Residential Building Permit (New Construction) in Page, Arizona

Required for new single-family and two-family dwelling construction in the City of Page. Reviewed against the 2018 IRC as adopted by the City. Applications are submitted via the City of Page Building Permit Application (paper) or the online iWorQ portal, and single-family dwellings are reviewed directly by the Chief Building Official rather than going through the commercial Site Plan Review Committee process.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for new single-family and two-family dwelling construction within Page city limits
  • Plans must comply with the 2018 IRC as adopted by the City of Page and local design criteria (115 MPH wind, Exposure C; Seismic Zone 2, Site Class D or per geotechnical report; 18-inch frost depth; 20 PSF snow load, no reduction)
  • Site/plot plan required showing property dimensions, distances between existing/proposed structures, distance from building to property lines, utility hook-up locations, street identification, and north arrow
  • House plans required: foundation plan with details, electrical plans with service panel location/size, fully dimensioned floor plan, equipment locations, floor framing (all levels), roof framing, elevation drawings, cross-sections, deck framing details, and livable square footage
  • Two sets of truss calculations from the manufacturer required
  • Two stamped sets of engineering specifications by an Arizona-registered engineer required where applicable
  • A building permit may not be issued prior to receiving verbal approval from Coconino County Health Department
  • Owner/Builder permits are allowed for residential projects only; any hired contractor must be licensed per A.R.S. § 32-1169 Owner-builderContractor
  • Wood sill-plates on concrete must be pressure-treated or foundation-grade redwood; footing reinforcing steel cannot be tied to metal grade stakes due to corrosive soil

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Table 1-A (Total Valuation)City of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023), Building Department — Table 1-A, Building Permit Fees, p.4
$23.50 (valuation $1-$500); $23.50 + $3.05 per additional $100 (or fraction) to $2,000; $69.25 + $14.00 per additional $1,000 (or fraction) to $25,000; $391.25 + $10.10 per additional $1,000 to $50,000; $643.75 + $7.00 per additional $1,000 to $100,000; $993.75 + $5.60 per additional $1,000 to $500,000; $3,233.75 + $4.75 per additional $1,000 to $1,000,000; $5,608.75 + $3.65 per additional $1,000 above $1,000,000
Plan Review FeeCity of Page Consolidated Fee Schedule, p.5 note: 'Plan Review Fees: When submittal documents are required, a plan review fee shall be paid at the time of submitting documents for plan review. Said plan review shall be 65 percent of the building permit fee.'
65% of the calculated Building Permit Fee
Additional Plan Review (changes/additions/revisions to plans)City of Page Consolidated Fee Schedule, p.4, Other Inspections and Fees item 4
$47.00 per hour
Re-inspection FeeCity of Page Consolidated Fee Schedule, p.4, Other Inspections and Fees items 2, 3, and 6
$47.00 per hour (minimum charge one-half hour for inspections with no specifically indicated fee; $54.00 per hour cited for other inspections/fees under item 6)
Inspection Outside Normal Business HoursCity of Page Consolidated Fee Schedule, p.4, Other Inspections and Fees item 1
$47.00 per hour, 2-hour minimum charge

Review timeline

Plan review
Not published — contact the department

How long did your Residential Building Permit (New Construction) permit actually take in Page?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour; verify subsoil drain lines around perimeter of below-grade floors per 2006 IBC Section 1807.4 as locally referenced

  2. 2

    Framing

    Structural framing, connections, egress per 2018 IRC and City of Page design criteria

  3. 3

    Final

    All work complete per approved plans; final inspection and approval required prior to occupying any room. Schedule at least 24 hours in advance

See the full Page inspection guide — scheduling & re-inspection fees →

Tips

  • As of July 2026, the City of Page does not appear to publish permit-specific plan review turnaround times for residential building permits on its public website. The City publishes permit requirements, fee schedules, and process information (Consolidated Fee Schedule; City of Page Building Permit Application; Zoning Code § 152.095), but not category-specific review timelines. Zoning Code § 152.095's 14-day SPRC scheduling requirement applies only to commercial developments — single-family dwellings are explicitly exempted from SPRC review and are reviewed directly by the Chief Building Official. There is no verifiable online source stating a residential building-permit turnaround time — call the City of Page Building Safety Department directly at 928-645-4266.
  • Single-family dwellings are reviewed only by the Chief Building Official/Director or designee and are explicitly exempt from the Site Plan Review Committee (SPRC) process that applies to commercial developments (Zoning Code § 152.095(A)(1)(a)).
  • Plan review fee (65% of the Table 1-A Building Permit Fee) is due at time of submittal, per the Consolidated Fee Schedule.
  • County Health verbal approval is a prerequisite the City checks before permit issuance — coordinate with Coconino County Health Department (Page office: 928-608-6108 x13) early if the project involves onsite wastewater.

Frequently asked questions

Page requires a residential building permit (new construction) for: Building permit required for new single-family and two-family dwelling construction within Page city limits; Plans must comply with the 2018 IRC as adopted by the City of Page and local design criteria (115 MPH wind, Exposure C; Seismic Zone 2, Site Class D or per geotechnical report; 18-inch frost depth; 20 PSF snow load, no reduction); Site/plot plan required showing property dimensions, distances between existing/proposed structures, distance from building to property lines, utility hook-up locations, street identification, and north arrow; House plans required: foundation plan with details, electrical plans with service panel location/size, fully dimensioned floor plan, equipment locations, floor framing (all levels), roof framing, elevation drawings, cross-sections, deck framing details, and livable square footage; Two sets of truss calculations from the manufacturer required; Two stamped sets of engineering specifications by an Arizona-registered engineer required where applicable; A building permit may not be issued prior to receiving verbal approval from Coconino County Health Department; Owner/Builder permits are allowed for residential projects only; any hired contractor must be licensed per A.R.S. § 32-1169; Wood sill-plates on concrete must be pressure-treated or foundation-grade redwood; footing reinforcing steel cannot be tied to metal grade stakes due to corrosive soil. If your project isn't listed, confirm with City of Page Building Safety Department at 928-645-4266 before starting work.

In Page, the published Building Permit Fee — Table 1-A (Total Valuation) is: $23.50 (valuation $1-$500); $23.50 + $3.05 per additional $100 (or fraction) to $2,000; $69.25 + $14.00 per additional $1,000 (or fraction) to $25,000; $391.25 + $10.10 per additional $1,000 to $50,000; $643.75 + $7.00 per additional $1,000 to $100,000; $993.75 + $5.60 per additional $1,000 to $500,000; $3,233.75 + $4.75 per additional $1,000 to $1,000,000; $5,608.75 + $3.65 per additional $1,000 above $1,000,000. Additional published fees: Plan Review Fee — 65% of the calculated Building Permit Fee; Additional Plan Review (changes/additions/revisions to plans) — $47.00 per hour; Re-inspection Fee — $47.00 per hour (minimum charge one-half hour for inspections with no specifically indicated fee; $54.00 per hour cited for other inspections/fees under item 6); Inspection Outside Normal Business Hours — $47.00 per hour, 2-hour minimum charge. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

As of July 2026, the City of Page does not publish a specific plan review turnaround time for residential building permits. The City's Zoning Code (§ 152.095) sets a 14-day SPRC scheduling requirement, but that applies only to commercial developments — single-family dwellings are exempt from SPRC review and are reviewed directly by the Chief Building Official. For a current estimate, call the Building Safety Department at 928-645-4266.

You'll need: City of Page Building Permit Application; Site/Plot Plan; House Plans (Foundation, Electrical, Floor, Framing, Elevations); Truss Calculations (2 sets). Depending on your project, Page may also ask for: Engineering Specifications (2 stamped sets). See the required-documents checklist on this page for details on each.

Page requires 3 inspection(s) for a residential building permit (new construction), in order: Foundation/Footing, Framing, Final. Schedule each through City of Page Building Safety Department (928-645-4266).

Apply through City of Page Building Safety Department at Page City Hall, 697 Vista Avenue / P.O. Box 1180, Page, AZ 86040. Phone: 928-645-4266, email: bslavens@pageaz.gov. Office hours: Building Official: Brett Slavens (bslavens@pageaz.gov, 928-645-4266, fax 928-645-4265). Main City line: 928-645-8861. Applications are submitted via the City of Page Building Permit Application (paper form, PO Box 1180 / 697 Vista Avenue) or through the online iWorQ Building Permit Application Portal (pageaz_permit.portal.iworq.net/portalhome/pageaz_permit). Final inspections must be scheduled at least 24 hours in advance, and final inspection/approval is required before occupying any room.. Official information: https://cityofpage.org/departments/building-and-safety/.

Page, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Page runs its own Building Safety Department and independently adopts and administers its own construction codes; it does not defer permitting to Coconino County. Source: City of Page Building and Safety Department page (cityofpage.org/departments/building-and-safety/).; 2018 International Building Code (IBC), Chapters 1-35, with amendments to Chapter 9 and Appendix Chapters B, H, and I, adopted by the City of Page as its uniform building code. Source: City of Page Building and Safety Department page.; 2018 International Residential Code (IRC), Chapters 1-44, with Appendix Chapters A, B, C, D, H, and P adopted, governing one- and two-family dwelling construction. Source: City of Page Building and Safety Department page.; 2018 International Plumbing Code (IPC), Chapters 1-15, with Appendix E adopted. Source: City of Page Building and Safety Department page.; 2018 International Fuel Gas Code, Chapters 1-8, with Appendix Chapters A, B, and C adopted. Source: City of Page Building and Safety Department page.; 2018 International Mechanical Code (IMC), Chapters 1-15, with Appendix Chapters A and B adopted. Source: City of Page Building and Safety Department page.; 2018 International Existing Building Code, Chapters 1-16, with Appendix C adopted. Source: City of Page Building and Safety Department page.; 2018 International Pool and Spa Code, Chapters 1-11, with Appendix Chapters A, B, C, and D adopted. Source: City of Page Building and Safety Department page.; 2017 National Electrical Code (NEC), Chapters 1-9, with Annexes A-E adopted (note: the electrical code cycle is one edition behind the 2018 ICC set). Source: City of Page Building and Safety Department page.; 2012 International Energy Conservation Code (IECC), Chapters 1-6, adopted; governs energy-efficiency requirements for the City of Page. Source: City of Page Building and Safety Department page.; 2018 International Fire Code (IFC) Chapter 61 adopted specifically for LP Gas regulation, in addition to ANSI Standards 2009 combined with the 2018 IBC. Source: City of Page Building and Safety Department page.; ICC A117.1 / ANSI Standards 2009 accessibility provisions apply in conjunction with the 2018 IBC, alongside the federal Americans with Disabilities Act (ADA) standards. Source: City of Page Building and Safety Department page.; Local ordinance amendments layered onto the adopted ICC codes: Ordinance 666-19 amending Chapter 92 for automatic fire sprinkler systems; City Code Article 9-5, Sections 9-5-1 through 9-5-17, regulating wood-burning stoves; City Code Article 11-4-1(B) requiring sewer backwater valves; City Code Article 11-5-2 requiring grease interceptors. Source: City of Page Building and Safety Department page.; Manufactured homes and factory-built buildings (FBBs) are licensed and permitted through a joint state/City structure: the Arizona Department of Fire, Building and Life Safety (Office of Manufactured Housing) sets manufacturer/installer/retailer licensing and issues State/IGA installation permits (state fee schedule effective July 1, 2022 - June 30, 2023, per City of Page Consolidated Fee Schedule, Building Department - Manufactured Home Fees, pp. 6-7), while the City of Page Building Safety Department handles local site/foundation/utility compliance. Source: City of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023).; A building permit may not be issued prior to receiving verbal approval from Coconino County Health Department (Page office: 928-608-6108 x13; main office: 928-679-8760) — relevant for projects involving onsite wastewater/septic systems. Source: City of Page Building and Safety Department page.. Local amendments apply — see the Page overview page for the full list.

The 2018 IRC (Chapters 1-44, plus Appendix Chapters A, B, C, D, H, and P) as adopted by the City of Page, along with the City's local design criteria: 115 MPH wind (Exposure C), Seismic Zone 2 (Site Class D or per geotechnical report), 18-inch frost depth, and 20 PSF snow load with no reduction.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Page building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.