Change of Use / Certificate of Compliance in Show Low, Arizona

Covers a change in the use or occupancy of an existing building or space in the City of Show Low (for example converting a retail suite to a restaurant). The City publishes no application named 'Change of Use' — its complete permit inventory on the City Permits & Applications page is Accessory, Commercial, Fence, Short Term Rental Registration, Plumbing, Sign, Shed, Solar, Additions, Manufactured Home, Water/Sewer Connection and Residential, plus Conditional Use Permits, Temporary Permits, Business Permits and Other Applications (207 Waiver, Right of Way Permit, Special Inspection Certificate). A use change is instead handled through three existing City instruments, each independently grounded in the Show Low Municipal Code: (1) the Commercial Permit Application on its tenant-improvement track for the physical work; (2) a Certificate of Compliance under Municipal Code § 18.20.020, which the Code expressly ties to 'use change' in an existing structure, or a new Certificate of Occupancy under § 18.20.010; and (3) a Conditional Use Permit from Planning & Zoning where the new use is a conditional rather than permitted use in the zoning district.

Verified 2026-08-15 · Source

When you need this permit

  • Show Low Municipal Code § 18.20.020 (Certificate of compliance): 'The certificate of compliance is for existing structures. It may be associated with removing, relocating, renovation, use change, addition and existing structure or housing code. A letter of certification (duplicate certification) may be for other than the original issue.' This is the only place in the Show Low code that names a use change as its own certificate trigger.
  • Show Low Municipal Code § 18.20.010 (Certificate of occupancy): when final inspection indicates a building is in full compliance with applicable codes, a certificate of occupancy shall be issued; no building may be occupied for any reason or purpose until after a final inspection has been performed and the certificate of occupancy issued. A temporary certificate of occupancy may be issued for a specified period where uncompleted items are not a threat to occupant health and safety. Certificates of occupancy are not issued for accessory buildings.
  • Physical work associated with a change of use is permitted on the City's Commercial Permit Application, which requires an Occupancy Classification, Type of Construction and number of stories to be stated on the form, plus a material cost valuation for all commercial jobs.
  • Show Low Municipal Code § 18.15.060: a pre-application meeting is required for all new commercial construction and substantial commercial remodels or additions; a commercial tenant improvement submittal requires four (4) copies of plans and specifications (versus six (6) for new commercial).
  • Show Low Municipal Code § 18.25.080 defines 'new development' to include 'any change in use of an existing building, structure or lot requiring any form of city building permit or approval and which increases the demand for one (1) or more public facilities' — so a change of use can trigger development (impact) fees.
  • Show Low Municipal Code § 18.25.100(B)(2): 'Upon receipt of an application for a building permit, the city shall determine whether it is for a change in use. In such cases, the development fee due shall be based only on the incremental increase in the fee for the additional public facilities needed for the change in use.' Development fees are calculated by the City and paid before the building permit is issued.
  • Where the proposed new use is a conditional use in the zoning district rather than a use permitted by right, a Conditional Use Permit is required from Planning & Zoning; the Planning and Zoning Commission is empowered to grant or deny applications for Conditional Use Permits and to impose conditions upon them, and the process runs application → public notice → public hearing → appeals.
  • A change of use in a commercial building also triggers fire review by the Timber Mesa Fire and Medical District (the City adopts no fire code) — see this file's fire-sprinkler-alarm-permit entry; the District's Commercial Development Plan review fee is expressly for 'new and remodel projects'.
  • Contractor licensing: § 18.15.030 bars issuance of a permit to anyone contracting regulated work who does not hold a valid, unexpired, unrevoked Arizona contractor's license, unless the applicant is the bona fide owner of the premises. Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit FeeSame fee mechanism documented on this file's commercial-building-permit entry; Show Low Municipal Code § 18.25.010 provides only that the common council may establish building permit fee amounts by resolution, so no numeric table is codified
Formulated by the 1997 Uniform Building Code (UBC) valuation-based fee schedule
Plan Review Fee (Commercial), including tenant improvementsCity of Show Low Fee Schedules page (read 2026-08-15): 'For commercial project reviews, a fee of 50% of the building permit fee will be applied to the plan review fee. A $400 deposit for new commercial or a $200 deposit for tenant improvements will be received when the plans are submitted.' The deposit is applied to the plan review fee at issuance.
50% of the Building Permit Fee
Conditional Use Permit filing fee (only where the new use is a conditional use)Stated consistently in two independent City sources read directly: the Conditional Use Permits section of the City Permits & Applications page ('Permits cost $150 to file') and the face of the Conditional Use Permit Application PDF itself ('Filing Fee: $150.00')
$150.00
Development (impact) fees on a change of useShow Low Municipal Code § 18.25.100(B)(2). The Street Facilities (Transportation) Development Fee rates codified at § 18.25.140 are $1,112 per single-family detached housing unit, $874 per all other housing type and $834 per recreational vehicle dwelling unit; § 18.25.090(C)(2)-(3) provides that no development fee is imposed on nonresidential development that adds no square footage, or on any activity that does not increase demand for public facilities, unless demand increases.
Incremental increase only — the difference in fee for the additional public facilities needed for the change in use

Review timeline

Plan reviewShow Low’s published plan-review target
30–40 business days

How long did your Change of Use / Certificate of Compliance permit actually take in Show Low?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In (Plumbing / Framing / Electrical / Mechanical)

    Combined rough-in inspection on tenant-improvement work before wall closure, where the scope requires it

  2. 2

    Fire District Inspection

    Timber Mesa Fire and Medical District conducts final inspections of fire protection systems prior to issuance of a Certificate of Occupancy by the City Building Department; request a minimum of 48 business hours in advance

  3. 3

    Final / Certificate of Occupancy or Certificate of Compliance

    When final inspection indicates full compliance with applicable codes, Building Safety issues the certificate; the space may not be occupied for any purpose before it is issued (§ 18.20.010). For a use change in an existing structure the instrument the Code names is the Certificate of Compliance (§ 18.20.020).

See the full Show Low inspection guide — scheduling & re-inspection fees →

Tips

  • There is no form called 'Change of Use Permit' in Show Low. The instrument the Code actually names for a use change in an existing structure is the Certificate of Compliance (§ 18.20.020) — ask Building Safety for it by that name.
  • A change of use does not automatically mean full development-impact fees: § 18.25.100(B)(2) limits the development fee on a change in use to the INCREMENTAL increase for the additional public facilities needed, and § 18.25.090(C)(3) exempts activity that does not increase demand for public facilities at all.
  • Check the zoning district use table before budgeting. If the new use is permitted by right, no Conditional Use Permit is needed and neither the $150 filing fee nor the public-hearing calendar applies; if it is a conditional use, the Planning and Zoning Commission — not staff — decides, and may attach conditions.
  • A pre-application meeting is mandatory for substantial commercial remodels under § 18.15.060 — call 928-532-4040 before assembling a submittal; commercial tenant improvements need four (4) plan sets and a $200 deposit at submittal.
  • Budget separately for the fire district. Show Low adopts no fire code, so any sprinkler, alarm, hood suppression or commercial remodel fire review is invoiced by Timber Mesa Fire and Medical District and paid directly to the District (see this file's fire-sprinkler-alarm-permit entry).

Frequently asked questions

Show Low requires a change of use / certificate of compliance permit for: Show Low Municipal Code § 18.20.020 (Certificate of compliance): 'The certificate of compliance is for existing structures. It may be associated with removing, relocating, renovation, use change, addition and existing structure or housing code. A letter of certification (duplicate certification) may be for other than the original issue.' This is the only place in the Show Low code that names a use change as its own certificate trigger.; Show Low Municipal Code § 18.20.010 (Certificate of occupancy): when final inspection indicates a building is in full compliance with applicable codes, a certificate of occupancy shall be issued; no building may be occupied for any reason or purpose until after a final inspection has been performed and the certificate of occupancy issued. A temporary certificate of occupancy may be issued for a specified period where uncompleted items are not a threat to occupant health and safety. Certificates of occupancy are not issued for accessory buildings.; Physical work associated with a change of use is permitted on the City's Commercial Permit Application, which requires an Occupancy Classification, Type of Construction and number of stories to be stated on the form, plus a material cost valuation for all commercial jobs.; Show Low Municipal Code § 18.15.060: a pre-application meeting is required for all new commercial construction and substantial commercial remodels or additions; a commercial tenant improvement submittal requires four (4) copies of plans and specifications (versus six (6) for new commercial).; Show Low Municipal Code § 18.25.080 defines 'new development' to include 'any change in use of an existing building, structure or lot requiring any form of city building permit or approval and which increases the demand for one (1) or more public facilities' — so a change of use can trigger development (impact) fees.; Show Low Municipal Code § 18.25.100(B)(2): 'Upon receipt of an application for a building permit, the city shall determine whether it is for a change in use. In such cases, the development fee due shall be based only on the incremental increase in the fee for the additional public facilities needed for the change in use.' Development fees are calculated by the City and paid before the building permit is issued.; Where the proposed new use is a conditional use in the zoning district rather than a use permitted by right, a Conditional Use Permit is required from Planning & Zoning; the Planning and Zoning Commission is empowered to grant or deny applications for Conditional Use Permits and to impose conditions upon them, and the process runs application → public notice → public hearing → appeals.; A change of use in a commercial building also triggers fire review by the Timber Mesa Fire and Medical District (the City adopts no fire code) — see this file's fire-sprinkler-alarm-permit entry; the District's Commercial Development Plan review fee is expressly for 'new and remodel projects'.; Contractor licensing: § 18.15.030 bars issuance of a permit to anyone contracting regulated work who does not hold a valid, unexpired, unrevoked Arizona contractor's license, unless the applicant is the bona fide owner of the premises.. If your project isn't listed, confirm with City of Show Low Building Safety Department at 928-532-4053 before starting work.

In Show Low, the published Building Permit Fee is: Formulated by the 1997 Uniform Building Code (UBC) valuation-based fee schedule. Additional published fees: Plan Review Fee (Commercial), including tenant improvements — 50% of the Building Permit Fee; Conditional Use Permit filing fee (only where the new use is a conditional use) — $150.00; Development (impact) fees on a change of use — Incremental increase only — the difference in fee for the additional public facilities needed for the change in use. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Show Low's published plan-review target for a change of use / certificate of compliance permit is 30–40 business days.

You'll need: Commercial Permit Application (tenant improvement track); Pre-Submittal Checklist; Certificate of Compliance / Certificate of Occupancy. Depending on your project, Show Low may also ask for: Conditional Use Permit Application. See the required-documents checklist on this page for details on each.

Show Low requires 3 inspection(s) for a change of use / certificate of compliance permit, in order: Rough-In (Plumbing / Framing / Electrical / Mechanical), Fire District Inspection, Final / Certificate of Occupancy or Certificate of Compliance. Schedule each through City of Show Low Building Safety Department (928-532-4053).

Apply through City of Show Low Building Safety Department at 180 N. 9th Street, Show Low, AZ 85901. Phone: 928-532-4053, email: jwilhelm@showlowaz.gov. Office hours: Monday - Friday, 9 a.m. - 12 p.m. and 1 p.m. - 4 p.m. (or by appointment), per the City of Show Low Building Safety page. The general Permits & Applications page separately lists City Hall hours as Monday - Friday, 9 a.m. - 4 p.m. (excluding holidays), and appointments are recommended (928-532-4050). The Inspection Line (928-532-4055) requires inspections to be called in 24 hours in advance; as of October 1, 2024, the cutoff for next-day inspections is 3:00 p.m. (previously 5:00 p.m.) — requests after 3:00 p.m. are scheduled two business days out.. Official information: https://www.showlowaz.gov/o/cosl/page/building-safety.

Not under that name. The City's published permit inventory contains no 'Change of Use' application. A use change in an existing structure is handled through the Commercial Permit Application (tenant improvement track) for the physical work plus a Certificate of Compliance under Show Low Municipal Code § 18.20.020, which the Code expressly ties to 'use change' in an existing structure, and a Conditional Use Permit ($150 filing fee) from Planning & Zoning only if the new use is a conditional use in that zoning district.

Only on the incremental increase. Show Low Municipal Code § 18.25.100(B)(2) requires the City to determine whether a building permit application is for a change in use and, if so, to base the development fee 'only on the incremental increase in the fee for the additional public facilities needed for the change in use.' § 18.25.090(C) further provides that no development fee is imposed on nonresidential development that adds no square footage, or on any activity that does not increase the demand for public facilities, unless demand increases.