Show Low building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Show Low, Arizona.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
180 N. 9th Street, Show Low, AZ 85901
Phone
928-532-4053
Office hours
Monday - Friday, 9 a.m. - 12 p.m. and 1 p.m. - 4 p.m. (or by appointment), per the City of Show Low Building Safety page. The general Permits & Applications page separately lists City Hall hours as Monday - Friday, 9 a.m. - 4 p.m. (excluding holidays), and appointments are recommended (928-532-4050). The Inspection Line (928-532-4055) requires inspections to be called in 24 hours in advance; as of October 1, 2024, the cutoff for next-day inspections is 3:00 p.m. (previously 5:00 p.m.) — requests after 3:00 p.m. are scheduled two business days out.

Published scheduling rules

  • Inspections must be called in 24 hours in advance; as of October 1, 2024, requests made after 3:00 p.m. are scheduled two business days later rather than the next business day. (Residential Building Permit (New Construction))
  • Inspections must be called in at least 24 hours in advance via the Inspection Line (928-532-4055); as of October 1, 2024, the next-day cutoff moved from 5:00 p.m. to 3:00 p.m. — requests after 3:00 p.m. are scheduled two business days out rather than the next business day. (General)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footings

    Before concrete pour; no footing/foundation inspection approved without clearly delineated, accurate property lines and yard setbacks

  2. 2

    Stem Wall / Slab Reinforcement

    Verifies stem wall construction and slab reinforcement (fiber mesh, woven wire mesh, or 3/8-inch rebar at 30 in O.C.)

  3. 3

    Under-Floor Framing

    Framing beneath the floor system prior to enclosure

  4. 4

    Roof Sheathing/Nail

    Roof sheathing and nailing pattern before roofing material application

  5. 5

    Framing

    Structural framing, connections, and egress per 2018 IRC/IBC and City design criteria

  6. 6

    Insulation

    Wall (R-11 minimum) and ceiling (R-19 minimum) insulation, per City amendment to IRC Chapter 11

  7. 7

    Drywall Nail

    Fastening pattern verification prior to taping/finishing

  8. 8

    Water Service/Sewer Service, Underground Plumbing

    Underground utility connections before backfill

  9. 9

    Rough Plumbing/Framing/Electrical/Heating Ducts/Vents

    Combined rough-in inspection prior to wall closure

  10. 10

    Gas Yard Line, Final Gas Test

    Gas piping test at minimum 3 lb PSI for 10 minutes on a 1/10-lb-increment gauge

  11. 11

    Electric Service

    Service entrance and panel verification

  12. 12

    Final

    All work complete per approved plans; Certificate of Occupancy or Temporary Certificate of Occupancy issued by Building Safety

Applies to: Commercial Building Permit

  1. 1

    Foundation

    Before concrete pour; no footing/foundation inspection approved without clearly delineated, accurate property lines and setbacks

  2. 2

    Framing

    Structural framing per stamped engineered plans

  3. 3

    Rough Plumbing/Electrical/Mechanical

    Combined rough-in inspection before wall closure

  4. 4

    Final

    All work complete per approved plans; a newly constructed building may not be occupied until a final inspection and Certificate of Occupancy (or Temporary Certificate of Occupancy) is issued by Building Safety

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footings

    Required before concrete pour for additions

  2. 2

    Framing

    Structural connections to the existing structure

  3. 3

    Rough Plumbing/Electrical/Mechanical

    Combined rough-in inspection where applicable

  4. 4

    Final

    Completed work verified against approved plans

Applies to: Electrical / Plumbing / Mechanical Like-for-Like Replacement Permit

  1. 1

    Rough-In (if applicable)

    Wiring, piping, or ductwork verification before closure, where the scope requires it

  2. 2

    Final

    Replacement verified operational and code-compliant

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect/breaker placement before energizing

  2. 2

    Final

    Charger mounted, connections verified, panel labeled per 2017 NEC as adopted

Applies to: Residential Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before energizing

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, and interconnection point verified

Show Low building permits

Get alerts for Show Low

We'll email you when Show Low's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.