor Barrier, Windows & Doors Flashing, Rough Framing

    After rough MEP/gas inspections complete, roofing done, framing and fire blocking complete, structure weather-tight

  8. 8

    Insulation

    After framing, before drywall on walls (sprayed ceiling insulation inspected at final)

  9. 9

    Sewer and Water

    After sewer and water lines installed, before backfill

  10. 10

    Final / Certificate of Occupancy

    Prior to moving furnishings into the building; tap fees must be paid when the permit is issued

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Footings/foundation before concrete pour, per soils engineer verification

  2. 2

    Framing

    Structural framing per applicable district's Accessory Structure setback/height standards

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Commercial Tenant Improvement / Commercial Building Permit

  1. 1

    Foundation / Footing

    Per stamped structural plans, before concrete pour

  2. 2

    Rough MEP / Fire

    Electrical, plumbing, mechanical, and fire suppression rough-in before walls closed

  3. 3

    Final — Building Inspection

    All work complete per approved plans

  4. 4

    TCO / CO

    Temporary Certificate of Occupancy or Certificate of Occupancy issued by Building Inspection after Council acceptance of utilities (if applicable) and FLC (Final Location Certificate) submittal to Planning/GIS

Applies to: Plumbing Permit

  1. 1

    Underground Plumbing

    After under-ground waste, vent, and water piping installed and pressure tested, before backfill/concrete

  2. 2

    Rough Plumbing

    After all waste, vent, and water piping installed, before walls closed

  3. 3

    Sewer and Water

    After sewer and water service lines installed, before backfill

  4. 4

    Final

    All fixtures connected, ready for occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing / Foundation (if new footings)

    Before concrete pour, per soils engineer verification

  2. 2

    Rough Plumbing / Electric / Mechanical / Gas

    Before walls closed

  3. 3

    Rough Framing

    After rough MEP/gas complete and structure weather-tight

  4. 4

    Final

    All work complete per approved plans

Applies to: Basement Finish Permit

  1. 1

    Rough Plumbing / Rough Electric / Rough Mechanical

    Before walls closed

  2. 2

    Rough Framing

    After rough MEP/gas inspections complete, framing and fire blocking complete

  3. 3

    Final

    All work complete per approved plans

Applies to: Deck Permit

  1. 1

    Footing

    Before concrete pour — verify 42-inch minimum depth and post footing dimensions

  2. 2

    Framing

    Ledger board attachment/flashing, joist hangers, post/beam connections

  3. 3

    Final

    Completed deck per approved plans

Applies to: Electrical Permit

  1. 1

    Temporary Electric Service

    After installation of the temporary meter base post with an approved means of grounding; may be installed by a licensed contractor or the homeowner

  2. 2

    Rough Electric

    After all wiring and boxes are installed, before walls closed

  3. 3

    Final

    All devices installed, system energized, before Certificate of Occupancy

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    After all venting and ductwork installed, before walls closed

  2. 2

    Gas

    After gas piping installed, supported, and under air test

  3. 3

    Final

    Equipment operational, combustion air and venting verified

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final — Structural/Racking

    Panel mounting, racking attachment, roof penetration sealing verified

  3. 3

    Final — Electrical

    All connections, inverter, and interconnection point verified

Applies to: Demolition Permit

  1. 1

    Pre-Demolition Utility Disconnects

    Verification that electrical service line is disconnected and plumbing is capped off at the street before demolition

  2. 2

    Final

    Site cleared, lot restored per code requirements

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electric

    EVSE circuit wiring and boxes installed, before walls closed

  2. 2

    Final

    EVSE unit installed, circuit energized and verified

Applies to: Fire Sprinkler System Permit

  1. 1

    Sprinkler Rough-In

    CCFD construction inspection of sprinkler piping before concealment, per CCFD's published inspection-type list; schedule at least 48 hours in advance via (307) 682-5319

  2. 2

    Sprinkler Hydro (Hydrostatic Test)

    CCFD hydrostatic pressure test of the completed sprinkler system, per CCFD's published inspection-type list

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Gillette building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Gillette building permits

Get alerts for Gillette

We'll email you when Gillette's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.