Taylor building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Taylor, Arizona.
Verified 2026-07-07 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- Taylor Town Hall, 425 Papermill Road (P.O. Box 158), Taylor, AZ 85939
- Phone
- 928-536-7366
- geri@tayloraz.gov
- Office hours
- Town Hall is currently open Monday - Thursday, 7:30 a.m. - 5:30 p.m. (closed Fridays and all major holidays), per the Town's current live website. An older (2014) Town of Taylor 'Homeowner's Guide to Permits' handout lists Development Services Department hours as Monday - Friday, 8:30 a.m. - 5:00 p.m.; the Town Hall-wide 4-day/10-hour schedule on the current tayloraz.gov site is treated as the more current figure for permit-counter purposes. The single Building Official/Zoning Administrator position (reporting directly to the Town Manager as part of the executive leadership team, per the Town's 2024 AZBO job posting) administers both building permits and zoning/planning for the Town.
- Website
- Official site
Inspection sequence
Applies to: Commercial Building Permit / Tenant Improvement
- 1
Foundation
Before concrete pour
- 2
Framing
Structural framing per stamped plans where required
- 3
Rough Plumbing/Electrical/Mechanical
Combined rough-in inspection before wall closure
- 4
Fire Suppression System Inspection
Required where a fire suppression system is installed ($500 fee)
- 5
Final
All work complete per approved plans; Certificate of Occupancy issued
Applies to: Residential Building Permit (New Construction)
- 1
Footing/Foundation
Before concrete pour; verify footing size and reinforcement per Foundation Detail A or B
- 2
Framing
Structural framing, connections, and egress per 2015 IRC and Town design criteria
- 3
Rough Plumbing/Electrical/Mechanical
Combined rough-in inspection prior to wall closure
- 4
Final
All work complete per approved plans; Certificate of Occupancy issued
Applies to: Electrical / Mechanical / Plumbing (Trade) Permit
- 1
Rough-In
Wiring, piping, or ductwork verification before closure
- 2
Service/Meter (electrical only)
Service entrance and panel verification prior to utility connection
- 3
Final
Devices/fixtures/equipment installed and operational, code-compliant
Applies to: Residential Accessory Structure / Detached Structure Permit
- 1
Footing/Foundation
Before concrete pour
- 2
Framing
Structural framing and connections per 2015 IRC/IBC
- 3
Final
Completed structure verified against approved plans and setback/height compliance
Applies to: Electric Vehicle (EV) Charger / Charging Station Permit
- 1
Rough-In
EV charger circuit wiring verified before closure, per the same framework documented in this file's Electrical/Mechanical/Plumbing Permit entry.
- 2
Final
Charger installed and operational, code-compliant; Green Tag issued for utility release.
Applies to: Manufactured Home Installation Permit
- 1
Foundation/Anchoring
Verify masonry block skirting foundation and OMH-approved anchoring system before enclosure
- 2
Final
Porch/deck (32 sq ft minimum per exterior door), exterior finish condition, and garage/carport/addition material match verified before Certificate of Occupancy
Applies to: Residential/Commercial Solar Photovoltaic (PV) System Permit
- 1
Rough Electrical / Interconnection
Wiring, disconnect placement, and conduit verified before closure and utility interconnection.
- 2
Final
Panel/array wiring complete, disconnect labeled, Green Tag issued for utility interconnection.
Final inspection only: Demolition Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Taylor building permits
Get alerts for Taylor
We'll email you when Taylor's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.