EV Charger / EVSE Permit — Show Low, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.showlowaz.gov/page/fee-schedules
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Show Low, Arizona
The City of Show Low has no dedicated EV charger/EVSE permit application or fee line — confirmed by reviewing the City's Fee Schedules page and City Permits & Applications page, which list a dedicated Solar Permit Application but nothing for EV chargers. An EV charging station (Level 2 or DC fast charger) installation does NOT qualify for the City's $30 flat-fee Electrical/Plumbing/Mechanical Like-for-Like Replacement Permit, since that category is expressly limited to routine LIKE-for-like replacement of existing hardwired systems with no other modification — a new dedicated EV charger circuit is new electrical work, not a replacement. It is instead processed under the standard valuation-based Building Permit Fee (1997 UBC schedule) plus Plan Review Fee, the same fee mechanism this file's solar-pv-permit entry documents for the electrical scope of a PV installation.
Verified 2026-07-20 · Source
When you need this permit
- Building Addition Permit Application required, submitted at 180 N. 9th Street, Show Low, AZ 85901 — no dedicated EV-charger-specific application exists
- Does NOT qualify for the $30 flat-fee Like-for-Like Replacement Permit, since that category excludes any change in design, capacity, or routing (a new EV charger circuit is new work, not a like-for-like replacement of an existing hardwired system)
- Applicant selects Standard Plan Review (30 working days) or Non-Standard Plan Review (40 working days) per § 18.15.070, the same election documented for solar and other building permits in this file
- Governed by the 2017 NEC as adopted and amended by the City of Show Low
- Contractor licensing verification (Arizona ROC) required prior to permit issuance, or confirm owner-exemption status Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect/breaker placement before energizing
- 2
Final
Charger mounted, connections verified, panel labeled per 2017 NEC as adopted
See the full Show Low inspection guide — scheduling & re-inspection fees →
Tips
- An EV charger circuit does NOT qualify for Show Low's $30 flat-fee Like-for-Like Replacement Permit — that fee is strictly for replacing an existing hardwired system with no design/capacity/routing change. A new EV charger circuit is billed under the standard valuation-based Building Permit Fee plus 20% Plan Review Fee instead.
- No dedicated expedited/same-day review track for EV chargers was found published by the City — expect the same 30/40-working-day Standard/Non-Standard election under § 18.15.070 that applies to solar and other building permits.
- If the EV charger installation is a simple replacement of an already-existing dedicated EV charger circuit with no modification, it may qualify for the $30 Like-for-Like fee — confirm with the Building Safety Department which category applies to your specific scope.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Show Low building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Show Low
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →