Skip to main content
PermitBase

Commercial Building Permit in City of Globe, Arizona

Required for new commercial construction, additions, and tenant-improvement (TI) build-outs in the City of Globe, reviewed against the 2021 IBC and City of Globe amendments (Ordinance No. 889, effective late 2024). Globe does NOT have a separately named 'Tenant Improvement' or 'Commercial TI' permit product in its CitizenServe portal or Fee Schedule Resolution No. 1904 -- confirmed via the same permit-category listing and fee-schedule full-text review already relied on for this jurisdiction's certificate-of-occupancy-permit entry (which independently confirmed no distinct Change of Use/Change of Occupancy product exists either). Tenant-improvement work is instead processed through this same Building Permit application (for a full new build-out) or the Stand-Alone Building Permit (for a partial remodel not requiring a full new permit), billed off the same general Permit Valuation Fee Table 1-A used for new construction, followed by the Certificate of Occupancy process if occupancy classification or use is changing. Applications are submitted through the City's CitizenServe online portal (Building Permit - New Construction application type) or in person at Globe City Hall, 150 N. Pine Street. Unlike residential permits, commercial building permits are reviewed on the City's published 30-working-day commercial plan-review track (vs. 15 working days for residential) and separately require a Planning and Zoning Plan Review ($650.00 for Commercial/Multi-Family, vs. $50.00 for Residential) in addition to the Building Safety Department's plan review.

Verified 2026-07-29 · Source

When you need this permit

  • Building permit required for new commercial construction, commercial additions, and commercial tenant-improvement (TI) build-outs within Globe city limits
  • Plans must comply with the 2021 IBC and City of Globe amendments (Ordinance No. 889); occupancy classification (e.g., B Business, M Mercantile, A Assembly, S-1/S-2 Storage) determines the applicable construction-type requirements and valuation rate
  • Building plan review (Building, Plumbing, Mechanical, Electrical, Footing/Foundation, Fire sprinkler, Fire alarm) follows the City's published 30-working-day commercial plan-review timeframe, distinct from the 15-working-day residential track -- per the City's Plan Submittal and Review page
  • A separate Planning and Zoning Plan Review fee of $650.00 applies to Commercial/Multi-Family projects (vs. $50.00 for Residential), in addition to the Building Safety Department's own plan-review fees
  • Larger or new-development commercial projects may also require a Design and Site Plan Review (fee tiers of $500.00 'Major' or $250.00 'Minor' are published, but the City's own criteria distinguishing which projects fall into each tier were not found published as of July 2026)
  • Construction documents must be prepared by a registered design professional where required by Arizona statute; submittal documents must be merged into one document and submitted in an unlocked digital/electronic format
  • Permit valuation is applicant-estimated; the Building Official cross-checks against the currently adopted February 2024 ICC Building Valuation Data Table (Table 1-B), which publishes distinct per-square-foot rates by occupancy group and construction type (e.g., B Business Type VB $200.78/sq ft, Type IIB $257.82/sq ft, Type IA $289.51/sq ft; M Mercantile Type VB $136.24/sq ft; S-1 Storage-moderate hazard Type VB $84.50/sq ft), and may deny underestimated valuations
  • No separate Tenant Improvement or Change of Use/Change of Occupancy permit product exists in Globe's CitizenServe portal or fee schedule -- TI work and occupancy changes are processed via this same Building Permit / Stand-Alone Building Permit path, followed by the Certificate of Occupancy application where occupancy or use is changing
  • Permit applications expire 180 calendar days after filing if not pursued in good faith or issued; issued permits become invalid if work is not commenced within 180 calendar days or is suspended/abandoned for 180 calendar days

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on Valuation (Table 1-A / Permit Valuation Fee)City of Globe Fee Schedule Resolution No. 1904, Exhibit A, Permit Valuation Fee table (same sliding-scale table used for all building permits, residential and commercial), effective April 22, 2025
$33.00 ($1-$500); $33.00 + $5.00 per additional $100 to $2,000; $97.00 + $14.00 per additional $1,000 to $25,000; $545.00 + $14.00 per additional $1,000 to $50,000; $897.00 + $9.00 per additional $1,000 to $100,000; $1,384.00 + $7.00 per additional $1,000 to $500,000; $4,027.00 + $5.00 per additional $1,000 to $1,000,000; $7,827.00 + $3.00 per additional $1,000 to $5,000,000; $18,327.00 + $1.00 per additional $1,000 above $5,000,000
Valuation basis for commercial construction (examples)City of Globe Fee Schedule Resolution No. 1904, Exhibit A, Table 1-B (Square Foot Construction Costs); figures verified directly against the table image in the adopted fee-schedule PDF, not a third-party summary. Full table covers all IBC occupancy groups (A, B, E, F, H, I, M, R, S, U) across all nine construction types.
Per February 2024 ICC Building Valuation Data Table (Table 1-B): B Business — $289.51/sq ft (Type IA), $257.82/sq ft (Type IIB), $200.78/sq ft (Type VB); M Mercantile — $203.29/sq ft (Type IA), $136.24/sq ft (Type VB); S-1 Storage, moderate hazard — $148.46/sq ft (Type IA), $84.50/sq ft (Type VB)
Plan Review (New/Revisions/Additions) — Building SafetyCity of Globe Fee Schedule Resolution No. 1904, Exhibit A, Community Development Department-Building Safety-Planning and Zoning, Plan Review Fees section; a 65% multiplier is also referenced in the same section
$70/hour (standard); $140/hour (expedited)
Planning and Zoning Plan Review — Commercial/Multi-FamilyCity of Globe Fee Schedule Resolution No. 1904, Exhibit A, Planning and Zoning Plan Review section (Residential is billed separately at $50.00)
$650.00
Design and Site Plan ReviewCity of Globe Fee Schedule Resolution No. 1904, Exhibit A, Design and Site Plan Review section; the City's own criteria for what qualifies as Major vs. Minor were not found published as of July 2026
$500.00 (Major); $250.00 (Minor)
Technology FeeCity of Globe Fee Schedule Resolution No. 1904, Exhibit A, Community Development Department-Building Safety Admin fee section
Assessed on permits over $500 (rate per Admin fee section)

Review timeline

Plan reviewCity of Globe’s published plan-review target
30–30 business days

How long did your Commercial Building Permit permit actually take in City of Globe?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Framing / Rough-In

    Structural framing and MEP (mechanical/electrical/plumbing) rough-in, plus fire sprinkler/alarm rough-in where a fire protection system permit is also required

  3. 3

    Final / Certificate of Occupancy

    All work complete per approved plans; a separate Certificate of Occupancy application and fee ($70 Building sign-off + $70 Fire sign-off) is required before occupancy

See the full City of Globe inspection guide — scheduling & re-inspection fees →

Tips

  • The City of Globe's Plan Submittal and Review page publishes a real 30-working-day commercial plan review timeframe (vs. 15 working days for residential). Source: City of Globe Plan Submittal and Review page (globeaz.gov/o/cog/page/plan-submittal-and-review).
  • Budget for the separate $650 Planning and Zoning Plan Review fee (Commercial/Multi-Family) on top of the Building Safety Department's own hourly plan-review charges -- this is a distinct line item from the base Building Permit Fee.
  • Globe has no distinct 'Tenant Improvement' or 'Commercial TI' permit product -- a TI build-out is processed as either a full Building Permit or a Stand-Alone Building Permit (60% of Table 1-A) depending on scope, the same path used for any other commercial building work.
  • Commercial valuation swings widely by occupancy classification and construction type under Table 1-B -- e.g., a Type VB Business (B) occupancy is valued at $200.78/sq ft vs. $84.50/sq ft for a Type VB Storage (S-1) occupancy, so confirm the correct occupancy group and construction type before estimating your permit fee.

Frequently asked questions

City of Globe requires a commercial building permit for: Building permit required for new commercial construction, commercial additions, and commercial tenant-improvement (TI) build-outs within Globe city limits; Plans must comply with the 2021 IBC and City of Globe amendments (Ordinance No. 889); occupancy classification (e.g., B Business, M Mercantile, A Assembly, S-1/S-2 Storage) determines the applicable construction-type requirements and valuation rate; Building plan review (Building, Plumbing, Mechanical, Electrical, Footing/Foundation, Fire sprinkler, Fire alarm) follows the City's published 30-working-day commercial plan-review timeframe, distinct from the 15-working-day residential track -- per the City's Plan Submittal and Review page; A separate Planning and Zoning Plan Review fee of $650.00 applies to Commercial/Multi-Family projects (vs. $50.00 for Residential), in addition to the Building Safety Department's own plan-review fees; Larger or new-development commercial projects may also require a Design and Site Plan Review (fee tiers of $500.00 'Major' or $250.00 'Minor' are published, but the City's own criteria distinguishing which projects fall into each tier were not found published as of July 2026); Construction documents must be prepared by a registered design professional where required by Arizona statute; submittal documents must be merged into one document and submitted in an unlocked digital/electronic format; Permit valuation is applicant-estimated; the Building Official cross-checks against the currently adopted February 2024 ICC Building Valuation Data Table (Table 1-B), which publishes distinct per-square-foot rates by occupancy group and construction type (e.g., B Business Type VB $200.78/sq ft, Type IIB $257.82/sq ft, Type IA $289.51/sq ft; M Mercantile Type VB $136.24/sq ft; S-1 Storage-moderate hazard Type VB $84.50/sq ft), and may deny underestimated valuations; No separate Tenant Improvement or Change of Use/Change of Occupancy permit product exists in Globe's CitizenServe portal or fee schedule -- TI work and occupancy changes are processed via this same Building Permit / Stand-Alone Building Permit path, followed by the Certificate of Occupancy application where occupancy or use is changing; Permit applications expire 180 calendar days after filing if not pursued in good faith or issued; issued permits become invalid if work is not commenced within 180 calendar days or is suspended/abandoned for 180 calendar days. If your project isn't listed, confirm with City of Globe Building Safety Department at 928-425-7146 ext. 219 before starting work.

Yes. Commercial and multi-family projects are billed an additional $650.00 Planning and Zoning Plan Review fee (vs. $50.00 for residential), and larger or new-development projects may also incur a Design and Site Plan Review fee of $500.00 (Major) or $250.00 (Minor), per City of Globe Fee Schedule Resolution No. 1904.

30 working days, per the City of Globe's Plan Submittal and Review page -- double the 15-working-day timeframe published for residential plan review.

You'll need: Building Permit Application (CitizenServe: Building Permit - New Construction); Site/Plot Plan; Construction Documents; Planning and Zoning Plan Review Submittal. See the required-documents checklist on this page for details on each.

City of Globe requires 3 inspection(s) for a commercial building permit, in order: Foundation/Footing, Framing / Rough-In, Final / Certificate of Occupancy. Schedule each through City of Globe Building Safety Department (928-425-7146 ext. 219).

Apply through City of Globe Building Safety Department at Globe City Hall, 150 N. Pine Street, Globe, AZ 85501. Phone: 928-425-7146 ext. 219, email: kestrada@globeaz.gov. Office hours: Permit Technician: Katrina Estrada, (928) 425-7146 ext. 219. Building Inspector: Gary Grimes, (928) 961-0158. Fax: 928-425-4820. Specific published office hours were not found on the City's live 'How to Obtain Permits' page as of July 2026 — City Hall is located at 150 N. Pine Street, Globe, AZ 85501. Applications may be submitted in person at City Hall or online via the City's CitizenServe portal (citizenserve.com/globeaz, installation ID 469), which lists permit-specific application types (Building Permit - New Construction, Stand-Alone Building/Electrical/Mechanical/Plumbing, OTC Electrical/Mechanical/Plumbing/Demolition, Photovoltaic, Pool and Spa, Manufactured Home, Sign, Demolition, Certificate of Occupancy, Temporary CO, and others).. Official information: https://www.globeaz.gov/o/cog/page/how-to-obtain-permits.

City of Globe, Arizona has adopted: Arizona has NO statewide mandatory building code for general construction — code adoption is a per-jurisdiction (city/town/county) authority under state enabling statutes (A.R.S. § 9-802 for municipal adoption by reference). The City of Globe independently adopts and administers its own construction codes through its Building Safety Department; it does not defer to Gila County for permitting within city limits. Source: City of Globe Ordinance No. 889 (adopted October 22, 2024), Section 1 and Exhibit A, Section 12-1-4(A).; As of a 2025 industry directory listing (Arizona Building Officials/AZBO), Globe was shown still using the 2003 International Codes and 2002 NEC — this research independently confirmed via the City's own Ordinance No. 889 that Globe has SINCE UPDATED: Ordinance No. 889, adopted by the Mayor and Council on October 22, 2024 (effective per A.R.S. § 9-812, 30 days after publication/posting), repealed the former Article 12-1 'Building Safety Code' and Article 5-2 'Fire Prevention Code' in their entirety and adopted by reference the 2021 edition of the International Building, Residential, Mechanical, Plumbing, Fuel Gas, Energy Conservation, Fire, Property Maintenance, and Existing Building Codes (all ICC), plus the 2021 International Swimming Pool and Spa Code, together with the 2020 National Electrical Code (NFPA 70) — each with City of Globe local amendments. The prior 2003 I-Codes/2002 NEC citation in the AZBO directory is confirmed STALE as of this update; 2021 ICC/2020 NEC is the current, verified code cycle. Source: City of Globe Ordinance No. 889, Recitals and Exhibit A, Section 2 (adopted 10/22/2024, on file at globeaz.gov).; 2021 International Building Code (IBC), published by the International Code Council, Inc., adopted by reference with City of Globe amendments (Ordinance 889, Exhibit A §12-1-8), including adopted Appendix C (Group U — Agricultural Buildings), Appendix F (Rodent Proofing), Appendix H (Signs), and Appendix I (Patio Covers). Exception: detached one- and two-family dwellings and townhouses not more than three stories above grade with a separate means of egress, and their accessory structures, comply with the IRC instead. Source: City of Globe Ordinance No. 889, Exhibit A, Section 12-1-8.; 2021 International Residential Code (IRC) for One- and Two-Family Dwellings, published by ICC, adopted by reference with City of Globe amendments (Ordinance 889, Exhibit A §12-1-9), including adopted Appendices AA, AB, AC, AE (Manufactured Housing Used As Dwellings), AG, AH (Patio Covers), AJ (Existing Buildings and Structures), AQ (Tiny Homes), AU (Cob/Monolithic Adobe Construction), and AW (3D-Printed Building Construction). Source: City of Globe Ordinance No. 889, Exhibit A, Section 12-1-9.; 2021 International Mechanical Code (IMC), adopted by reference with City of Globe amendments, including Appendix A (Chimney Connector Pass-Throughs). Source: City of Globe Ordinance No. 889, Exhibit A, Section 12-1-10.; 2021 International Plumbing Code (IPC), adopted by reference with City of Globe amendments, including Appendix C (Structural Safety 150) and Appendix E (Sizing of Water Piping Systems). Source: City of Globe Ordinance No. 889, Exhibit A, Section 12-1-11.; 2021 International Fuel Gas Code (IFGC), adopted by reference with City of Globe amendments, including Appendices A, B, and C (gas piping sizing and venting systems). Source: City of Globe Ordinance No. 889, Exhibit A, Section 5-1-12 (numbered within Exhibit A as shown in the ordinance).; 2020 National Electrical Code (NEC / NFPA 70), published by the National Fire Protection Association, adopted by reference with limited City of Globe amendments (garage receptacle placement under Article 210.52(G); equipment grounding conductor types under Article 250.118). Source: City of Globe Ordinance No. 889, Exhibit A, Section 12-1-13.; 2021 International Energy Conservation Code (IECC), adopted by reference with City of Globe amendments, including Appendix CB (Solar Ready Zone — Commercial); Climate Zone 2 Maximum Energy Rating Index changed from 52 to 64; RESNET third-party testing/inspection protocol adopted for building envelope, air leakage, and duct tightness testing. Source: City of Globe Ordinance No. 889, Exhibit A, Section 12-1-14.; 2021 International Fire Code (IFC), adopted by reference as the City's uniform fire code with City of Globe amendments, including adopted Appendices B, C, D, E, F, G, H, I, and L; administered by the Globe Fire Department Fire Code Official/Fire Marshal, with the Building Official having equal enforcement authority. Source: City of Globe Ordinance No. 889, Exhibit A, Section 12-1-15.; 2021 International Property Maintenance Code (IPMC), adopted by reference with City of Globe amendments, including Appendix A (Boarding Standards). Source: City of Globe Ordinance No. 889, Exhibit A, Section 12-1-16.; 2021 International Existing Building Code (IEBC), adopted by reference with City of Globe amendments, including Appendix A1 (Seismic Strengthening Provisions for Unreinforced Masonry Bearing Wall Buildings) and Appendix A3 (Prescriptive Seismic Strengthening for Cripple Walls/Sill Plate Anchorage of Light Wood-Frame Residential Buildings). Source: City of Globe Ordinance No. 889, Exhibit A, Section 12-1-17.; 2021 International Swimming Pool and Spa Code (ISPSC), adopted by reference with City of Globe amendments; swimming pool, spa, and hot tub enclosures and safety devices must additionally comply with Arizona Revised Statutes § 36-1681 and Arizona Administrative Code Title 18, Chapter 5 for public/semi-public pools, whichever standard is more restrictive. Source: City of Globe Ordinance No. 889, Exhibit A, Sections 12-1-18 and 101.4.11 (IBC amendment).; ICC A117.1 Accessibility standard, applied together with Arizona Attorney General Administrative Rules R10-3-401 through R10-3-404 (2010 ADA Standards for Accessible Design) and A.R.S. §§ 41-1492 through 41-1492.12 — whichever standard provides the greatest degree of accessibility governs. Source: City of Globe Ordinance No. 889, Exhibit A, Section 1101/1102 (IBC Chapter 11 amendment).; Manufactured homes, mobile homes, factory-built buildings, and Park Model living units require a City of Globe permit for site placement, foundation, skirting/perimeter enclosure, and utility connection (IRC Appendix AE as amended); statewide construction/installation standards for factory-built structures are separately regulated by the Arizona Department of Fire, Building and Life Safety, Office of Manufactured Housing (A.R.S. § 41-4001 et seq.). Source: City of Globe Ordinance No. 889, Exhibit A (IRC Appendix AE amendment); Fee Schedule Resolution No. 1904, Exhibit A (Manufactured Homes fee section).. Local amendments apply — see the City of Globe overview page for the full list.

No. Confirmed via the City's own CitizenServe permit-category listing and a full-text review of Fee Schedule Resolution No. 1904 -- there is no separately named Tenant Improvement or Commercial TI permit product. TI work is processed through the same Building Permit (for a full build-out) or Stand-Alone Building Permit (for a partial remodel) used for other commercial building work, followed by a Certificate of Occupancy application if occupancy or use is changing.

Sources & verification

Verified against official sources. Last reviewed 2026-07-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Globe building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in City of Globe.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.