Skip to main content
PermitBase

Demolition Permit in Page, Arizona

Required for demolition of any residential or commercial structure in the City of Page, processed through the standard Building Permit Application. No demolition-specific published fee line was found; demolition is billed on the same Table 1-A valuation basis as other Building Department permits.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required before demolishing a residential or commercial structure within Page city limits (application 'Class of Work' includes a 'Remove' option on the standard Building Permit Application)
  • Property owner and general contractor information required on the Building Permit Application
  • Coordination with utility providers (Water/Sewer: 928-645-4214; Electrical/PEU: 928-645-2419; Propane/SemStream: 928-645-2391) for service termination is expected as part of standard demolition practice, though no City of Page-published demolition-specific checklist was found
  • Call Arizona Blue Stake (1-800-STAKE-IT / 811) before any excavation, per the notice printed on the City of Page Building Permit Application

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Table 1-A (Total Valuation)City of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4. No separately itemized demolition-only fee line was found; demolition is billed on the general valuation schedule based on the value/scope of the demolition work.
$23.50 (valuation $1-$500) through $5,608.75 + $3.65 per additional $1,000 above $1,000,000

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit permit actually take in Page?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Verifies utility termination and site condition after demolition is complete

See the full Page inspection guide — scheduling & re-inspection fees →

Tips

  • As of July 2026, the City of Page does not appear to publish a permit-specific plan review turnaround time for demolition permits on its public website. The City publishes its general Building Permit Application (which includes a 'Remove' class-of-work option) and fee schedule, but not category-specific review timelines or a dedicated demolition checklist. There is no verifiable online source for this — call the City of Page Building Safety Department directly at 928-645-4266.
  • No City of Page-published requirement for a separate County Air Quality/NESHAP asbestos clearance step was found (unlike some Maricopa County cities) — confirm directly with Coconino County and ADEQ whether asbestos survey/NESHAP notification applies to your specific structure before demolition.
  • Call Arizona Blue Stake (811 / 1-800-STAKE-IT) before any excavation, per the notice printed directly on the City's Building Permit Application form.

Frequently asked questions

A standard City of Page Building Permit Application with 'Remove' selected under Class of Work, billed on the Table 1-A valuation fee schedule. No dedicated demolition checklist or flat demolition fee was found published by the City as of July 2026 — contact the Building Safety Department (928-645-4266) for project-specific requirements, including whether Coconino County or ADEQ asbestos/air-quality clearance applies to your structure.

In Page, the published Building Permit Fee — Table 1-A (Total Valuation) is: $23.50 (valuation $1-$500) through $5,608.75 + $3.65 per additional $1,000 above $1,000,000. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Page does not publish a plan-review timeline for this permit. Contact City of Page Building Safety Department at 928-645-4266 for current turnaround.

You'll need: City of Page Building Permit Application. See the required-documents checklist on this page for details on each.

Page requires 1 inspection(s) for a demolition permit, in order: Final. Schedule each through City of Page Building Safety Department (928-645-4266).

Apply through City of Page Building Safety Department at Page City Hall, 697 Vista Avenue / P.O. Box 1180, Page, AZ 86040. Phone: 928-645-4266, email: bslavens@pageaz.gov. Office hours: Building Official: Brett Slavens (bslavens@pageaz.gov, 928-645-4266, fax 928-645-4265). Main City line: 928-645-8861. Applications are submitted via the City of Page Building Permit Application (paper form, PO Box 1180 / 697 Vista Avenue) or through the online iWorQ Building Permit Application Portal (pageaz_permit.portal.iworq.net/portalhome/pageaz_permit). Final inspections must be scheduled at least 24 hours in advance, and final inspection/approval is required before occupying any room.. Official information: https://cityofpage.org/departments/building-and-safety/.

Page, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Page runs its own Building Safety Department and independently adopts and administers its own construction codes; it does not defer permitting to Coconino County. Source: City of Page Building and Safety Department page (cityofpage.org/departments/building-and-safety/).; 2018 International Building Code (IBC), Chapters 1-35, with amendments to Chapter 9 and Appendix Chapters B, H, and I, adopted by the City of Page as its uniform building code. Source: City of Page Building and Safety Department page.; 2018 International Residential Code (IRC), Chapters 1-44, with Appendix Chapters A, B, C, D, H, and P adopted, governing one- and two-family dwelling construction. Source: City of Page Building and Safety Department page.; 2018 International Plumbing Code (IPC), Chapters 1-15, with Appendix E adopted. Source: City of Page Building and Safety Department page.; 2018 International Fuel Gas Code, Chapters 1-8, with Appendix Chapters A, B, and C adopted. Source: City of Page Building and Safety Department page.; 2018 International Mechanical Code (IMC), Chapters 1-15, with Appendix Chapters A and B adopted. Source: City of Page Building and Safety Department page.; 2018 International Existing Building Code, Chapters 1-16, with Appendix C adopted. Source: City of Page Building and Safety Department page.; 2018 International Pool and Spa Code, Chapters 1-11, with Appendix Chapters A, B, C, and D adopted. Source: City of Page Building and Safety Department page.; 2017 National Electrical Code (NEC), Chapters 1-9, with Annexes A-E adopted (note: the electrical code cycle is one edition behind the 2018 ICC set). Source: City of Page Building and Safety Department page.; 2012 International Energy Conservation Code (IECC), Chapters 1-6, adopted; governs energy-efficiency requirements for the City of Page. Source: City of Page Building and Safety Department page.; 2018 International Fire Code (IFC) Chapter 61 adopted specifically for LP Gas regulation, in addition to ANSI Standards 2009 combined with the 2018 IBC. Source: City of Page Building and Safety Department page.; ICC A117.1 / ANSI Standards 2009 accessibility provisions apply in conjunction with the 2018 IBC, alongside the federal Americans with Disabilities Act (ADA) standards. Source: City of Page Building and Safety Department page.; Local ordinance amendments layered onto the adopted ICC codes: Ordinance 666-19 amending Chapter 92 for automatic fire sprinkler systems; City Code Article 9-5, Sections 9-5-1 through 9-5-17, regulating wood-burning stoves; City Code Article 11-4-1(B) requiring sewer backwater valves; City Code Article 11-5-2 requiring grease interceptors. Source: City of Page Building and Safety Department page.; Manufactured homes and factory-built buildings (FBBs) are licensed and permitted through a joint state/City structure: the Arizona Department of Fire, Building and Life Safety (Office of Manufactured Housing) sets manufacturer/installer/retailer licensing and issues State/IGA installation permits (state fee schedule effective July 1, 2022 - June 30, 2023, per City of Page Consolidated Fee Schedule, Building Department - Manufactured Home Fees, pp. 6-7), while the City of Page Building Safety Department handles local site/foundation/utility compliance. Source: City of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023).; A building permit may not be issued prior to receiving verbal approval from Coconino County Health Department (Page office: 928-608-6108 x13; main office: 928-679-8760) — relevant for projects involving onsite wastewater/septic systems. Source: City of Page Building and Safety Department page.. Local amendments apply — see the Page overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Page building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.