Residential Building Permit (New Construction) in Taylor, Arizona

Required for new single-family and two-family dwelling construction in the Town of Taylor. Reviewed against the 2015 IRC/IBC and Town of Taylor amendments (Taylor Municipal Code § 15.05). Applications are submitted at the Building/Zoning Department, Taylor Town Hall.

Verified 2026-07-07 · Source

When you need this permit

  • Building permit required for new single-family and two-family dwelling construction within Taylor town limits
  • Plans must comply with the 2015 IRC and Town of Taylor Climatic and Geographic Design Criteria (115 mph wind, Exposure C; Seismic Design Category B, D for concrete footings; 20 lb/sf ground snow load; 18-inch frost depth; 15°F winter design temperature)
  • Two (2) sets of plans/drawings required for a building project, showing a plot plan with property lines, project dimensions, materials type/size, structural details (footings, post-to-beam connections, header/beam sizes), building elevations (front/rear/side), floor plan, and floor/roof framing plans
  • IRC Section R313 (residential fire sprinklers) is deleted and replaced with a cross-reference to A.R.S. § 9-807
  • Contractor must hold a valid Arizona ROC license, or the applicant must be the bona fide property owner (owner-builder) Owner-builderContractor
  • Building Permit Application submitted at the Building/Zoning Department, Taylor Town Hall, 425 Papermill Rd.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (Homes) — Building Code Valuation Regional ModifierTown of Taylor Fee Schedule, effective April 5, 2025 (Building > Residential Permits > Homes)
75% of standard ICC/UBC valuation-based fee table
Plan Review, under 1,500 sq ftTown of Taylor Fee Schedule, effective April 5, 2025
$100.00
Plan Review, 1,500 sq ft and overTown of Taylor Fee Schedule, effective April 5, 2025
$200.00
Re-InspectionTown of Taylor Fee Schedule, effective April 5, 2025
$75.00
Green TagTown of Taylor Fee Schedule, effective April 5, 2025
$25.00

Review timeline

Plan reviewTaylor’s published plan-review target
10–10 business days

How long did your Residential Building Permit (New Construction) permit actually take in Taylor?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    Before concrete pour; verify footing size and reinforcement per Foundation Detail A or B

  2. 2

    Framing

    Structural framing, connections, and egress per 2015 IRC and Town design criteria

  3. 3

    Rough Plumbing/Electrical/Mechanical

    Combined rough-in inspection prior to wall closure

  4. 4

    Final

    All work complete per approved plans; Certificate of Occupancy issued

See the full Taylor inspection guide — scheduling & re-inspection fees →

Tips

  • The Town's own Permits page states: 'A plan review generally takes up to two weeks for one- and two-family dwellings,' noting time frames can change depending on project complexity and submittal completeness. This file converts that published 'up to two weeks' figure to a 10-business-day (2 calendar weeks) review-timeline estimate — this is the Town's own stated figure, not an inferred one, and is treated as the governing published timeframe under this jurisdiction's zero-tolerance verified bar (no separate, more granular A.R.S. § 9-835-style Standard/Non-Standard split of the kind published by Show Low or Buckeye was found for Taylor specifically).
  • Building permit fees for homes use a 75% 'Building Code Valuation Regional Modifier' against the standard ICC/UBC valuation fee table — Taylor's own Fee Schedule states this modifier explicitly rather than a full 100% valuation charge.
  • Two sets of plans are required (not more), and the Town provides its own fill-in-the-blank 'Easy Plan' templates with pre-computed rafter/ceiling-joist span and header tables for simple buildings up to 10-ft wall height.
  • IRC Section R313 (automatic residential fire sprinklers) is deleted outright and replaced with a cross-reference to A.R.S. § 9-807, meaning Taylor does not impose the model code's own prescriptive sprinkler mandate independently of state law.

Frequently asked questions

Taylor requires a residential building permit (new construction) for: Building permit required for new single-family and two-family dwelling construction within Taylor town limits; Plans must comply with the 2015 IRC and Town of Taylor Climatic and Geographic Design Criteria (115 mph wind, Exposure C; Seismic Design Category B, D for concrete footings; 20 lb/sf ground snow load; 18-inch frost depth; 15°F winter design temperature); Two (2) sets of plans/drawings required for a building project, showing a plot plan with property lines, project dimensions, materials type/size, structural details (footings, post-to-beam connections, header/beam sizes), building elevations (front/rear/side), floor plan, and floor/roof framing plans; IRC Section R313 (residential fire sprinklers) is deleted and replaced with a cross-reference to A.R.S. § 9-807; Contractor must hold a valid Arizona ROC license, or the applicant must be the bona fide property owner (owner-builder); Building Permit Application submitted at the Building/Zoning Department, Taylor Town Hall, 425 Papermill Rd.. If your project isn't listed, confirm with Town of Taylor Building / Zoning Department (Development Services Department) at 928-536-7366 before starting work.

In Taylor, the published Building Permit Fee (Homes) — Building Code Valuation Regional Modifier is: 75% of standard ICC/UBC valuation-based fee table. Additional published fees: Plan Review, under 1,500 sq ft — $100.00; Plan Review, 1,500 sq ft and over — $200.00; Re-Inspection — $75.00; Green Tag — $25.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the Town of Taylor's own Permits page, plan review for one- and two-family dwellings generally takes up to two weeks, though this can extend depending on project complexity and submittal completeness.

You'll need: Building Permit Application; Site/Plot Plan; Floor Plan and Building/Foundation Section & Detail Plan. See the required-documents checklist on this page for details on each.

Taylor requires 4 inspection(s) for a residential building permit (new construction), in order: Footing/Foundation, Framing, Rough Plumbing/Electrical/Mechanical, Final. Schedule each through Town of Taylor Building / Zoning Department (Development Services Department) (928-536-7366).

Apply through Town of Taylor Building / Zoning Department (Development Services Department) at Taylor Town Hall, 425 Papermill Road (P.O. Box 158), Taylor, AZ 85939. Phone: 928-536-7366, email: geri@tayloraz.gov. Office hours: Town Hall is currently open Monday - Thursday, 7:30 a.m. - 5:30 p.m. (closed Fridays and all major holidays), per the Town's current live website. An older (2014) Town of Taylor 'Homeowner's Guide to Permits' handout lists Development Services Department hours as Monday - Friday, 8:30 a.m. - 5:00 p.m.; the Town Hall-wide 4-day/10-hour schedule on the current tayloraz.gov site is treated as the more current figure for permit-counter purposes. The single Building Official/Zoning Administrator position (reporting directly to the Town Manager as part of the executive leadership team, per the Town's 2024 AZBO job posting) administers both building permits and zoning/planning for the Town.. Official information: https://www.tayloraz.gov/departments/building/.

Taylor, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/town authority under state enabling statutes (A.R.S. Title 9). The Town of Taylor independently adopts and administers its own construction codes through its own Building/Zoning Department (Development Services Department) at Taylor Town Hall; it does not defer building permitting to Navajo County. Verified independence: Taylor maintains its own Municipal Code Chapter 15.05 (Building and Construction Codes), its own Fee Schedule (effective April 5, 2025), its own Building Permit Application, and a dedicated Building Official/Zoning Administrator position reporting to the Town Manager. The Town shares only Fire/EMS (Taylor-Snowflake Fire) and Police (Snowflake-Taylor Police Department) with the adjacent Town of Snowflake — building/zoning permitting is NOT a shared program between the two towns. Source: Town of Taylor Municipal Code § 15.05 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html); tayloraz.gov Building Department and Permits pages; Town of Taylor Fee Schedule effective 4/5/2025; Town of Taylor Building Official/Zoning Administrator job posting (AZBO, 2024).; 2015 International Building Code (IBC), published by the International Code Council, adopted by reference with Appendices C and I, as amended by the Town of Taylor (Taylor Municipal Code § 15.05). Source: Town of Taylor Municipal Code § 15.05.040 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html).; 2015 International Residential Code (IRC) for One- and Two-Family Dwellings, adopted by reference with Appendices A, B, H, M, N, R, and S, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Plumbing Code (IPC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Mechanical Code (IMC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fuel Gas Code (IFGC), adopted by reference with Appendices A, B, and C, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2009 International Energy Conservation Code (IECC) — notably one code family behind the Town's otherwise-2015 ICC set. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Existing Building Code (IEBC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fire Code (IFC), adopted by reference as the Town's uniform fire code, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2014 National Electrical Code (NEC/NFPA 70), published by the National Fire Protection Association, adopted by reference, as amended by the Town of Taylor — one edition behind the otherwise-2015 ICC family set (the same one-cycle-behind pattern seen in other Navajo County towns, e.g. Show Low's 2017 NEC alongside 2018 ICC codes). Source: Town of Taylor Municipal Code § 15.05.; Residential fire sprinklers: IRC Section R313 is deleted in its entirety and replaced with a cross-reference directing compliance to Arizona Revised Statute § 9-807 (the state statute governing municipal authority to require or not require residential fire sprinklers) rather than the model code's own prescriptive sprinkler trigger. Source: Town of Taylor Municipal Code § 15.05 (IRC Chapter 3 amendment).; Manufactured homes, mobile homes, and factory-built buildings: construction/installation standards are regulated directly by the State of Arizona (Arizona Department of Housing, Office of Manufactured Housing (OMH); A.R.S. § 41-4001 et seq.). The Town of Taylor's own Building/Zoning Department governs on-site placement, foundation/tie-down, and zoning compliance, and imposes its own additional zoning-based requirements (see localAmendments). As of the Town's published guidance, Arizona no longer allows Owner-Builder permits for manufactured home installation — a licensed installer must apply for the permit. Source: Town of Taylor 'Manufactured Homes Requirements in Taylor AZ' handout (Taylor Building/Zoning Department); A.R.S. § 41-4001 et seq.. Local amendments apply — see the Taylor overview page for the full list.

The 2015 IRC and 2015 IBC (for non-residential portions), the 2009 IECC, and the 2014 NEC, all as adopted and amended by the Town of Taylor (Taylor Municipal Code § 15.05), apply to new residential construction.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.