Electrical / Plumbing / Mechanical Like-for-Like Replacement Permit — Show Low, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.showlowaz.gov/page/fee-schedules
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electrical / Plumbing / Mechanical Like-for-Like Replacement Permit in Show Low, Arizona
Flat-fee permit covering routine like-for-like replacement of hardwired electrical, plumbing, and mechanical systems and appliances (e.g., water heaters, panels, HVAC equipment) in single-family and two-family residential dwellings in Show Low, where no other system modification occurs.
Verified 2026-07-06 · Source
When you need this permit
- Covers routine like-for-like replacement of hardwired electrical, plumbing, and mechanical systems and appliances for single-family and 2-family residential dwellings
- Appliances are those defined in the International Mechanical Code and International Plumbing Code — does not include countertop, convenience, laundry, or similar appliances
- Governed by the 2018 IMC, 2018 IPC, and 2017 NEC as adopted by the City of Show Low
- Applicant must verify contractor licensing (Arizona ROC) or owner-exemption status prior to issuance Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In (if applicable)
Wiring, piping, or ductwork verification before closure, where the scope requires it
- 2
Final
Replacement verified operational and code-compliant
See the full Show Low inspection guide — scheduling & re-inspection fees →
Tips
- This $30 flat fee is specifically for LIKE-for-like replacement with no other system modification; any change in design, capacity, or routing takes the project out of this flat-fee category and into the standard valuation-based Building Permit Fee (1997 UBC schedule) with 20% plan review.
- Even though this is a low-cost flat-fee permit, it still goes through the City's standard § 18.15.070 plan review time frame election (Standard 30 working days / Non-Standard 40 working days) — no dedicated same-day track for this permit type was found published by the City.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Show Low building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Show Low
Compare electrical / plumbing / mechanical like-for-like replacement permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Show Low project checklist
Describe your project once and get every permit, document, and fee it triggers in Show Low — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →