Residential Solar Photovoltaic (PV) Permit in Page, Arizona

Required for installation of rooftop residential solar photovoltaic systems in Page. No dedicated streamlined PV procedure or PV-specific fee schedule was found published by the City; systems are subject to the state-law baseline (A.R.S. § 9-468) and the City's standard Building/Electrical Permit process under the 2018 IBC/IRC and 2017 NEC.

Verified 2026-07-06 · Source

When you need this permit

  • Residential PV systems must meet the minimum standards set by Arizona Revised Statutes § 9-468 (Solar construction permits; standards; definition), which all Arizona municipalities must follow at minimum for residential solar permit review
  • Construction plans showing PV system location, roof plan and elevation views, panel mounting/racking details, and a one-line or three-line electrical diagram are required per the state-law baseline
  • Electrical work must comply with the 2017 NEC as adopted by the City of Page
  • No City of Page-specific streamlined review procedure, dedicated PV checklist, or PV-specific fee schedule (comparable to some other Arizona cities' dedicated residential PV procedures) was found published on the City's Building and Safety Department page or in the Consolidated Fee Schedule as of July 2026

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Table 1-A (Total Valuation) and/or Electrical Permit Fee (valuation-based)City of Page Consolidated Fee Schedule (Resolution 1296-23), Building Department — Table 1-A, p.4. No dedicated 'Photovoltaic System' fee line was found in the published fee schedule; a residential PV system is billed under the general Building Permit Fee and/or the Electrical Permit Fee formula depending on how the City classifies the work at intake.
Building Permit Fee per Table 1-A ($23.50 for valuation $1-$500 up through $5,608.75 + $3.65 per additional $1,000 above $1,000,000) and/or Electrical Permit Fee ($27.00 for the first $500 + $3.75 per additional $1,000 of valuation)
Plan Review Fee (where plan review is required)City of Page Consolidated Fee Schedule, p.5
65% of the calculated permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Residential Solar Photovoltaic (PV) Permit permit actually take in Page?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified per 2017 NEC

See the full Page inspection guide — scheduling & re-inspection fees →

Tips

  • As of July 2026, the City of Page does not appear to publish permit-specific plan review turnaround times for residential solar PV permits on its public website. The City publishes general permit requirements and its fee schedule, but not a dedicated PV procedure or PV-specific review timeline (unlike some other Arizona cities that publish a streamlined multi-day PV track). There is no verifiable online source for this — call the City of Page Building Safety Department directly at 928-645-4266.
  • Because no City-specific PV fee line or checklist was found published, confirm directly with the Building Safety Department whether a given residential PV installation will be processed and fee-classified as an Electrical Permit, a Building Permit, or both.
  • At minimum, Arizona municipalities including Page must comply with A.R.S. § 9-468's baseline requirements for residential solar construction permits (plan content and review standards).

Frequently asked questions

Page requires a residential solar photovoltaic (pv) permit for: Residential PV systems must meet the minimum standards set by Arizona Revised Statutes § 9-468 (Solar construction permits; standards; definition), which all Arizona municipalities must follow at minimum for residential solar permit review; Construction plans showing PV system location, roof plan and elevation views, panel mounting/racking details, and a one-line or three-line electrical diagram are required per the state-law baseline; Electrical work must comply with the 2017 NEC as adopted by the City of Page; No City of Page-specific streamlined review procedure, dedicated PV checklist, or PV-specific fee schedule (comparable to some other Arizona cities' dedicated residential PV procedures) was found published on the City's Building and Safety Department page or in the Consolidated Fee Schedule as of July 2026. If your project isn't listed, confirm with City of Page Building Safety Department at 928-645-4266 before starting work.

In Page, the published Building Permit Fee — Table 1-A (Total Valuation) and/or Electrical Permit Fee (valuation-based) is: Building Permit Fee per Table 1-A ($23.50 for valuation $1-$500 up through $5,608.75 + $3.65 per additional $1,000 above $1,000,000) and/or Electrical Permit Fee ($27.00 for the first $500 + $3.75 per additional $1,000 of valuation). Additional published fees: Plan Review Fee (where plan review is required) — 65% of the calculated permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Page does not publish a plan-review timeline for this permit. Contact City of Page Building Safety Department at 928-645-4266 for current turnaround.

You'll need: City of Page Building Permit Application; PV Construction Plans (roof plan, elevation, racking/mounting details, electrical diagram). See the required-documents checklist on this page for details on each.

Page requires 2 inspection(s) for a residential solar photovoltaic (pv) permit, in order: Rough Electrical, Final. Schedule each through City of Page Building Safety Department (928-645-4266).

Apply through City of Page Building Safety Department at Page City Hall, 697 Vista Avenue / P.O. Box 1180, Page, AZ 86040. Phone: 928-645-4266, email: bslavens@pageaz.gov. Office hours: Building Official: Brett Slavens (bslavens@pageaz.gov, 928-645-4266, fax 928-645-4265). Main City line: 928-645-8861. Applications are submitted via the City of Page Building Permit Application (paper form, PO Box 1180 / 697 Vista Avenue) or through the online iWorQ Building Permit Application Portal (pageaz_permit.portal.iworq.net/portalhome/pageaz_permit). Final inspections must be scheduled at least 24 hours in advance, and final inspection/approval is required before occupying any room.. Official information: https://cityofpage.org/departments/building-and-safety/.

Page, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Page runs its own Building Safety Department and independently adopts and administers its own construction codes; it does not defer permitting to Coconino County. Source: City of Page Building and Safety Department page (cityofpage.org/departments/building-and-safety/).; 2018 International Building Code (IBC), Chapters 1-35, with amendments to Chapter 9 and Appendix Chapters B, H, and I, adopted by the City of Page as its uniform building code. Source: City of Page Building and Safety Department page.; 2018 International Residential Code (IRC), Chapters 1-44, with Appendix Chapters A, B, C, D, H, and P adopted, governing one- and two-family dwelling construction. Source: City of Page Building and Safety Department page.; 2018 International Plumbing Code (IPC), Chapters 1-15, with Appendix E adopted. Source: City of Page Building and Safety Department page.; 2018 International Fuel Gas Code, Chapters 1-8, with Appendix Chapters A, B, and C adopted. Source: City of Page Building and Safety Department page.; 2018 International Mechanical Code (IMC), Chapters 1-15, with Appendix Chapters A and B adopted. Source: City of Page Building and Safety Department page.; 2018 International Existing Building Code, Chapters 1-16, with Appendix C adopted. Source: City of Page Building and Safety Department page.; 2018 International Pool and Spa Code, Chapters 1-11, with Appendix Chapters A, B, C, and D adopted. Source: City of Page Building and Safety Department page.; 2017 National Electrical Code (NEC), Chapters 1-9, with Annexes A-E adopted (note: the electrical code cycle is one edition behind the 2018 ICC set). Source: City of Page Building and Safety Department page.; 2012 International Energy Conservation Code (IECC), Chapters 1-6, adopted; governs energy-efficiency requirements for the City of Page. Source: City of Page Building and Safety Department page.; 2018 International Fire Code (IFC) Chapter 61 adopted specifically for LP Gas regulation, in addition to ANSI Standards 2009 combined with the 2018 IBC. Source: City of Page Building and Safety Department page.; ICC A117.1 / ANSI Standards 2009 accessibility provisions apply in conjunction with the 2018 IBC, alongside the federal Americans with Disabilities Act (ADA) standards. Source: City of Page Building and Safety Department page.; Local ordinance amendments layered onto the adopted ICC codes: Ordinance 666-19 amending Chapter 92 for automatic fire sprinkler systems; City Code Article 9-5, Sections 9-5-1 through 9-5-17, regulating wood-burning stoves; City Code Article 11-4-1(B) requiring sewer backwater valves; City Code Article 11-5-2 requiring grease interceptors. Source: City of Page Building and Safety Department page.; Manufactured homes and factory-built buildings (FBBs) are licensed and permitted through a joint state/City structure: the Arizona Department of Fire, Building and Life Safety (Office of Manufactured Housing) sets manufacturer/installer/retailer licensing and issues State/IGA installation permits (state fee schedule effective July 1, 2022 - June 30, 2023, per City of Page Consolidated Fee Schedule, Building Department - Manufactured Home Fees, pp. 6-7), while the City of Page Building Safety Department handles local site/foundation/utility compliance. Source: City of Page Consolidated Fee Schedule (Resolution 1296-23, adopted 1-25-2023).; A building permit may not be issued prior to receiving verbal approval from Coconino County Health Department (Page office: 928-608-6108 x13; main office: 928-679-8760) — relevant for projects involving onsite wastewater/septic systems. Source: City of Page Building and Safety Department page.. Local amendments apply — see the Page overview page for the full list.

No dedicated streamlined residential PV review procedure, checklist, or PV-specific fee schedule was found published by the City of Page as of July 2026. Solar PV installations are processed under the City's standard Building/Electrical Permit process (2018 IBC/IRC and 2017 NEC), subject at minimum to the statewide baseline in A.R.S. § 9-468. Confirm current process details with the Building Safety Department at 928-645-4266.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Page building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.