Change of Use / Certificate of Occupancy Permit — Williams, Arizona · Requirements sheet
Reviewed 2026-07-07 · Source: https://www.williamsaz.gov/departments_and_services/building_department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Certificate of Occupancy Permit in Williams, Arizona
A change of use in Williams runs on two tracks that must both close. On the building-code side, Code of Ordinances § 150.20 adopts the International Building Code, 2024 Edition (including Appendices C, F, I, J and K) as the Building Code for the City, amending only Section 111.3 of the certificate-of-occupancy article (by adding Section 111.3.1 on temporary occupancy) — so IBC Section 111's requirement that a building not be used or occupied and that its occupancy classification not be changed until the building official issues a certificate of occupancy applies as adopted. Section 150.27 separately adopts the International Existing Building Code, 2024 Edition 'as the code for regulating and governing the repair, alteration, change of occupancy, addition and relocation of existing buildings, including historic buildings.' On the zoning side, § 158.126 requires a building permit and an approved plot plan, applied for under Chapter 154, and the City's own Procedure to Obtain Building Permit states that all building permits are subject to Planning & Zoning review for compliance with the Zoning and Development Procedure Ordinance, with Planning & Zoning determining whether a public hearing (variance, zoning change, conditional use permit) is needed. The City publishes no dedicated change-of-use application form.
Reviewed 2026-07-07 · Source
When you need this permit
- § 150.20(A) adopts the International Building Code, 2024 Edition, including Appendices C, F, I, J and K, as the Building Code for the City of Williams, 'providing for the issuance of permits and collection of fees therefore' (Ord. 1007, passed 9-12-2024). Within the certificate-of-occupancy article the City amends only Section 111.3, adding Section 111.3.1: if required work is not completed on or before the expiration date of the Temporary Certificate of Occupancy, the Building Official may request the utility companies to de-energize the building and the building may not be occupied, with neither the City nor the utility companies liable for damages or delays
- § 150.27(A) adopts the International Existing Building Code, 2024 Edition, including Appendix B, as the code regulating and governing the repair, alteration, change of occupancy, addition and relocation of existing buildings, including historic buildings; § 150.27(B)(2) makes the Chief Building Inspector or their designee the 'code official' under that code, and § 150.27(B)(3) routes IEBC fees to IBC Section 109.2 as amended
- § 158.126(A): prior to the construction, remodeling or placement of any building or accessory building, a building permit and an approved plot plan are required; § 158.126(B) directs that the application be made in accordance with Chapter 154 of the code of ordinances
- All building permits are subject to review by the Planning & Zoning Department for compliance with the Zoning and Development Procedure Ordinance; Planning & Zoning also determines the need for a public hearing, and public hearing issues include variance, zoning changes and conditional use permits (City of Williams Procedure to Obtain Building Permit, section 2)
- All work within the Historic District must have approval from the Historic Commission prior to permitting; work within the Main Street District is forwarded to the Main Street Design Committee under § 154.018
- Where the new use is a motel or restaurant, a copy of Coconino County Health Department approval to construct must be received before the City will issue a permit (928-679-7120)
- Where the change of use involves commercial construction or alteration of 3,000 square feet or more, major electrical, mechanical or plumbing improvements or replacements, housing of more than 4 units, or public improvements, plans must bear the seal of an Arizona-licensed architect and/or engineer (A.R.S. § 32-144)
- Cover sheet requirements for the plan set include the occupancy and occupancy load along with type of construction, design codes, design criteria, floor area, site address, legal description (APN), flood zone, deferred submittals, design professionals, number of employees and special inspections
- Filed on the City's standard paper Building Permit Application — the form's 'TYPE OF IMPROVEMENT' checkboxes (Alteration, Remodel, Repair, Addition) and its 'PROPOSED USE' block (Single Family, Multi-Family with unit count, Garage attached/detached, Commercial, Restaurant, Motel with unit count, Other/Non-Residential specify) are where the use change is declared; there is no separate change-of-use form
- Permit term (§ 150.20 amendments): all construction permits for new, remodels, additions and alterations are valid for a maximum period of 365 days, with one written-request extension of up to an additional 365 days; after that extension a further 180-day extension requires payment of one-half the permit fee, and permits not passing final inspection after 1,000 days expire and require a new permit and all associated fees
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Alteration Inspections (if construction is performed)
Rough-in and progress inspections on building, plumbing, mechanical and electrical work performed to serve the new occupancy; the number of inspections varies with the complexity of the job (Building Department FAQ)
- 2
Final / Certificate of Occupancy
Completed work verified against the approved plans, closing with the building official's certificate of occupancy; a Temporary Certificate of Occupancy carries an expiration date after which, under § 150.20's added Section 111.3.1, the Building Official may request that utilities de-energize the building and the building may not be occupied
See the full Williams inspection guide — scheduling & re-inspection fees →
Tips
- There is no change-of-use form in Williams. The use change is declared on the standard Building Permit Application via the Type of Improvement checkboxes and the PROPOSED USE block (which distinguishes Single Family, Multi-Family, Commercial, Restaurant, Motel and Other/Non-Residential), and the plan set's cover sheet must state the occupancy and occupancy load.
- The City adopts the 2024 International Existing Building Code specifically to govern change of occupancy in existing buildings — expect the work to be evaluated under IEBC compliance methods rather than as new construction.
- Do not skip the plot plan. § 158.126(A) requires an approved plot plan alongside the building permit, and § 154.018 routes it through every reviewing city department, plus the Main Street Design Committee for Main Street and Historic Preservation District work.
- Restaurant and motel conversions have an external gate: the City will not issue the permit until it receives Coconino County Health Department approval to construct (928-679-7120). Build that lead time into the schedule.
- A Temporary Certificate of Occupancy in Williams has teeth — under the City's added Section 111.3.1, missing the TCO expiration date can result in the Building Official asking utilities to de-energize the building.
- If the new use is not permitted outright in the district, Planning & Zoning will determine that a public hearing is required (variance, zoning change or conditional use permit) and route the file to the Planning & Zoning Commission — a separate, longer track than the building permit itself.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Williams building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Williams
Change of Use / Certificate of Occupancy Permit in other cities
Compare change of use / certificate of occupancy permit fees across Arizona →
Look up this fee in a different city →