Residential Accessory Structure / Detached Structure Permit — Taylor, Arizona · Requirements sheet
Verified 2026-07-07 · Source: https://www.tayloraz.gov/wp-content/uploads/2016/10/Taylor-Detached-Structure-Handout-2016.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Accessory Structure / Detached Structure Permit in Taylor, Arizona
Required for detached accessory structures over 200 square feet in the Town of Taylor (garages, sheds, workshops, barns), and for enclosure of any carport, garage, or patio regardless of size. The Town's own 2016 handout explicitly states there is NO exception for temporary or moveable structures once the 200-sq-ft threshold is crossed.
Verified 2026-07-07 · Source
When you need this permit
- Any detached structure over 200 sq ft, regardless of use, requires a permit — with NO exception for temporary or moveable/portable structures, per the Town's 2016 Residential Accessory Structure Handout
- Any change, addition, or deletion of a room or building requires a permit
- Any enclosure of a carport, garage, or patio requires a permit
- To erect, install, enlarge, alter, repair, remove, convert, or replace any electrical, gas, mechanical, or plumbing system requires a permit
- Applicant must first check with Planning & Zoning for lot coverage, setback requirements, and maximum building height for the applicable zoning district; HOA/CC&R compliance is the property owner's own responsibility
- Two (2) site plans required showing project dimensions and relationship to all existing buildings, utilities, septic systems, easements, and other structures, plus distances to property lines, drawn to scale
- Two (2) copies each of a floor plan and a building/foundation section & detail plan required; the Town's 'Easy Plan' fill-in template may be used (maximum 10-ft wall height)
- One-story detached accessory structures of 200 sq ft or less are exempt from the permit requirement (per the older Homeowner's Guide to Permits exemption list, still consistent with the 200-sq-ft threshold in the newer 2016 handout)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation
Before concrete pour
- 2
Framing
Structural framing and connections per 2015 IRC/IBC
- 3
Final
Completed structure verified against approved plans and setback/height compliance
See the full Taylor inspection guide — scheduling & re-inspection fees →
Tips
- The Town's own Fee Schedule does not publish a separate/expedited review timeline distinct from the general building-permit process; this file applies the same Town-published 'up to two weeks' (10-business-day) figure from the Permits page, since accessory structures over 200 sq ft go through the same Building/Zoning Department plan-review process as other building permits.
- Portable sheds, containers, and carports carry a flat $25 fee under the current Fee Schedule regardless of size — but per the 2016 handout, this does NOT exempt them from needing a permit once they exceed 200 sq ft, and even under 200 sq ft, any electrical/plumbing/direct-attachment scope still requires a permit.
- Always confirm lot coverage, setback, and height limits with Planning & Zoning BEFORE submitting a site plan — the Town's guidance explicitly frames this as the mandatory first step.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Taylor
Compare residential accessory structure / detached structure permit fees across Arizona →
Look up this fee in a different city →