Change of Occupancy Permit in Taylor, Arizona
The Town of Taylor issues a Change of Occupancy Permit, which its own handout describes as a building permit. Per the Town's Change of Occupancy handout: 'Whenever the use of any part of a building changes from one occupancy classification to another as classified in the International Building Code, then a Change of Occupancy Permit is required', citing IBC Chapter 3 and Section 110.1. The handout gives the worked examples of using a store building (an M occupancy) as a day care center (an E-3 occupancy), or enlarging restaurant seating from fewer than 50 (a B occupancy) to 50 or more (an A-3 occupancy). When occupancy changes, the Building Code requires the building to meet all current code requirements for the new use. The handout is explicit that a change of occupancy 'applies to the use of a building only, and should not be confused with any process required by the Zoning Code to change the use of a property.' A separate, lighter path exists for a new tenant taking over a space with the same occupancy classification and no work requiring a tenant improvement permit.
Reviewed 2026-07-07 · Source
When you need this permit
- First check with the planning department and the fire department to find out whether the change is allowable and whether the building will meet fire department requirements — the Town's handout warns there is no use pursuing a permit if the project would not be allowed anyway
- A Change of Occupancy Permit is a building permit. Three sets of building plans are required to process it; plans are turned in and plan check fees paid at the Development Services Center, where a case number is assigned to track the permit
- Plans must be neatly drawn and to scale and must show existing conditions as well as proposed changes (IBC Section 106)
- Site plan: size of the building and its location relative to property lines and streets, relative elevation dimensions showing grade changes, other structures on the property, paved driveways and parking, landscaping, and a north arrow
- Floor plan for each level: overall building size and evidence of compliance with IBC Chapter 5 for allowable height and area; proposed use and dimensions of each room; window sizes and how windows open; size of exit doors, direction of door swing, door hardware, steps at doors and glass panels in doors; stairways and landings inside and outside; restroom sizes and fixture quantities complying with the proposed use and ADA; any electrical changes; mechanical unit sizes and outside air calculations
- A change of occupancy resulting in any increase in demand for fossil fuel or electrical energy must comply with the International Energy Conservation Code
- Where electrical, plumbing and/or mechanical changes are deemed significant or deficient, a specific plan sheet may be required showing how code compliance is achieved
- Simple tenant change (new tenant, same occupancy classification, no changes requiring a tenant improvement permit): a sketch of the floor plan showing an accessible counter 34 to 38 inches high, 36 inches long and 12 inches wide, a water cooler and a fire extinguisher, plus a completed Building Permit Application
- Building Department inspections require a minimum of 24 hours' notice and are scheduled by calling 928-536-7366
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Building Department inspection of the place of business
For a simple tenant change the Town's handout states the $25 fee 'includes Building Department inspection of your place of business'. Inspections are scheduled by calling 928-536-7366 with a minimum of 24 hours' notice.
- 2
Re-inspection
$75.00 per the Town Fee Schedule effective April 5, 2025 (Building, Other Fees).
See the full Taylor inspection guide — scheduling & re-inspection fees →
Tips
- Two different paths, two very different costs. A true change of occupancy classification is a full building permit with three plan sets and valuation-based fees; a new tenant moving into a space with the SAME occupancy classification and no tenant improvement work is a $25 simple tenant change with a floor plan sketch.
- Call planning and fire before you draw anything. The Town's own handout leads with this: confirm the change is allowable and that the building will meet fire department requirements before pursuing the permit.
- Changing occupancy means meeting current code for the new use, not the code the building was built to. The handout's example: an old house (R-3) used as an office building must comply with the requirements for a new office building.
- Zoning is a separate question. The handout warns that a change of occupancy 'applies to the use of a building only' and should not be confused with any Zoning Code process to change the use of a property — building occupancy classifications address impact on occupants, zoning use classifications address impact on surrounding properties.
- Watch the ripple effects. The handout notes a change of occupancy can change parking requirements and site traffic patterns, which can change impervious surface area, which can change the site's grading and drainage requirements.
- Restaurant seating is a classic trigger: going from under 50 seats (Group B) to 50 or more (Group A-3) is a change of occupancy even with no other work.
- An increase in fossil fuel or electrical energy demand pulls the International Energy Conservation Code in. Taylor's adopted IECC is the 2009 edition, one family behind its otherwise-2015 ICC set.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Taylor
Change of Occupancy Permit in other cities
Compare change of occupancy permit fees across Arizona →
Look up this fee in a different city →