Electrical Permit (OTC / Stand-Alone) in City of Globe, Arizona
Required for electrical installation, alteration, or repair work in Globe, governed by the 2020 NEC as adopted and amended by the City. Common over-the-counter (OTC) electrical items (panel replacement, sub-panel wiring, well/pump, additional circuits) are flat-fee permits; larger stand-alone electrical work is billed as a percentage of the Building Permit Fee Table.
Verified 2026-07-06 · Source
When you need this permit
- Electrical permit required for panel work, sub-panel wiring, well/pump connections, additional circuits, and other electrical installations
- Governed by the 2020 NEC as adopted by the City of Globe, with limited local amendments (garage receptacle placement per Article 210.52(G); equipment grounding conductor types per Article 250.118)
- Common OTC electrical items are flat-fee, counter-issued permits; larger scope electrical work not part of a full building permit is a Stand-Alone Electrical Permit billed at a percentage of the Building Permit Fee Table
- Apply via the CitizenServe online portal (Over-The-Counter Electrical Permit or Stand-Alone Electrical Permit application types) or in person at Globe City Hall
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed
- 2
Final
Devices installed and connections verified per 2020 NEC
See the full City of Globe inspection guide — scheduling & re-inspection fees →
Tips
- The City of Globe's Plan Submittal and Review page publishes a real 15-working-day residential plan review timeframe, which applies to electrical permits requiring plan review. OTC (over-the-counter) permits are, by design, intended for same-visit counter issuance where no separate plan review is required. Source: City of Globe Plan Submittal and Review page (globeaz.gov/o/cog/page/plan-submittal-and-review).
- OTC electrical items are flat-fee; larger-scope electrical work not tied to a full building permit is billed as a Stand-Alone Electrical Permit at 10% of the valuation-based Building Permit Fee Table plus a $30 administrative fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the City of Globe building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in City of Globe
Electrical Permit (OTC / Stand-Alone) in other cities
Compare electrical permit (otc / stand-alone) fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your City of Globe project checklist
Describe your project once and get every permit, document, and fee it triggers in City of Globe — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →