Residential Solar Photovoltaic (PV) Permit in Williams, Arizona

Required for installation of rooftop residential solar photovoltaic systems in Williams. The City publishes a dedicated Solar Policy: solar designs are reviewed by APS (the City's contracted electric-system operator) before the City's Building Department processes the permit and fees, and the City explicitly does not offer a net-metering/billing-credit program.

Verified 2026-07-07 · Source

When you need this permit

  • Complete Building Permit Application submitted with solar plans, per the City of Williams Solar Policy
  • Solar plans/design must be stamped by a certified electrical engineer or an approved solar design specialist
  • Plans are reviewed by APS (the City's contracted operator of its electric distribution system) for approval before the City's Building Department processes the permit and collects fees
  • The Solar Policy itself must be signed by the property owner (not just the installer), acknowledging that the City of Williams does NOT participate in any net metering/billing credit program — any electricity produced by the solar system in excess of the owner's use receives no billing credit, and any electricity metered off the City's system is billed accordingly
  • The Building Permit itself may be signed by the installer, but the Solar Policy acknowledgment must be signed by the owner
  • A schedule of required inspections is noted directly on the issued Building Permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar/Electrical Permit FeeCity of Williams Ordinance No. 956, IBC § 109.2 as amended; no dedicated PV-specific fee line was found published separately from the general electrical/building fee schedule — confirmed gap; contact the Building Department (928-635-4451 ext. 205).
Fee schedule as established by City of Williams resolution of the City Council (exact dollar amounts not published)

Review timeline

Plan review
Not published — contact the department

How long did your Residential Solar Photovoltaic (PV) Permit permit actually take in Williams?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified; specific inspection schedule noted on the issued permit

See the full Williams inspection guide — scheduling & re-inspection fees →

Tips

  • Williams' Solar Policy is unusual among Arizona jurisdictions in explicitly stating the City does NOT offer net metering/billing credits — any solar production exceeding the owner's own use receives no credit, which is a meaningfully different economic proposition than APS-served or net-metering jurisdictions elsewhere in the state.
  • The review process routes through APS as the City's contracted electric-system operator BEFORE the City's own Building Department processes the permit and fees — this external-utility review step is a dependency outside the Building Department's direct control and may add lead time beyond the general building-permit average.
  • The owner (not necessarily the installer) must personally sign the Solar Policy acknowledgment — confirm this administrative step is completed alongside the permit application itself, since the permit and the policy acknowledgment can be signed by different parties.

Frequently asked questions

Williams requires a residential solar photovoltaic (pv) permit for: Complete Building Permit Application submitted with solar plans, per the City of Williams Solar Policy; Solar plans/design must be stamped by a certified electrical engineer or an approved solar design specialist; Plans are reviewed by APS (the City's contracted operator of its electric distribution system) for approval before the City's Building Department processes the permit and collects fees; The Solar Policy itself must be signed by the property owner (not just the installer), acknowledging that the City of Williams does NOT participate in any net metering/billing credit program — any electricity produced by the solar system in excess of the owner's use receives no billing credit, and any electricity metered off the City's system is billed accordingly; The Building Permit itself may be signed by the installer, but the Solar Policy acknowledgment must be signed by the owner; A schedule of required inspections is noted directly on the issued Building Permit. If your project isn't listed, confirm with City of Williams Building Department at 928-635-4451 ext. 205 before starting work.

In Williams, the published Solar/Electrical Permit Fee is: Fee schedule as established by City of Williams resolution of the City Council (exact dollar amounts not published). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Williams does not publish a plan-review timeline for this permit. Contact City of Williams Building Department at 928-635-4451 ext. 205 for current turnaround.

You'll need: City of Williams Building Permit Application; City of Williams Solar Policy (signed); Stamped Solar Plans/Design. See the required-documents checklist on this page for details on each.

Williams requires 2 inspection(s) for a residential solar photovoltaic (pv) permit, in order: Rough Electrical, Final. Schedule each through City of Williams Building Department (928-635-4451 ext. 205).

Apply through City of Williams Building Department at 113 South 1st Street, Williams, AZ 86046-2549. Phone: 928-635-4451 ext. 205, email: tmartinez@williamsaz.gov. Office hours: Phone 928-635-4451, fax 928-635-4495. Chief Building Inspector / Building Official: Tim Martinez (928-295-5478, tmartinez@williamsaz.gov) handles building permit review and issuance; Building Official Raul Hatch (928-635-4451 / 928-295-5478, rhatch@williamsaz.gov) is listed as the signing official on the Fence and Demolition permit application forms — the department appears to operate with more than one Building Official-titled staff member across different permit forms as of 2025. Applications are submitted in person or by mail using the City's paper Building Permit Application (no online portal was found); permits are picked up and fees paid at the City Hall front desk. Two sets of construction documents/plans required for submittal.. Official information: https://www.williamsaz.gov/departments_and_services/building_department.

No. The City of Williams Solar Policy explicitly states the City does not participate in any net metering/billing credit program — electricity produced in excess of the owner's use receives no billing credit, and any electricity drawn from the City's system is billed normally.

Solar plans/design (stamped by a certified electrical engineer or approved solar design specialist) are first reviewed by APS, the City's contracted operator of its electric distribution system; once APS approves, the City's Building Department processes the permit and collects fees.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Williams building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.