Demolition Permit — City of Globe, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.globeaz.gov/o/cog/page/fee-schedules
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in City of Globe, Arizona
Required for demolition of any residential or commercial structure in Globe. OTC demolition fees differ for residential vs. commercial. Demolition permits are unique among Globe permits in expiring 90 calendar days after issuance with no extension allowed.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required before demolishing a residential or commercial structure within Globe city limits
- Demolition permits expire 90 calendar days after issuance and may NOT be extended (unlike other permit types, which allow one 180-day extension)
- All utilities must be terminated per code prior to demolition
- Applicant should confirm asbestos abatement / air quality clearance requirements applicable to Gila County/ADEQ prior to demolition, as is standard practice statewide for structure demolition
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Final
Verifies utility termination and site condition after demolition is complete
See the full City of Globe inspection guide — scheduling & re-inspection fees →
Tips
- The City of Globe's Plan Submittal and Review page publishes a real 15-working-day residential plan review timeframe, which applies to demolition permits requiring plan review. Source: City of Globe Plan Submittal and Review page (globeaz.gov/o/cog/page/plan-submittal-and-review).
- Demolition permits are the one permit type in Globe's code that CANNOT be extended past their 90-calendar-day validity window (Ordinance No. 889, Exhibit A, Section 105.5 Exception 1) — plan the demolition timeline accordingly.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Globe building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
City of Globe's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for City of Globe yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when City of Globe lands. Privacy.
Other permits in City of Globe
Demolition Permit in other cities
Compare demolition permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your City of Globe project checklist
Describe your project once and get every permit, document, and fee it triggers in City of Globe — in one checklist. Free, for any city and any number of projects.
Get started →