Demolition Permit in Taylor, Arizona

Required to demolish, move, or change the occupancy of a building or structure in the Town of Taylor, per the Town's Residential Accessory Structure Handout and Building Permit Application (which lists 'DEMOLITION' as a distinct Permit Type checkbox).

Verified 2026-07-07 · Source

When you need this permit

  • Permit required to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure
  • Building Permit Application used, with 'DEMOLITION' checked under Permit Type
  • Site plan showing the structure to be demolished and its relationship to remaining structures/utilities/easements is standard Building/Zoning Department submittal practice
  • All utility disconnections must be coordinated prior to demolition (standard practice; confirm specifics directly with the Building/Zoning Department at 928-536-7366, as no Taylor-specific utility-disconnect checklist was found published separately from the general permit application)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition PermitCONFIRMED GAP: the Town of Taylor Fee Schedule, effective April 5, 2025, itemizes Building fees for Homes, Garage, Portable Sheds/Containers/Carports, Fences, Plan Review, Commercial/Industrial Buildings-Additions-Repairs, and Other Fees (Electrical-Mechanical-Plumbing, Fire Suppression, Green Tag, Re-Inspection, Solar PV) — no separate 'Demolition' fee line exists anywhere in the current schedule despite Demolition being a distinct checkbox on the Building Permit Application. Chase trail: checked the live 2025 Fee Schedule PDF (tayloraz.gov/wp-content/uploads/2025/04/2025-Fee-Schedule.pdf) in full; checked the Town of Taylor Municipal Code § 15.05 (codepublishing.com) for a demolition-specific fee cross-reference — none found; the Building Permit Application itself (both the 2014 and 2016-revised fillable versions) has no fee schedule printed on it. Given the zero-tolerance no-fabrication policy, this file does not assert a specific demolition fee; contact the Building/Zoning Department directly at 928-536-7366 to confirm the exact charge, which most likely defaults to the general valuation-based Building Permit Fee structure (75% modifier) applied to demolition work, but this has not been independently confirmed in writing by the Town.
Not separately itemized in the Town's current Fee Schedule

Review timeline

Plan reviewTaylor’s published plan-review target
10–10 business days

How long did your Demolition Permit permit actually take in Taylor?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Site verified clear of debris and utilities properly terminated

See the full Taylor inspection guide — scheduling & re-inspection fees →

Tips

  • CONFIRMED GAP (fee only): Demolition is a distinct, named permit type on the Town's own Building Permit Application, but no demolition-specific fee line appears anywhere in the Town's current (April 2025) Fee Schedule after an exhaustive check of the PDF, the Municipal Code § 15.05, and both versions of the permit application form itself. This is treated as a genuine confirmed gap rather than an assumption — call 928-536-7366 to obtain the exact current fee.
  • The review timeline is not separately published for demolition; the Town's general 'up to two weeks' plan-review figure (Permits page) is applied here as the best-available governing timeframe, since demolition uses the same Building Permit Application and Building/Zoning Department review process as other permit types.

Frequently asked questions

Taylor requires a demolition permit for: Permit required to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure; Building Permit Application used, with 'DEMOLITION' checked under Permit Type; Site plan showing the structure to be demolished and its relationship to remaining structures/utilities/easements is standard Building/Zoning Department submittal practice; All utility disconnections must be coordinated prior to demolition (standard practice; confirm specifics directly with the Building/Zoning Department at 928-536-7366, as no Taylor-specific utility-disconnect checklist was found published separately from the general permit application). If your project isn't listed, confirm with Town of Taylor Building / Zoning Department (Development Services Department) at 928-536-7366 before starting work.

The Town of Taylor's current Fee Schedule (effective April 5, 2025) does not publish a separate demolition fee line, despite Demolition being a distinct permit-type option on the Building Permit Application. Contact the Building/Zoning Department at 928-536-7366 to confirm the current charge for your specific project.

Taylor's published plan-review target for a demolition permit is 10–10 business days.

You'll need: Building Permit Application; Site Plan. See the required-documents checklist on this page for details on each.

Taylor requires 1 inspection(s) for a demolition permit, in order: Final. Schedule each through Town of Taylor Building / Zoning Department (Development Services Department) (928-536-7366).

Apply through Town of Taylor Building / Zoning Department (Development Services Department) at Taylor Town Hall, 425 Papermill Road (P.O. Box 158), Taylor, AZ 85939. Phone: 928-536-7366, email: geri@tayloraz.gov. Office hours: Town Hall is currently open Monday - Thursday, 7:30 a.m. - 5:30 p.m. (closed Fridays and all major holidays), per the Town's current live website. An older (2014) Town of Taylor 'Homeowner's Guide to Permits' handout lists Development Services Department hours as Monday - Friday, 8:30 a.m. - 5:00 p.m.; the Town Hall-wide 4-day/10-hour schedule on the current tayloraz.gov site is treated as the more current figure for permit-counter purposes. The single Building Official/Zoning Administrator position (reporting directly to the Town Manager as part of the executive leadership team, per the Town's 2024 AZBO job posting) administers both building permits and zoning/planning for the Town.. Official information: https://www.tayloraz.gov/departments/building/.

Taylor, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/town authority under state enabling statutes (A.R.S. Title 9). The Town of Taylor independently adopts and administers its own construction codes through its own Building/Zoning Department (Development Services Department) at Taylor Town Hall; it does not defer building permitting to Navajo County. Verified independence: Taylor maintains its own Municipal Code Chapter 15.05 (Building and Construction Codes), its own Fee Schedule (effective April 5, 2025), its own Building Permit Application, and a dedicated Building Official/Zoning Administrator position reporting to the Town Manager. The Town shares only Fire/EMS (Taylor-Snowflake Fire) and Police (Snowflake-Taylor Police Department) with the adjacent Town of Snowflake — building/zoning permitting is NOT a shared program between the two towns. Source: Town of Taylor Municipal Code § 15.05 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html); tayloraz.gov Building Department and Permits pages; Town of Taylor Fee Schedule effective 4/5/2025; Town of Taylor Building Official/Zoning Administrator job posting (AZBO, 2024).; 2015 International Building Code (IBC), published by the International Code Council, adopted by reference with Appendices C and I, as amended by the Town of Taylor (Taylor Municipal Code § 15.05). Source: Town of Taylor Municipal Code § 15.05.040 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html).; 2015 International Residential Code (IRC) for One- and Two-Family Dwellings, adopted by reference with Appendices A, B, H, M, N, R, and S, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Plumbing Code (IPC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Mechanical Code (IMC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fuel Gas Code (IFGC), adopted by reference with Appendices A, B, and C, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2009 International Energy Conservation Code (IECC) — notably one code family behind the Town's otherwise-2015 ICC set. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Existing Building Code (IEBC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fire Code (IFC), adopted by reference as the Town's uniform fire code, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2014 National Electrical Code (NEC/NFPA 70), published by the National Fire Protection Association, adopted by reference, as amended by the Town of Taylor — one edition behind the otherwise-2015 ICC family set (the same one-cycle-behind pattern seen in other Navajo County towns, e.g. Show Low's 2017 NEC alongside 2018 ICC codes). Source: Town of Taylor Municipal Code § 15.05.; Residential fire sprinklers: IRC Section R313 is deleted in its entirety and replaced with a cross-reference directing compliance to Arizona Revised Statute § 9-807 (the state statute governing municipal authority to require or not require residential fire sprinklers) rather than the model code's own prescriptive sprinkler trigger. Source: Town of Taylor Municipal Code § 15.05 (IRC Chapter 3 amendment).; Manufactured homes, mobile homes, and factory-built buildings: construction/installation standards are regulated directly by the State of Arizona (Arizona Department of Housing, Office of Manufactured Housing (OMH); A.R.S. § 41-4001 et seq.). The Town of Taylor's own Building/Zoning Department governs on-site placement, foundation/tie-down, and zoning compliance, and imposes its own additional zoning-based requirements (see localAmendments). As of the Town's published guidance, Arizona no longer allows Owner-Builder permits for manufactured home installation — a licensed installer must apply for the permit. Source: Town of Taylor 'Manufactured Homes Requirements in Taylor AZ' handout (Taylor Building/Zoning Department); A.R.S. § 41-4001 et seq.. Local amendments apply — see the Taylor overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.