Commercial Building Permit (New Construction & Tenant Improvement) in Williams, Arizona

Required for new commercial construction AND commercial alterations/tenant improvements in the City of Williams — the City's published 'Procedure to Obtain Building Permit' contains a dedicated 'Commercial Plans' and 'Commercial Submittals' track covering both 'new construction and alterations' under a single process with a single $500 Commercial application deposit. There is no separate tenant-improvement permit category. Given Williams' tourism-heavy economy (Route 66 historic downtown, Grand Canyon Railway), two commercial-specific gates matter frequently here: Historic Commission approval before permitting for any work in the Historic District, and Coconino County Health Department approval-to-construct before permit issuance for all motels and restaurants.

Verified 2026-08-01 · Source

When you need this permit

  • Building permit and approved plot plan required prior to construction, remodeling, or alteration of any building within Williams city limits (Code of Ordinances § 158.126); plot plan/building permit procedure follows Code of Ordinances § 154.018 (plot plan and fees to the City Planner, staff review within six working days, then Building Permit Application and plans to the Chief Building Official — commercial plans may be reviewed by city staff or a referred architecture/engineering consultant)
  • Commercial Plans design-professional threshold: new construction and alterations for buildings of 3,000 sq ft or more, major electrical/mechanical/plumbing improvements or replacements, housing of more than 4 units, or public improvements must have plans sealed by a qualified registrant (architect and/or engineer) holding an Arizona State License per A.R.S. § 32-144 ('Procedure to Obtain Building Permit', Commercial Plans section)
  • Motels and restaurants: the City must receive a copy of approval-to-construct from the Coconino County Health Department (928-679-7120) prior to issuing a permit — a hard pre-issuance gate for Williams' dominant hospitality/food-service project types
  • Commercial Submittals per the City's published checklist: (A) complete Permit Application with required deposit — an incomplete application will not be accepted; (B) five (5) sets of Civil Plans; (C) three (3) sets of Construction Plans with civil drawing attached; (D) Soils Report; (E) Structural Calculations; (F) Life Safety Plan; (G) SWPPP — submit Notice of Intent (NOI) if required; (H) Floodplain determination and documentation, sealed by a registered design professional, if required; (I) Deferred Submittals listed on the construction-plan cover sheet, reviewed by the architect/engineer for design conformance and approved by the Building Official prior to construction or installation
  • Plan cover sheet must list: design codes, design criteria, legal description (APN), site address, floodplain, floor area, design professionals, deferred submittals, type of construction, occupancy, occupancy load, number of employees, and special inspections
  • All work within the Historic District must have approval from the Historic Commission prior to permitting ('Procedure to Obtain Building Permit', Planning & Zoning section) — directly relevant to Williams' Route 66 historic downtown commercial corridor; work in the Main Street District is forwarded to the Main Street Design Committee under Code of Ordinances § 154.018
  • Commercial soil pressure design is per engineered design (not the 1,500 psi residential default); building shall not be built on fill material unless the fill is engineered and tested by an approved agency ('Building and Design Criteria Requirements')
  • Commercial fire-protection amendments (Ordinance No. 956, IFC §§ 903.2/903.2.3/905.3): automatic sprinklers required for new buildings unable to meet fire-flow requirements as determined by the Fire Chief, for Group E occupancies more than one story, and for any commercial building greater than two stories; standpipe systems required in any commercial building greater than two stories — relevant to multi-story hotel/lodging projects
  • $500.00 non-refundable Commercial application submittal deposit due at submittal, credited toward total permit cost; applicant has 90 days after acceptance notification to resolve all application/plan issues and pay for/pick up the permit or the deposit is forfeited
  • New-construction permits are valid one (1) year with an inspection no less than every 180 days; revisions to approved plans must be submitted by drawings or addendum letters BEFORE the revised work is commenced

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 6 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Application Submittal Deposit (Commercial)City of Williams 'Procedure to Obtain Building Permit', Application Submittal Deposit schedule — the single 'Commercial' deposit line covers both new commercial construction and commercial remodel/alteration (tenant improvement) applications; there is no reduced commercial-remodel deposit tier equivalent to the $100 residential-remodel tier
$500.00 (non-refundable, credited toward total permit cost)
Building Permit Fee / Plan Review Fee / trade feesCity of Williams Ordinance No. 956, IBC § 109.2 as amended: 'Fee schedule as established by the City of Williams and passed by resolution of the City Council.' No itemized commercial valuation-based fee table or plan-review-fee percentage was found published online as of 2026-08-01 — confirmed gap (re-verified this session against the Building Department page, the 'Procedure to Obtain Building Permit' PDF, and web search); the Building Department page itself states 'Because fees are subject to change, actual amounts are not listed.' Contact the Building Department (928-635-4451 ext. 205) for a project-specific quote.
Fee schedule as established by City of Williams resolution of the City Council (exact dollar amounts not published)

Review timeline

Plan reviewWilliams’s published plan-review target
15–15 business days

How long did your Commercial Building Permit (New Construction & Tenant Improvement) permit actually take in Williams?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    Before concrete pour; commercial soil pressure design per engineered design, no building on untested fill; verify footing depth/width and reinforcement per City of Williams amendments

  2. 2

    Framing / Rough Trades

    Structural framing and rough electrical/plumbing/mechanical before cover; new-construction permits require an inspection no less than every 180 days to remain valid

  3. 3

    Special Inspections

    As listed on the approved plan cover sheet (a required cover-sheet line item for commercial submittals), performed per the approved plans

  4. 4

    Final / Certificate of Occupancy

    All work complete per approved plans before occupancy; work not completed under a Temporary Certificate of Occupancy by its expiration may result in the Building Official requesting utility de-energization (Ordinance No. 956)

See the full Williams inspection guide — scheduling & re-inspection fees →

Tips

  • There is NO separate tenant-improvement permit in Williams: the City's 'Procedure to Obtain Building Permit' explicitly folds 'new construction and alterations' into one Commercial Plans/Commercial Submittals track, and the deposit schedule has a single $500 'Commercial' line (unlike the residential side, which splits $500 new / $100 remodel). A commercial TI is applied for on the same Building Permit Application, with the same $500 deposit and the same commercial submittal checklist — scale of required items (soils report, civil plan sets) is a Building Official judgment call to confirm at intake for interior-only scopes.
  • For Williams' dominant hospitality project types, sequence the Coconino County Health Department approval-to-construct (928-679-7120) EARLY: for all motels and restaurants the City will not issue the building permit until it receives a copy of that approval — it is a pre-issuance gate, not a parallel process.
  • Route 66 corridor work: all work within the Historic District requires Historic Commission approval PRIOR to permitting, and Main Street District work is routed through the Main Street Design Committee under § 154.018 — Williams' downtown commercial building stock (the Williams Historic Business District) sits squarely in this overlay, so budget an extra review body into any storefront TI or facade change there.
  • The Arizona design-professional seal threshold (A.R.S. § 32-144) is triggered at 3,000 sq ft or more, major electrical/mechanical/plumbing improvements OR REPLACEMENTS, more than 4 housing units, or public improvements — note that a major MEP replacement alone can trigger the seal requirement on an otherwise-modest tenant improvement.
  • Multi-story lodging economics: Ordinance No. 956's IFC amendments require automatic sprinklers in any commercial building greater than two stories (and standpipes in the same), plus sprinklers where fire-flow requirements cannot be met as determined by the Fire Chief — a meaningful cost factor for hotel projects in a small city with limited fire-flow infrastructure.
  • No dollar-figure commercial permit/plan-review fee schedule is published anywhere the City posts documents — Ordinance No. 956 deletes the adopted codes' fee sections in favor of an unpublished Council-resolution fee schedule, and the Building Department page says outright that actual amounts are not listed because fees are subject to change. Only the $500 commercial deposit is a published dollar figure; call 928-635-4451 ext. 205 for a quote.
  • No A.R.S. § 9-835 'Building Permit Processing Time Frames' compliance document was found published by the City of Williams (targeted search, 2026-08-01) — the only published turnaround figure is the Building Department's own '15 working days on average' statement.
  • An incomplete commercial application will not be accepted at intake (stated verbatim in the Commercial Submittals checklist) — with five civil sets, three construction sets, soils report, structural calcs, and a life safety plan required, assemble the full package before the counter visit; there is no online portal.

Frequently asked questions

Williams requires a commercial building permit (new construction & tenant improvement) for: Building permit and approved plot plan required prior to construction, remodeling, or alteration of any building within Williams city limits (Code of Ordinances § 158.126); plot plan/building permit procedure follows Code of Ordinances § 154.018 (plot plan and fees to the City Planner, staff review within six working days, then Building Permit Application and plans to the Chief Building Official — commercial plans may be reviewed by city staff or a referred architecture/engineering consultant); Commercial Plans design-professional threshold: new construction and alterations for buildings of 3,000 sq ft or more, major electrical/mechanical/plumbing improvements or replacements, housing of more than 4 units, or public improvements must have plans sealed by a qualified registrant (architect and/or engineer) holding an Arizona State License per A.R.S. § 32-144 ('Procedure to Obtain Building Permit', Commercial Plans section); Motels and restaurants: the City must receive a copy of approval-to-construct from the Coconino County Health Department (928-679-7120) prior to issuing a permit — a hard pre-issuance gate for Williams' dominant hospitality/food-service project types; Commercial Submittals per the City's published checklist: (A) complete Permit Application with required deposit — an incomplete application will not be accepted; (B) five (5) sets of Civil Plans; (C) three (3) sets of Construction Plans with civil drawing attached; (D) Soils Report; (E) Structural Calculations; (F) Life Safety Plan; (G) SWPPP — submit Notice of Intent (NOI) if required; (H) Floodplain determination and documentation, sealed by a registered design professional, if required; (I) Deferred Submittals listed on the construction-plan cover sheet, reviewed by the architect/engineer for design conformance and approved by the Building Official prior to construction or installation; Plan cover sheet must list: design codes, design criteria, legal description (APN), site address, floodplain, floor area, design professionals, deferred submittals, type of construction, occupancy, occupancy load, number of employees, and special inspections; All work within the Historic District must have approval from the Historic Commission prior to permitting ('Procedure to Obtain Building Permit', Planning & Zoning section) — directly relevant to Williams' Route 66 historic downtown commercial corridor; work in the Main Street District is forwarded to the Main Street Design Committee under Code of Ordinances § 154.018; Commercial soil pressure design is per engineered design (not the 1,500 psi residential default); building shall not be built on fill material unless the fill is engineered and tested by an approved agency ('Building and Design Criteria Requirements'); Commercial fire-protection amendments (Ordinance No. 956, IFC §§ 903.2/903.2.3/905.3): automatic sprinklers required for new buildings unable to meet fire-flow requirements as determined by the Fire Chief, for Group E occupancies more than one story, and for any commercial building greater than two stories; standpipe systems required in any commercial building greater than two stories — relevant to multi-story hotel/lodging projects; $500.00 non-refundable Commercial application submittal deposit due at submittal, credited toward total permit cost; applicant has 90 days after acceptance notification to resolve all application/plan issues and pay for/pick up the permit or the deposit is forfeited; New-construction permits are valid one (1) year with an inspection no less than every 180 days; revisions to approved plans must be submitted by drawings or addendum letters BEFORE the revised work is commenced. If your project isn't listed, confirm with City of Williams Building Department at 928-635-4451 ext. 205 before starting work.

In Williams, the published Application Submittal Deposit (Commercial) is: $500.00 (non-refundable, credited toward total permit cost). Additional published fees: Building Permit Fee / Plan Review Fee / trade fees — Fee schedule as established by City of Williams resolution of the City Council (exact dollar amounts not published). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The City publishes a general average of 15 working days for plan review and permit issuance (workload-dependent), with a six-working-day plot-plan review step preceding it under Code of Ordinances § 154.018. There is no published commercial-specific timeline and no A.R.S. § 9-835 time-frames document was found; external steps (Coconino County Health Department approval for motels/restaurants, Historic Commission review downtown) add lead time outside that figure.

You'll need: City of Williams Building Permit Application; Civil Plans (5 sets); Construction Plans (3 sets, with civil drawing attached); Soils Report; Structural Calculations; Life Safety Plan. Depending on your project, Williams may also ask for: SWPPP / Notice of Intent (NOI); Floodplain Determination and Documentation; Coconino County Health Department Approval-to-Construct. See the required-documents checklist on this page for details on each.

Williams requires 4 inspection(s) for a commercial building permit (new construction & tenant improvement), in order: Footing/Foundation, Framing / Rough Trades, Special Inspections, Final / Certificate of Occupancy. Schedule each through City of Williams Building Department (928-635-4451 ext. 205).

Apply through City of Williams Building Department at 113 South 1st Street, Williams, AZ 86046-2549. Phone: 928-635-4451 ext. 205, email: tmartinez@williamsaz.gov. Office hours: Phone 928-635-4451, fax 928-635-4495. Chief Building Inspector / Building Official: Tim Martinez (928-295-5478, tmartinez@williamsaz.gov) handles building permit review and issuance; Building Official Raul Hatch (928-635-4451 / 928-295-5478, rhatch@williamsaz.gov) is listed as the signing official on the Fence and Demolition permit application forms — the department appears to operate with more than one Building Official-titled staff member across different permit forms as of 2025. Applications are submitted in person or by mail using the City's paper Building Permit Application (no online portal was found); permits are picked up and fees paid at the City Hall front desk. Two sets of construction documents/plans required for submittal.. Official information: https://www.williamsaz.gov/departments_and_services/building_department.

No. Commercial alterations/tenant improvements are processed under the same Commercial Plans / Commercial Submittals track as new commercial construction, on the same Building Permit Application with the same $500 non-refundable application deposit. The City's 'Procedure to Obtain Building Permit' addresses 'new construction and alterations' together and publishes only one Commercial deposit tier.

Three common ones: (1) motels and restaurants must provide a copy of Coconino County Health Department approval-to-construct (928-679-7120) before the City will issue a permit; (2) any work within the Historic District needs Historic Commission approval prior to permitting (Main Street District work goes to the Main Street Design Committee); (3) projects at 3,000+ sq ft, with major MEP improvements/replacements, more than 4 housing units, or public improvements need plans sealed by an Arizona-licensed architect/engineer per A.R.S. § 32-144.

This one’s complicated · Get an expediter