Commercial Building Permit — City of Globe, Arizona · Requirements sheet
Verified 2026-07-29 · Source: https://www.globeaz.gov/o/cog/page/fee-schedules
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in City of Globe, Arizona
Required for new commercial construction, additions, and tenant-improvement (TI) build-outs in the City of Globe, reviewed against the 2021 IBC and City of Globe amendments (Ordinance No. 889, effective late 2024). Globe does NOT have a separately named 'Tenant Improvement' or 'Commercial TI' permit product in its CitizenServe portal or Fee Schedule Resolution No. 1904 -- confirmed via the same permit-category listing and fee-schedule full-text review already relied on for this jurisdiction's certificate-of-occupancy-permit entry (which independently confirmed no distinct Change of Use/Change of Occupancy product exists either). Tenant-improvement work is instead processed through this same Building Permit application (for a full new build-out) or the Stand-Alone Building Permit (for a partial remodel not requiring a full new permit), billed off the same general Permit Valuation Fee Table 1-A used for new construction, followed by the Certificate of Occupancy process if occupancy classification or use is changing. Applications are submitted through the City's CitizenServe online portal (Building Permit - New Construction application type) or in person at Globe City Hall, 150 N. Pine Street. Unlike residential permits, commercial building permits are reviewed on the City's published 30-working-day commercial plan-review track (vs. 15 working days for residential) and separately require a Planning and Zoning Plan Review ($650.00 for Commercial/Multi-Family, vs. $50.00 for Residential) in addition to the Building Safety Department's plan review.
Verified 2026-07-29 · Source
When you need this permit
- Building permit required for new commercial construction, commercial additions, and commercial tenant-improvement (TI) build-outs within Globe city limits
- Plans must comply with the 2021 IBC and City of Globe amendments (Ordinance No. 889); occupancy classification (e.g., B Business, M Mercantile, A Assembly, S-1/S-2 Storage) determines the applicable construction-type requirements and valuation rate
- Building plan review (Building, Plumbing, Mechanical, Electrical, Footing/Foundation, Fire sprinkler, Fire alarm) follows the City's published 30-working-day commercial plan-review timeframe, distinct from the 15-working-day residential track -- per the City's Plan Submittal and Review page
- A separate Planning and Zoning Plan Review fee of $650.00 applies to Commercial/Multi-Family projects (vs. $50.00 for Residential), in addition to the Building Safety Department's own plan-review fees
- Larger or new-development commercial projects may also require a Design and Site Plan Review (fee tiers of $500.00 'Major' or $250.00 'Minor' are published, but the City's own criteria distinguishing which projects fall into each tier were not found published as of July 2026)
- Construction documents must be prepared by a registered design professional where required by Arizona statute; submittal documents must be merged into one document and submitted in an unlocked digital/electronic format
- Permit valuation is applicant-estimated; the Building Official cross-checks against the currently adopted February 2024 ICC Building Valuation Data Table (Table 1-B), which publishes distinct per-square-foot rates by occupancy group and construction type (e.g., B Business Type VB $200.78/sq ft, Type IIB $257.82/sq ft, Type IA $289.51/sq ft; M Mercantile Type VB $136.24/sq ft; S-1 Storage-moderate hazard Type VB $84.50/sq ft), and may deny underestimated valuations
- No separate Tenant Improvement or Change of Use/Change of Occupancy permit product exists in Globe's CitizenServe portal or fee schedule -- TI work and occupancy changes are processed via this same Building Permit / Stand-Alone Building Permit path, followed by the Certificate of Occupancy application where occupancy or use is changing
- Permit applications expire 180 calendar days after filing if not pursued in good faith or issued; issued permits become invalid if work is not commenced within 180 calendar days or is suspended/abandoned for 180 calendar days
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour
- 2
Framing / Rough-In
Structural framing and MEP (mechanical/electrical/plumbing) rough-in, plus fire sprinkler/alarm rough-in where a fire protection system permit is also required
- 3
Final / Certificate of Occupancy
All work complete per approved plans; a separate Certificate of Occupancy application and fee ($70 Building sign-off + $70 Fire sign-off) is required before occupancy
See the full City of Globe inspection guide — scheduling & re-inspection fees →
Tips
- The City of Globe's Plan Submittal and Review page publishes a real 30-working-day commercial plan review timeframe (vs. 15 working days for residential). Source: City of Globe Plan Submittal and Review page (globeaz.gov/o/cog/page/plan-submittal-and-review).
- Budget for the separate $650 Planning and Zoning Plan Review fee (Commercial/Multi-Family) on top of the Building Safety Department's own hourly plan-review charges -- this is a distinct line item from the base Building Permit Fee.
- Globe has no distinct 'Tenant Improvement' or 'Commercial TI' permit product -- a TI build-out is processed as either a full Building Permit or a Stand-Alone Building Permit (60% of Table 1-A) depending on scope, the same path used for any other commercial building work.
- Commercial valuation swings widely by occupancy classification and construction type under Table 1-B -- e.g., a Type VB Business (B) occupancy is valued at $200.78/sq ft vs. $84.50/sq ft for a Type VB Storage (S-1) occupancy, so confirm the correct occupancy group and construction type before estimating your permit fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Globe building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in City of Globe.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in City of Globe
Commercial Building Permit in other cities
Compare commercial building permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your City of Globe project checklist
Describe your project once and get every permit, document, and fee it triggers in City of Globe — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →