Page building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Page, Arizona.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Page City Hall, 697 Vista Avenue / P.O. Box 1180, Page, AZ 86040
- Phone
- 928-645-4266
- bslavens@pageaz.gov
- Office hours
- Building Official: Brett Slavens (bslavens@pageaz.gov, 928-645-4266, fax 928-645-4265). Main City line: 928-645-8861. Applications are submitted via the City of Page Building Permit Application (paper form, PO Box 1180 / 697 Vista Avenue) or through the online iWorQ Building Permit Application Portal (pageaz_permit.portal.iworq.net/portalhome/pageaz_permit). Final inspections must be scheduled at least 24 hours in advance, and final inspection/approval is required before occupying any room.
- Website
- Official site
Inspection sequence
Applies to: Plumbing Permit
- 1
Underground/Slab
Before concrete pour — verify pipe slope, materials, cleanouts
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
Fixtures connected, backwater valve and grease interceptor (where required) verified, no leaks
Applies to: Residential Addition / Remodel Permit
- 1
Foundation/Footing
Required before concrete pour for additions
- 2
Framing
Structural connections to existing structure
- 3
Final
Completed work verified against approved plans before occupancy
Applies to: Residential Building Permit (New Construction)
- 1
Foundation/Footing
Before concrete pour; verify subsoil drain lines around perimeter of below-grade floors per 2006 IBC Section 1807.4 as locally referenced
- 2
Framing
Structural framing, connections, egress per 2018 IRC and City of Page design criteria
- 3
Final
All work complete per approved plans; final inspection and approval required prior to occupying any room. Schedule at least 24 hours in advance
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed
- 2
Final
Devices installed, panel labeled, protections verified per 2017 NEC
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
Circuit wiring, box placement, and panel connections before walls are closed
- 2
Final
EVSE installed, protections verified per 2017 NEC
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and equipment placement before walls closed
- 2
Final
Equipment operational, clearances and combustion air verified
Applies to: Residential Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified per 2017 NEC
Final inspection only: Demolition Permit, Re-Roofing Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Page building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.