Fire Sprinkler / Fire Alarm Permit in Page, Arizona

The City of Page adopted the 2018 International Fire Code, with local amendments requiring an automatic sprinkler system throughout all buildings of 4,000 square feet or greater. Fire system permits are issued on a valuation basis using the 'Valuation of Fire System' table in the City's Consolidated Fee Schedule. Where a development requires fire sprinklers or fire protection, a third complete set of paper plans must be submitted for the Fire Marshall's review and approval, and the Building Permit Application carries a Fire Dept approval box and a sprinklers entry that must be completed.

Verified 2026-08-15 · Source

When you need this permit

  • The 2018 International Fire Code, together with Appendices A, B, C, D, E, F, H and I, is adopted as the City Fire Code (Page Code of Ordinances § 92.02; Ord. 548-09, passed 6-11-2009; Ord. 666-19, passed 12-11-2019)
  • The 2017 edition of the National Fire Protection Association Standards is adopted (§ 92.03)
  • An automatic sprinkler system must be installed throughout all buildings 4,000 square feet or greater in total area; fire resistant walls and barriers do not define separate buildings for this purpose (§ 92.04(A))
  • An addition to any existing non-sprinklered building or structure which expands the total area to 4,000 square feet or greater must contain an automatic sprinkler system (§ 92.04(B))
  • With the exception of special hazard areas as approved by the Fire Chief, if any fire area in a building or structure is provided with fire sprinklers — whether required or not — all fire areas in the building or structure must be provided with fire sprinklers (§ 92.04(C))
  • All buildings requiring an exterior lock box for fire department access must install a KNOX BOX in an approved location or locations; existing buildings have up to five years to comply upon approval of the Fire Chief (§ 92.04(D))
  • Where the development requires fire sprinklers or fire protection due to code requirements, a third complete set of paper plans must be submitted for the Fire Marshall's review and approval, in addition to the electronic PDF set and the two bound paper sets (§ 152.095(B)(1)(e) and § 152.095(F)(1)(e))
  • Building permit application packets must include everything required by the most current adopted editions of the International Building Codes, the International Residential Codes, and the Fire, Electrical and Plumbing Codes, the MAG SPECS, and the City Zoning and Subdivision Codes, as amended and adopted by City Council from time to time (§ 152.095(F)(2))
  • For commercial developments, the site plan must be approved by the Site Plan Review Committee — which includes the Fire, Police and Ambulance Departments as appropriate — and by the Fire Marshall where required, before building permits can be pulled (§ 152.095(B)(4)(h) and (B)(5))
  • The City of Page Building Permit Application requires the FIRE DEPT approval box to be marked required and received, and carries a SPRINKLERS entry alongside the OCCUPANCY and valuation entries
  • Fire permit fees are established periodically by the City Council by separate resolution (§ 92.05)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Fire System Permit Fee — Valuation of Fire SystemCity of Page 2026 Consolidated Fee Schedule (Adopted by Resolution 1345-26 on June 10, 2026), 'Valuation of Fire System / Fee' table, printed page 5 (the Fire Permit and Inspection Fees page immediately following the Building Inspection and Permit Fees page). Read from a 200 dpi rendered page image rather than extracted text, and the image confirms the row pairings. The bands and amounts are identical to the Building Permit Fee Table 1-A bands, but applied to the valuation of the fire system rather than total construction valuation. Authorised by Page Code of Ordinances § 92.05, under which the City Council periodically establishes fire permit fees by separate resolution.
$23.50 (valuation $1.00 to $500.00); $23.50 for the first $500.00 plus $3.05 for each additional $100.00 or fraction thereof to and including $2,000.00; $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00 or fraction thereof to and including $25,000.00; $391.25 for the first $25,000.00 plus $10.10 for each additional $1,000.00 or fraction thereof to and including $50,000.00; $643.75 for the first $50,000.00 plus $7.00 for each additional $1,000.00 or fraction thereof to and including $100,000.00; $993.75 for the first $100,000.00 plus $5.60 for each additional $1,000.00 or fraction thereof to and including $500,000.00; $3,233.75 for the first $500,000.00 plus $4.75 for each additional $1,000.00 or fraction thereof to and including $1,000,000.00; $5,608.75 for the first $1,000,000.00 plus $3.65 for each additional $1,000.00 or fraction thereof
Fire Plan Review FeeCity of Page 2026 Consolidated Fee Schedule (Resolution 1345-26, adopted June 10, 2026), printed page 5, note at the foot of the fire fee table: 'Plan Review Fees: When submittal documents are required, a plan review fee shall be paid at the time of submitting documents for plan review. Said plan review shall be 65 percent of the building permit fee.' Read from the rendered page image.
65 percent of the building permit fee
Annual fire renewable permitCity of Page 2026 Consolidated Fee Schedule (Resolution 1345-26, adopted June 10, 2026), fire 'Other Inspections and Fees: Hourly Charge' table, item 5, printed page 5. Read from the rendered page image.
$47.00 per category
Fire Activity ReportCity of Page 2026 Consolidated Fee Schedule (Resolution 1345-26, adopted June 10, 2026), fire 'Other Inspections and Fees: Hourly Charge' table, item 6, printed page 5 — excludes non-commercial burn permits. Read from the rendered page image.
$47.00 per permit
Fire re-inspection / after-hours / unlisted inspection / additional plan reviewCity of Page 2026 Consolidated Fee Schedule (Resolution 1345-26, adopted June 10, 2026), fire 'Other Inspections and Fees: Hourly Charge' table, items 1 through 4, printed page 5. Inspections outside normal business hours carry a two-hour minimum charge; inspections for which no fee is specifically indicated carry a one-half hour minimum. The published note reads: 'Or the total hourly cost to the jurisdiction, whichever is the greatest. This cost shall include supervision, overhead, equipment, hourly wages, and fringe benefits for the employees involved.' Use of outside consultants for plan checking or inspections, or both, is charged at actual costs, including administrative and overhead costs.
$47.00 per hour

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler / Fire Alarm Permit permit actually take in Page?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Marshall plan review

    The third complete paper plan set is routed to the Fire Marshall for review and approval where the development requires fire sprinklers or fire protection (§ 152.095(B)(1)(e) and (F)(1)(e)). Site plan approval is not complete until the Fire Marshall has approved where required (§ 152.095(B)(5)).

  2. 2

    Chief Building Official review and permit issuance

    Once the site plan has received approval from the SPRC, the Fire Marshall where required, and any other required outside agencies, the applicant works with the Chief Building Official to pull the building permits required for construction (§ 152.095(B)(5)). The Building Permit Application's FIRE DEPT approval box must be marked received.

  3. 3

    Fire system field inspection

    Field inspection of the installed fire sprinkler or fire alarm system by the Page Fire Department / Building Safety Department. Re-inspections and inspections outside normal business hours are charged at $47.00 per hour under the fire fee table. Schedule inspections at least 24 hours in advance.

  4. 4

    Final inspection and Certificate of Occupancy

    No occupancy of any structure is allowed until all required improvements are complete and approved by the Chief Building Official, who is the City's representative authorized to issue a Temporary Certificate of Occupancy (30, 60 or 90 days at the CBO's discretion) or a final Certificate of Occupancy (§ 152.095(G)).

See the full Page inspection guide — scheduling & re-inspection fees →

Tips

  • The 4,000 square foot sprinkler threshold is a Page local amendment, not a base International Fire Code requirement, and it is measured on total area with fire resistant walls and barriers expressly not counting as building separations (§ 92.04(A)). An addition that pushes an existing non-sprinklered building over that threshold triggers sprinklers for the whole building (§ 92.04(B)).
  • Partial sprinklering is not allowed: if any fire area in a building is sprinklered — whether required or not — every fire area in that building must be sprinklered, except for special hazard areas approved by the Fire Chief (§ 92.04(C)).
  • The Fire System valuation table is separate from the Building Permit Table 1-A even though the bands and amounts are identical — the fire fee is calculated on the valuation of the fire system, not on total construction valuation.
  • Existing buildings that require an exterior lock box have up to five years from the requirement to install a KNOX BOX, subject to Fire Chief approval (§ 92.04(D)).

Frequently asked questions

If the development requires fire sprinklers or fire protection due to code requirements, a third complete set of paper plans must be submitted for the Fire Marshall's review and approval, on top of the standard submittal of one electronic PDF version and two bound sets on 24 inch by 36 inch paper with a white background. This applies both to commercial site plan submittals under § 152.095(B)(1)(e) and to building construction plan submittals under § 152.095(F)(1)(e). The City will not make paper copies for you to complete your package.

In Page, the published Fire System Permit Fee — Valuation of Fire System is: $23.50 (valuation $1.00 to $500.00); $23.50 for the first $500.00 plus $3.05 for each additional $100.00 or fraction thereof to and including $2,000.00; $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00 or fraction thereof to and including $25,000.00; $391.25 for the first $25,000.00 plus $10.10 for each additional $1,000.00 or fraction thereof to and including $50,000.00; $643.75 for the first $50,000.00 plus $7.00 for each additional $1,000.00 or fraction thereof to and including $100,000.00; $993.75 for the first $100,000.00 plus $5.60 for each additional $1,000.00 or fraction thereof to and including $500,000.00; $3,233.75 for the first $500,000.00 plus $4.75 for each additional $1,000.00 or fraction thereof to and including $1,000,000.00; $5,608.75 for the first $1,000,000.00 plus $3.65 for each additional $1,000.00 or fraction thereof. Additional published fees: Fire Plan Review Fee — 65 percent of the building permit fee; Annual fire renewable permit — $47.00 per category; Fire Activity Report — $47.00 per permit; Fire re-inspection / after-hours / unlisted inspection / additional plan review — $47.00 per hour. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Page does not publish a plan-review timeline for this permit. Contact City of Page Building Safety Department at 928-645-4266 for current turnaround.

You'll need: City of Page Building Permit Application; Fire sprinkler / fire protection plans — third complete paper set for the Fire Marshall; One electronic version of the plans and specifications in PDF format; Two bound sets of the complete plans on 24 inch by 36 inch paper with a white background. Depending on your project, Page may also ask for: Supporting documentation, studies or reports in PDF format. See the required-documents checklist on this page for details on each.

Page requires 4 inspection(s) for a fire sprinkler / fire alarm permit, in order: Fire Marshall plan review, Chief Building Official review and permit issuance, Fire system field inspection, Final inspection and Certificate of Occupancy. Schedule each through City of Page Building Safety Department (928-645-4266).

Apply through City of Page Building Safety Department at Page City Hall, 697 Vista Avenue / P.O. Box 1180, Page, AZ 86040. Phone: 928-645-4266, email: bslavens@pageaz.gov. Office hours: Building Official: Brett Slavens (bslavens@pageaz.gov, 928-645-4266, fax 928-645-4265). Main City line: 928-645-8861. Applications are submitted via the City of Page Building Permit Application (paper form, PO Box 1180 / 697 Vista Avenue) or through the online iWorQ Building Permit Application Portal (pageaz_permit.portal.iworq.net/portalhome/pageaz_permit). Final inspections must be scheduled at least 24 hours in advance, and final inspection/approval is required before occupying any room.. Official information: https://cityofpage.org/departments/building-and-safety/.

Page, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Page runs its own Building Safety Department and independently adopts and administers its own construction codes; it does not defer permitting to Coconino County. Source: City of Page Building and Safety Department page (cityofpage.org/departments/building-and-safety/).; 2018 International Building Code (IBC), Chapters 1-35, with amendments to Chapter 9 and Appendix Chapters B, H, and I, adopted by the City of Page as its uniform building code. Source: City of Page Building and Safety Department page.; 2018 International Residential Code (IRC), Chapters 1-44, with Appendix Chapters A, B, C, D, H, and P adopted, governing one- and two-family dwelling construction. Source: City of Page Building and Safety Department page.; 2018 International Plumbing Code (IPC), Chapters 1-15, with Appendix E adopted. Source: City of Page Building and Safety Department page.; 2018 International Fuel Gas Code, Chapters 1-8, with Appendix Chapters A, B, and C adopted. Source: City of Page Building and Safety Department page.; 2018 International Mechanical Code (IMC), Chapters 1-15, with Appendix Chapters A and B adopted. Source: City of Page Building and Safety Department page.; 2018 International Existing Building Code, Chapters 1-16, with Appendix C adopted. Source: City of Page Building and Safety Department page.; 2018 International Pool and Spa Code, Chapters 1-11, with Appendix Chapters A, B, C, and D adopted. Source: City of Page Building and Safety Department page.; 2017 National Electrical Code (NEC), Chapters 1-9, with Annexes A-E adopted (note: the electrical code cycle is one edition behind the 2018 ICC set). Source: City of Page Building and Safety Department page.; 2012 International Energy Conservation Code (IECC), Chapters 1-6, adopted; governs energy-efficiency requirements for the City of Page. Source: City of Page Building and Safety Department page.; 2018 International Fire Code (IFC) Chapter 61 adopted specifically for LP Gas regulation, in addition to ANSI Standards 2009 combined with the 2018 IBC. Source: City of Page Building and Safety Department page.; ICC A117.1 / ANSI Standards 2009 accessibility provisions apply in conjunction with the 2018 IBC, alongside the federal Americans with Disabilities Act (ADA) standards. Source: City of Page Building and Safety Department page.; Local ordinance amendments layered onto the adopted ICC codes: Ordinance 666-19 amending Chapter 92 for automatic fire sprinkler systems; City Code Article 9-5, Sections 9-5-1 through 9-5-17, regulating wood-burning stoves; City Code Article 11-4-1(B) requiring sewer backwater valves; City Code Article 11-5-2 requiring grease interceptors. Source: City of Page Building and Safety Department page.; Manufactured homes and factory-built buildings (FBBs) are licensed and permitted through a joint state/City structure: the Arizona Department of Fire, Building and Life Safety (Office of Manufactured Housing) sets manufacturer/installer/retailer licensing and issues State/IGA installation permits (state fee schedule effective July 1, 2022 - June 30, 2023, per City of Page Consolidated Fee Schedule, Building Department - Manufactured Home Fees, pp. 6-7), while the City of Page Building Safety Department handles local site/foundation/utility compliance. Source: City of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023).; A building permit may not be issued prior to receiving verbal approval from Coconino County Health Department (Page office: 928-608-6108 x13; main office: 928-679-8760) — relevant for projects involving onsite wastewater/septic systems. Source: City of Page Building and Safety Department page.. Local amendments apply — see the Page overview page for the full list.

Page Code of Ordinances § 92.04(A) requires an automatic sprinkler system throughout all buildings 4,000 square feet or greater in total area, and states that fire resistant walls and barriers do not define separate buildings for this purpose. Section 92.04(B) extends this to additions: an addition to any existing non-sprinklered building or structure which expands the total area to 4,000 square feet or greater must contain an automatic sprinkler system. Section 92.04(C) then prohibits partial sprinklering — if any fire area in a building is provided with sprinklers, whether required or not, all fire areas must be, except for special hazard areas approved by the Fire Chief. These amendments were adopted by Ord. 548-09 and amended by Ord. 666-19, passed 12-11-2019.