EV Charger / EVSE Permit — Page, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://cityofpage.org/departments/building-and-safety/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Page, Arizona
The City of Page does not publish a dedicated EV charger/EVSE permit. Installation of a Level 2 EV charging circuit is permitted as electrical work under the City's standard Electrical Permit, governed by the 2017 National Electrical Code as adopted by the City. The City's Consolidated Fee Schedule (Resolution 1296-23) uses a dedicated valuation-based formula for all electrical permits — there is no separate EV-specific line item.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for the EV charging circuit installation, alteration, or repair work
- Governed by the 2017 NEC (Chapters 1-9, Annexes A-E) as adopted by the City of Page
- Electrical contractor information (name, address, contact, phone, license #) required on the Building Permit Application
- Apply via paper Building Permit Application or the online iWorQ Building Permit Application Portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Circuit wiring, box placement, and panel connections before walls are closed
- 2
Final
EVSE installed, protections verified per 2017 NEC
See the full Page inspection guide — scheduling & re-inspection fees →
Tips
- Page has no dedicated EV charger permit — apply for the standard Electrical Permit and the valuation-based fee formula will apply.
- The electrical permit fee formula ($27.00 for the first $500 + $3.75 per additional $1,000 of construction valuation) is a separate line item from the general Table 1-A Building Permit Fee schedule used for other permit types.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Page building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Page
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Page project checklist
Describe your project once and get every permit, document, and fee it triggers in Page — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →