Residential Building Permit (New Construction) — Williams, Arizona · Requirements sheet
Verified 2026-07-07 · Source: https://www.williamsaz.gov/departments_and_services/building_department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Williams, Arizona
Required for new single-family residential construction in the City of Williams. Reviewed against the current Building and Design Criteria (2024-cycle ICC codes per the City's published submittal-requirements sheet, layered with the still-codified administrative/fee/expiration amendments of Ordinance No. 956). Applications are submitted in person or by mail to the Building Department; there is no online permitting portal.
Verified 2026-07-07 · Source
When you need this permit
- Building permit and an approved plot plan are required prior to construction, remodeling, or placement of any building or accessory building within Williams city limits (Code of Ordinances § 158.126)
- Plot plan/building permit application procedure follows Code of Ordinances § 154.018: plot plan and fees submitted to the City Planner; staff review within six working days; applicant meets with the Chief Building Official; four copies of the approved plot plan submitted; building permit application and two sets of building plans then submitted to the Chief Building Official for review and issuance
- Plans must comply with the City's current Building and Design Criteria (60 PSF ground snow load; 40 PSF roof load design; 105 MPH wind speed, Exposure B or C; Seismic Design Category C; 30-inch frost line; 4°F winter design temperature; ice barrier required) and City of Williams Energy Efficiency Standards (R-38 ceiling, R-19 frame wall, R-19 floors, minimum 90 AFUE heating, minimum 14 SEER/8 HSPF cooling)
- Residential single-family detached structures are exempt from the Arizona Design Professional (architect/engineer stamp) requirement under A.R.S. § 32-121 et seq. unless circumstances dictate otherwise
- Two complete sets of plans required: Plot Plan (survey showing drainage, structure locations/setbacks, utility locations and sizes, easements) and House Plans (foundation, floor, roof framing, four elevations, cross-sections, details), on uniform-sized paper (minimum 8.5"x11", maximum 24"x36"), drawn to scale minimum 3/16"=1 ft per the Residential Required Submittal Documents List (or 1/4" per foot minimum per the older Procedure sheet)
- Manufactured Truss Calculations and wood floor calculations required if applicable; two sets of engineered truss calculations
- Waste water/septic system approval letter from Coconino County Environmental/Health Department required if applicable (not on City sewer)
- Defensible Space / Vegetation Management Plan required if the property is located within the Wildland Urban Interface Zone — relevant given Williams' surrounding Kaibab National Forest / ponderosa pine forest setting
- Flood Management Plan required if the property is determined to be in Flood Zone A (FIRM Community Panel #040027-0001B-4B, effective 12/15/1983, revised 09/03/2010)
- Signed and approved Building Moratorium Exception Form required as part of the standard residential submittal packet
- Builder/Contractor Information Form required
- $500.00 non-refundable Plan Review Deposit due at submittal (new construction), credited toward total permit cost; applicant has 90 days after acceptance notice to resolve issues and pick up the permit or the deposit is forfeited
- Work within the Main Street District (including the Historic Preservation District) requires additional review/approval by the Main Street Design Committee / Historic Commission before permitting
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation
Before concrete pour; verify footing depth (min. 18 in. below undisturbed grade, or 3,500 psi concrete pinned to rock if under 30 in.), width, and reinforcement per City of Williams amendments
- 2
Framing
Structural framing, connections, egress, garage-dwelling fire separation (5/8" Type X gypsum board) per City of Williams amendments
- 3
Energy Efficiency Inspection
Verifies compliance with City of Williams Energy Efficiency Standards (insulation R-values, HVAC AFUE/SEER/HSPF, window/skylight U-factors) per Ordinance No. 956 amendment to IBC § 110.3.7
- 4
Final / Certificate of Occupancy
All work complete per approved plans before occupancy; Temporary Certificate of Occupancy work not completed by its expiration may result in the Building Official requesting utility de-energization
See the full Williams inspection guide — scheduling & re-inspection fees →
Tips
- The City of Williams Building Department directly publishes: 'On an average the Plan Review and Permit will be done within 15 working days' — this is a real, town-specific published figure from the City's own 'Procedure to Obtain Building Permit' guidance and Building Department webpage summary, not an inferred or statutory-default figure.
- Separately, Code of Ordinances § 154.018 requires the PLOT PLAN stage (which precedes formal building-plan submittal) to be reviewed by all city departments within six working days — this is a distinct, faster front-end step before the 15-working-day building-plan review begins.
- A significant code-cycle discrepancy exists: the codified Ordinance No. 956 (adopted 2016, effective 2017) locks in the 2015 ICC family and 2014 NEC, but the City's own current 'Building and Design Criteria Submittal Requirements' sheet lists the 2024 ICC family and 2023 NEC as the design codes — no intervening ordinance number was found published bridging this gap. This record treats the 2024 Design Criteria sheet as controlling for current code-cycle and design-load figures, while Ordinance No. 956's administrative/fee/expiration provisions remain the codified law absent a located repeal.
- Commercial-threshold triggers matter even for residential-adjacent projects: any structure exceeding 3,000 sq ft, occupant load over 20, any structural member exceeding 20-24 feet, or electrical service 600 amps or greater requires an Arizona-licensed design professional's stamp, even if it would otherwise be treated as residential.
- Given Williams' forested Kaibab National Forest setting, confirm early whether the parcel falls within a mapped Wildland Urban Interface Zone — a Defensible Space/Vegetation Management Plan is a hard submittal requirement if so.
- The $500 plan review deposit is non-refundable per Ordinance No. 956's refund provisions once the application is submitted, though up to 80% of the underlying plan-review or permit fee itself may be refunded if no review/work has occurred, per a written request filed within 180 days.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Williams building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Williams
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Williams project checklist
Describe your project once and get every permit, document, and fee it triggers in Williams — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →