Fire Sprinkler / Fire Alarm Permit in Page, Arizona
The City of Page adopted the 2018 International Fire Code, with local amendments requiring an automatic sprinkler system throughout all buildings of 4,000 square feet or greater. Fire system permits are issued on a valuation basis using the 'Valuation of Fire System' table in the City's Consolidated Fee Schedule. Where a development requires fire sprinklers or fire protection, a third complete set of paper plans must be submitted for the Fire Marshall's review and approval, and the Building Permit Application carries a Fire Dept approval box and a sprinklers entry that must be completed.
Verified 2026-08-15 · Source
When you need this permit
- The 2018 International Fire Code, together with Appendices A, B, C, D, E, F, H and I, is adopted as the City Fire Code (Page Code of Ordinances § 92.02; Ord. 548-09, passed 6-11-2009; Ord. 666-19, passed 12-11-2019)
- The 2017 edition of the National Fire Protection Association Standards is adopted (§ 92.03)
- An automatic sprinkler system must be installed throughout all buildings 4,000 square feet or greater in total area; fire resistant walls and barriers do not define separate buildings for this purpose (§ 92.04(A))
- An addition to any existing non-sprinklered building or structure which expands the total area to 4,000 square feet or greater must contain an automatic sprinkler system (§ 92.04(B))
- With the exception of special hazard areas as approved by the Fire Chief, if any fire area in a building or structure is provided with fire sprinklers — whether required or not — all fire areas in the building or structure must be provided with fire sprinklers (§ 92.04(C))
- All buildings requiring an exterior lock box for fire department access must install a KNOX BOX in an approved location or locations; existing buildings have up to five years to comply upon approval of the Fire Chief (§ 92.04(D))
- Where the development requires fire sprinklers or fire protection due to code requirements, a third complete set of paper plans must be submitted for the Fire Marshall's review and approval, in addition to the electronic PDF set and the two bound paper sets (§ 152.095(B)(1)(e) and § 152.095(F)(1)(e))
- Building permit application packets must include everything required by the most current adopted editions of the International Building Codes, the International Residential Codes, and the Fire, Electrical and Plumbing Codes, the MAG SPECS, and the City Zoning and Subdivision Codes, as amended and adopted by City Council from time to time (§ 152.095(F)(2))
- For commercial developments, the site plan must be approved by the Site Plan Review Committee — which includes the Fire, Police and Ambulance Departments as appropriate — and by the Fire Marshall where required, before building permits can be pulled (§ 152.095(B)(4)(h) and (B)(5))
- The City of Page Building Permit Application requires the FIRE DEPT approval box to be marked required and received, and carries a SPRINKLERS entry alongside the OCCUPANCY and valuation entries
- Fire permit fees are established periodically by the City Council by separate resolution (§ 92.05)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Fire Marshall plan review
The third complete paper plan set is routed to the Fire Marshall for review and approval where the development requires fire sprinklers or fire protection (§ 152.095(B)(1)(e) and (F)(1)(e)). Site plan approval is not complete until the Fire Marshall has approved where required (§ 152.095(B)(5)).
- 2
Chief Building Official review and permit issuance
Once the site plan has received approval from the SPRC, the Fire Marshall where required, and any other required outside agencies, the applicant works with the Chief Building Official to pull the building permits required for construction (§ 152.095(B)(5)). The Building Permit Application's FIRE DEPT approval box must be marked received.
- 3
Fire system field inspection
Field inspection of the installed fire sprinkler or fire alarm system by the Page Fire Department / Building Safety Department. Re-inspections and inspections outside normal business hours are charged at $47.00 per hour under the fire fee table. Schedule inspections at least 24 hours in advance.
- 4
Final inspection and Certificate of Occupancy
No occupancy of any structure is allowed until all required improvements are complete and approved by the Chief Building Official, who is the City's representative authorized to issue a Temporary Certificate of Occupancy (30, 60 or 90 days at the CBO's discretion) or a final Certificate of Occupancy (§ 152.095(G)).
See the full Page inspection guide — scheduling & re-inspection fees →
Tips
- The 4,000 square foot sprinkler threshold is a Page local amendment, not a base International Fire Code requirement, and it is measured on total area with fire resistant walls and barriers expressly not counting as building separations (§ 92.04(A)). An addition that pushes an existing non-sprinklered building over that threshold triggers sprinklers for the whole building (§ 92.04(B)).
- Partial sprinklering is not allowed: if any fire area in a building is sprinklered — whether required or not — every fire area in that building must be sprinklered, except for special hazard areas approved by the Fire Chief (§ 92.04(C)).
- The Fire System valuation table is separate from the Building Permit Table 1-A even though the bands and amounts are identical — the fire fee is calculated on the valuation of the fire system, not on total construction valuation.
- Existing buildings that require an exterior lock box have up to five years from the requirement to install a KNOX BOX, subject to Fire Chief approval (§ 92.04(D)).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-15.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Page building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Page
Fire Sprinkler / Fire Alarm Permit in other cities
Compare fire sprinkler / fire alarm permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Page project checklist
Describe your project once and get every permit, document, and fee it triggers in Page — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →