City of Globe building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in City of Globe, Arizona.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Globe City Hall, 150 N. Pine Street, Globe, AZ 85501
- Phone
- 928-425-7146 ext. 219
- kestrada@globeaz.gov
- Office hours
- Permit Technician: Katrina Estrada, (928) 425-7146 ext. 219. Building Inspector: Gary Grimes, (928) 961-0158. Fax: 928-425-4820. Specific published office hours were not found on the City's live 'How to Obtain Permits' page as of July 2026 — City Hall is located at 150 N. Pine Street, Globe, AZ 85501. Applications may be submitted in person at City Hall or online via the City's CitizenServe portal (citizenserve.com/globeaz, installation ID 469), which lists permit-specific application types (Building Permit - New Construction, Stand-Alone Building/Electrical/Mechanical/Plumbing, OTC Electrical/Mechanical/Plumbing/Demolition, Photovoltaic, Pool and Spa, Manufactured Home, Sign, Demolition, Certificate of Occupancy, Temporary CO, and others).
- Website
- Official site
Published scheduling rules
- Inspections must be requested through the CitizenServe Online Portal at least one day in advance of the desired inspection date (Fire Sprinkler & Fire Alarm System Permit)
Inspection sequence
Applies to: Manufactured Home / Park Model Permit
- 1
Ground Set/Foundation/Stem Wall
Verifies anchoring, foundation, and stem wall installation per manufacturer instructions and adopted IRC requirements
- 2
Electrical/Utility Connection
Verifies electrical panel, installation, and water/sewer connections
- 3
Final
Skirting and perimeter enclosure verified complete
Applies to: Residential Building Permit (New Construction)
- 1
Foundation/Footing
Before concrete pour
- 2
Framing
Structural framing, connections, and egress per 2021 IRC and City of Globe design criteria
- 3
Final / Certificate of Occupancy
All work complete per approved plans; Certificate of Occupancy fee of $70 applies
Applies to: Sign Permit (Commercial/Business Signage)
- 1
Footing Inspection
Required for freestanding signs exceeding 50 square feet in area and/or exceeding 30 inches in height (Sec. 14-13-13(a))
- 2
Electrical Inspection
Required for any sign containing electrical wiring; electrical components must bear the label of an approved testing agency (Sec. 14-13-13(b))
- 3
Final/Shop Inspection
Verifies the completed sign was constructed according to the approved application and valid sign permit, including inspection of braces, anchors, supports, and connections (Sec. 14-13-13(c)-(d))
Applies to: Stand-Alone Building Permit (Additions, Remodels, Accessory Structures)
- 1
Foundation/Footing
Required before concrete pour for additions or accessory structures with foundations
- 2
Framing
Structural connections to existing structure or accessory structure framing
- 3
Final
Completed work verified against approved plans
Applies to: Certificate of Occupancy (including Change of Use)
- 1
Final Building Inspection
Building Official verifies the completed work or existing space meets all applicable building code requirements for the certificate/change of use being sought
- 2
Final Fire Inspection
Fire Marshal sign-off confirming fire/life-safety code compliance, billed separately as the Fire C of O fee
Applies to: Electrical Permit (OTC / Stand-Alone)
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed
- 2
Final
Devices installed and connections verified per 2020 NEC
Applies to: Fire Sprinkler & Fire Alarm System Permit
- 1
Fire Protection System Rough-In / Underground Inspection
Inspection of underground piping, rough-in sprinkler/alarm wiring and devices prior to concealment, conducted by the Fire Marshal or designee
- 2
Fire Protection System Final Inspection
Final acceptance test/inspection of the completed fire sprinkler or fire alarm system prior to occupancy, requested through the CitizenServe portal at least one day in advance
Applies to: Mechanical / HVAC Permit (OTC / Stand-Alone)
- 1
Rough-In
Ductwork and equipment placement before walls closed (ducted systems)
- 2
Final
Equipment operational, clearances verified
Applies to: Plumbing Permit (OTC / Stand-Alone)
- 1
Rough-In
After pipes installed, before walls closed
- 2
Final
Fixtures connected, water heater connections verified, no leaks
Applies to: Solar Photovoltaic (PV) Permit
- 1
Rough Electrical
Conduit runs, disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, and interconnection point verified
Applies to: Swimming Pool / Spa / Hot Tub Permit
- 1
Pool/Mechanical/Electric/Plumbing
Combined inspection of pool shell, equipment, electrical bonding/grounding, and plumbing per the flat fee structure
- 2
Barrier/Final
Verifies compliance with the 60-inch enclosure/barrier requirement and self-closing/self-latching gate hardware
Final inspection only: Demolition Permit, EV Charger / Electric Vehicle Charging Station Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Globe building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
City of Globe building permits
Get alerts for City of Globe
We'll email you when City of Globe's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.