Residential Addition / Remodel Permit in Show Low, Arizona

Required for room additions, remodels, and alterations to existing residential structures in the City of Show Low, using the City's Building Addition Permit Application. Reviewed against the 2018 IRC/IBC and City of Show Low amendments.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for additions and remodels affecting structural, electrical, plumbing, or mechanical systems
  • Applicant selects Standard Plan Review (30 working days) or Non-Standard Plan Review (40 working days) per § 18.15.070
  • A minimum $50.00 deposit must be submitted with the Building Addition Permit Application
  • Plans must comply with City of Show Low Climatic and Geographic Design Criteria (90 mph wind, Exposure C; Seismic Zone B; 50 psf ground snow load; 18-inch frost line)
  • Repairs that only replace existing component parts with similar materials for maintenance (e.g., painting, floor coverings, cabinetry, storm doors/windows) are exempt from permit requirements per § 18.15.040, provided no addition, design change, or modification of exit facilities/fixtures/equipment is involved

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeCity of Show Low Fee Schedules page and Commercial/Addition Permit Applications
Formulated by the 1997 Uniform Building Code (UBC) valuation-based fee schedule
Plan Review Fee (Residential)City of Show Low Fee Schedules page; minimum $50.00 deposit submitted with the Building Addition Permit Application
20% of the Building Permit Fee
Like-for-Like Replacement (hardwired electrical, plumbing, or mechanical systems/appliances, single-family or 2-family)City of Show Low Fee Schedules page; excludes countertop, convenience, laundry, or similar appliances
$30 flat fee

Review timeline

Plan reviewShow Low’s published plan-review target
30–40 business days

How long did your Residential Addition / Remodel Permit permit actually take in Show Low?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footings

    Required before concrete pour for additions

  2. 2

    Framing

    Structural connections to the existing structure

  3. 3

    Rough Plumbing/Electrical/Mechanical

    Combined rough-in inspection where applicable

  4. 4

    Final

    Completed work verified against approved plans

See the full Show Low inspection guide — scheduling & re-inspection fees →

Tips

  • The Building Addition Permit Application requires only a $50.00 minimum deposit, versus $200 for new residential construction.
  • Like-for-like replacement of hardwired electrical, plumbing, or mechanical systems/appliances in a single-family or 2-family home is a flat $30 permit, regardless of the standard valuation-based fee formula.
  • Repairs using similar materials for maintenance only (painting, floor coverings, cabinetry, storm doors/windows) do not require a permit at all, per § 18.15.040 — but this exemption does not cover design changes or new fixtures/equipment.

Frequently asked questions

Yes, a building permit is required for room additions and remodels affecting structural, electrical, plumbing, or mechanical elements, using the City's Building Addition Permit Application and a minimum $50 deposit.

A flat $30 permit fee applies to routine like-for-like replacement of hardwired electrical, plumbing, and mechanical systems and appliances in single-family and two-family residential dwellings, per the City's Fee Schedules page.

Show Low's published plan-review target for a residential addition / remodel permit is 30–40 business days.

You'll need: Building Addition Permit Application; Site/Plot Plan. See the required-documents checklist on this page for details on each.

Show Low requires 4 inspection(s) for a residential addition / remodel permit, in order: Footings, Framing, Rough Plumbing/Electrical/Mechanical, Final. Schedule each through City of Show Low Building Safety Department (928-532-4053).

Apply through City of Show Low Building Safety Department at 180 N. 9th Street, Show Low, AZ 85901. Phone: 928-532-4053, email: jwilhelm@showlowaz.gov. Office hours: Monday - Friday, 9 a.m. - 12 p.m. and 1 p.m. - 4 p.m. (or by appointment), per the City of Show Low Building Safety page. The general Permits & Applications page separately lists City Hall hours as Monday - Friday, 9 a.m. - 4 p.m. (excluding holidays), and appointments are recommended (928-532-4050). The Inspection Line (928-532-4055) requires inspections to be called in 24 hours in advance; as of October 1, 2024, the cutoff for next-day inspections is 3:00 p.m. (previously 5:00 p.m.) — requests after 3:00 p.m. are scheduled two business days out.. Official information: https://www.showlowaz.gov/o/cosl/page/building-safety.

Show Low, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9). The City of Show Low independently adopts and administers its own construction codes through its Building Safety Department; it does not defer permitting to Navajo County. Source: City of Show Low Municipal Code Title 18, Chapter 18.05 (Building Codes), showlow.municipal.codes/Code/18.05.040.; 2018 International Building Code (IBC), together with its appendices and supplements, published by the International Code Council, adopted by reference (Show Low Municipal Code § 18.05.040). Source: City of Show Low Municipal Code § 18.05.040.; 2018 International Residential Code (IRC) for One- and Two-Family Dwellings, published by the International Code Council, adopted by reference, with Chapter 11 (Energy Efficiency) specifically excluded from adoption (Show Low Municipal Code § 18.05.040). Source: City of Show Low Municipal Code § 18.05.040.; 2018 International Mechanical Code (IMC), adopted by reference (Show Low Municipal Code § 18.05.040). Source: City of Show Low Municipal Code § 18.05.040; confirmed current on the City's live 'Show Low Codes & Standards' page (showlowaz.gov, page last updated 7/8/2021) and on the City's 2025/2026 permit application cover sheets (Residential, Commercial, Solar, Addition applications).; 2018 International Plumbing Code (IPC), adopted by reference (Show Low Municipal Code § 18.05.040). Source: City of Show Low Municipal Code § 18.05.040.; 2018 International Fuel Gas Code (IFGC), adopted by reference (Show Low Municipal Code § 18.05.040). Source: City of Show Low Municipal Code § 18.05.040.; 2017 National Electrical Code (NEC), published by the National Fire Protection Association, adopted by reference (Show Low Municipal Code § 18.05.040) — one edition behind the 2018 ICC family set. Source: City of Show Low Municipal Code § 18.05.040; confirmed current on the City's live 'Show Low Codes & Standards' page and 2025/2026 permit application cover sheets.; Fire Code: Show Low does not administer its own fire code — fire code jurisdiction and inspections are handled by Timber Mesa Fire & Medical District (928-537-5100), per every current City of Show Low building permit application cover sheet (Residential, Commercial, Solar, Addition). Source: City of Show Low permit application cover sheets, current as of 2025-2026 revisions.; ADA Accessibility: American National Standard ADA Accessibility Guidelines (2010 ADA Standards for Accessible Design) are adopted and required for new construction and alterations. Arizonans with Disabilities Act standards (A.R.S. Title 41, Chapter 9, Article 8) and implementing rules, declared a public record by City of Show Low Resolution No. 772, are adopted as an amendment to the IBC for both public entities and public accommodations/commercial facilities (applying to new construction and alterations commenced after September 3, 1996). Source: City of Show Low Municipal Code § 18.05.040.; Future code editions: when the City Council adopts a newer edition of the International Codes by resolution, either the most recent or the immediately previous edition may be used for building design for 12 months after adoption; the two editions' provisions may not be intermingled in a single building's design, and after 12 months only the newest adopted edition applies. Source: City of Show Low Municipal Code § 18.05.040.; Manufactured/mobile homes: as of March 28, 2025, the City of Show Low no longer issues manufactured home or factory-built building placement permits; both a City of Show Low Building Permit and a State of Arizona Manufactured Home Installation Permit (Arizona Department of Housing, Office of Manufactured Housing) are required for any manufactured home work still processed by the City. Manufactured/mobile homes must display a HUD compliance decal dated within 10 years of the building-permit application (or successor HUD standard), per City of Show Low Municipal Code § 18.05.050. Source: City of Show Low City Permits & Applications page (showlowaz.gov/o/cosl/page/city-permits-and-applications); City of Show Low Municipal Code § 18.05.050.. Local amendments apply — see the Show Low overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Show Low building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.