Residential Solar Photovoltaic (PV) Permit — Show Low, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.showlowaz.gov/o/cosl/page/city-permits-and-applications
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Solar Photovoltaic (PV) Permit in Show Low, Arizona
Required for installation of residential solar photovoltaic systems in the City of Show Low, using the City's dedicated Solar Permit Application. Governed by the 2017 NEC as adopted and amended by the City of Show Low.
Verified 2026-07-06 · Source
When you need this permit
- Solar Permit Application required, submitted at 180 N. 9th Street, Show Low, AZ 85901
- Applicant must select either an Existing Panel or Panel Upgrade option; if the selection or panel model changes after permit issuance, a resubmittal with additional fees is required
- Applicant selects Standard Plan Review (30 working days) or Non-Standard Plan Review (40 working days) per § 18.15.070
- A minimum $50.00 deposit must be submitted with the application
- Governed by the 2017 NEC as adopted by the City of Show Low
- Contractor licensing verification (Arizona ROC) required prior to permit issuance Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified
See the full Show Low inspection guide — scheduling & re-inspection fees →
Tips
- No dedicated expedited/same-day review track for solar PV was found published by the City of Show Low — solar permits go through the same 30/40-working-day Standard/Non-Standard election as other building permits under § 18.15.070.
- Changing the Electrical Panel selection (Existing vs. Upgrade) or the equipment model after permit issuance requires a resubmittal and additional fees — confirm final equipment specs before applying.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Show Low building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Show Low
Residential Solar Photovoltaic (PV) Permit in other cities
Compare residential solar photovoltaic (pv) permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Show Low project checklist
Describe your project once and get every permit, document, and fee it triggers in Show Low — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →