Commercial Building Permit — Page, Arizona · Requirements sheet
Verified 2026-08-01 · Source: https://cityofpage.org/departments/building-and-safety/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Page, Arizona
Required for new commercial building construction and for exterior remodeling/expansion of commercial uses in the City of Page, reviewed against the 2018 IBC and City amendments. Unlike residential construction, most commercial development must first pass Site Plan Review Committee (SPRC) approval — required by Zoning Code § 152.095(B) before any building permit can even be submitted — before the same generic City of Page Building Permit Application and Table 1-A valuation fee schedule used for every other permit type in this record is used to pull the actual building permit. Tenant improvement (interior remodeling of an existing commercial building) is not a separate permit type or fee schedule: it uses the identical Building Permit Application and Table 1-A fees as new commercial construction, and Zoning Code § 152.095(A)(1)(b) explicitly exempts 'interior remodeling only of commercial and multi-family structures' from the SPRC gate entirely (as does an exterior addition/modification under 500 sq ft or 10% of gross floor area, whichever is less, per § 152.095(A)(1)(c)).
Verified 2026-08-01 · Source
When you need this permit
- Building permit required for all new commercial building construction and for exterior remodeling/expansion of commercial uses, reviewed against the 2018 IBC (Chapters 1-35, with City of Page amendments) and ICC A117.1 (2009) accessibility standards as adopted by the City of Page
- 'Commercial development' is defined by Zoning Code § 152.095(B) as 'any residential development larger than a single-family detached residence on a single lot, and any commercial or industrial building or development'
- Per § 152.095(A)(1) and (B): commercial developments (new construction, major subdivisions, and exterior remodeling/expansion of commercial uses) require Site Plan Review Committee (SPRC) review and approval before any building permit can be submitted for review. Exempt from SPRC (but not from the underlying building permit): interior remodeling only of commercial structures (§ 152.095(A)(1)(b)); exterior modifications/additions that do not increase gross floor area by more than 500 sq ft or 10%, whichever is less (§ 152.095(A)(1)(c))
- Complete SPRC site plan package required per § 152.095(B)(1)-(2): a completed City of Page application for construction plan submittal; one electronic PDF of the complete site plan; two bound sets on 24"x36" white-background paper; supporting documentation/studies/reports; and, if the development requires fire sprinklers or fire protection, a third complete paper set for the Fire Marshal's review and approval. Partial or incomplete submittals, or submittals split across entities, are rejected and returned to the applicant at their expense
- SPRC review covers: compliance with the Zoning Code, Maricopa Association of Governments (MAG SPEC) design standards, ADA specifications, and the adopted IBC (SPRC as a whole); street plans, drainage, and floodplain (Public Works Director); water/sewer and electric utilities (Page Utility Enterprises); easement work (Western Area Power Authority); rights-of-way/intersection design where the site abuts a state highway (ADOT); and Fire, Police, and Ambulance Departments as appropriate
- Per § 152.095(B)(3), city staff schedule a formal SPRC meeting to be held within 14 days of determining the site plan application complete, held on the closest Thursday or another day the SPRC deems appropriate; the applicant or their civil engineer must attend in person or via videoconference to answer committee questions
- Once SPRC (and the Fire Marshal and any other required outside agency) approve the site plan, the applicant works with the City's Chief Building Official (CBO) to pull the building permit(s) required for construction, submitted on the same generic City of Page Building Permit Application used for every other permit type in this record, with 'NEW' (or 'ADDITION'/'ALTERATION' for remodel/TI scope) selected under Class of Work
- Per § 152.095(D): a site plan approval becomes void if a building permit has not been issued within one year of approval; a one-time three-month extension may be granted by the Director if requested before the one-year deadline, and additional extensions require Planning and Zoning Commission approval
- Per § 152.095(G): the CBO may issue a Temporary Certificate of Occupancy (30, 60, or 90 days, at the CBO's discretion) or a final Certificate of Occupancy; no occupancy of any structure is allowed until all required improvements are complete and CBO-approved
- Automatic fire sprinkler systems are required in any building (commercial included) exceeding 4,000 sq ft, per City Ordinances 548-09, 566-10, and 666-19 (City Code Chapter 92) — a threshold many hotel/hospitality and larger retail projects in Page will exceed
- Hotel/Motel-specific zoning standards apply during site plan/SPRC review (Zoning Code Table 4.2 series): off-street parking is calculated as 1 space per guest room, plus 1 space per 4 persons of the banquet room's maximum capacity (if a banquet room is present), plus 2 spaces per 3 employees, plus 1 RV/boat/bus space per 6 guest rooms (3-space minimum); hotel/motel parking stalls are allowed a reduced 9-foot width; and 4 passenger loading/unloading spaces are required for a Hotel or Motel use (Table 4.2-4). 'HOTEL or MOTEL' is defined in the Zoning Code as 'a facility with continuous on-site management with nine or more sleeping rooms that are intended to be occupied by guests for a fee'
- Owner/Builder permits are allowed for residential projects only (per this file's localAmendments); commercial project work must be performed by licensed contractors per A.R.S. § 32-1169 Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Site Plan Review Committee (SPRC) Review (pre-permit gate)
Required before a building permit can be submitted for new commercial construction or exterior remodel/expansion exceeding the 500 sq ft/10% GFA exemption threshold; not required for interior-only tenant improvement work. Scheduled within 14 days of administrative completeness per § 152.095(B)(3)
- 2
Foundation/Footing
Before concrete pour; per 2018 IBC and City of Page design criteria
- 3
Framing / Structural / MEP Rough-In
Structural framing, connections, and mechanical/electrical/plumbing rough-in verified before concealment
- 4
Final / Certificate of Occupancy
All work complete per approved plans; a Temporary Certificate of Occupancy (30/60/90 days, CBO discretion) or final Certificate of Occupancy is required before occupancy, per § 152.095(G)
See the full Page inspection guide — scheduling & re-inspection fees →
Tips
- Page does not have a separate tenant improvement permit or fee schedule — TI work uses the identical City of Page Building Permit Application and Table 1-A valuation fee as new commercial construction. The one genuine procedural difference: interior-only remodeling of a commercial structure is explicitly EXEMPT from the Site Plan Review Committee gate under Zoning Code § 152.095(A)(1)(b) (as is an exterior addition/modification under 500 sq ft or 10% of gross floor area, whichever is less, per § 152.095(A)(1)(c)) — so most TI-scale projects can skip straight to the standard Building Permit Application, while new construction or a larger exterior expansion cannot.
- Unlike residential permits, commercial developments must clear Site Plan Review Committee approval BEFORE a building permit can even be submitted (§ 152.095(B)) — budget for the $500 Site Plan Review fee and the SPRC's 14-business-day meeting-scheduling window as a distinct front-end step, separate from the building permit's own (unpublished) review time.
- As of August 2026, no numeric end-to-end review-timeline figure is published for the commercial building permit itself — only the 14-day SPRC meeting-scheduling requirement is a verified, commercial-specific number, and it covers just the scheduling step, not the full review-to-decision process. Call the Building Safety Department (928-645-4266) or Planning & Zoning for a current estimate.
- Given Page's tourism/hospitality economy, note two hotel-specific requirements checked at site plan review: the Zoning Code's dedicated Hotel/Motel parking formula (1 space per guest room + banquet-room and employee add-ons + RV/bus parking) and passenger loading-space requirement (4 spaces), and the City's 4,000-sq-ft fire-sprinkler trigger (Ordinance 666-19), which most hotel-scale buildings will exceed.
- A site plan approval expires if a building permit is not issued within one year (one-time 3-month extension available from the Director); the building permit itself becomes null and void if work is not commenced within 180 days or is suspended for 180 days, per the standard rule applied to every permit type in this file.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Page building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Page.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Page
Commercial Building Permit in other cities
Compare commercial building permit fees across Arizona →
Look up this fee in a different city →