Electric Vehicle (EV) Charger / Charging Station Permit in Taylor, Arizona

The Town of Taylor's current Fee Schedule (effective April 5, 2025) has no dedicated EV charger/EVSE line item, unlike Solar PV Systems, which does get its own $200 flat fee. Installing a Level 2 (or greater) EV charging station is electrical work, billed under the Town's general $50.00 combined Electrical-Mechanical-Plumbing trade-permit fee documented in this file's Electrical/Mechanical/Plumbing Permit entry, using the Town's standard Building Permit Application.

Verified 2026-07-20 · Source

When you need this permit

  • Building Permit Application submitted to the Town of Taylor Building/Zoning Department, checking 'ELECTRICAL' under Permit Type, per the same process documented in this file's Electrical/Mechanical/Plumbing Permit entry
  • Governed by the 2014 NEC as adopted and amended by the Town — see codesAdopted — which includes Article 625 (Electric Vehicle Charging System) requirements
  • Contractor must hold a valid Arizona ROC license, or a homeowner who owns and occupies the property may self-perform electrical work on their own residence (not intended for sale/lease/rent), per the same owner-builder allowance documented in this file's Electrical/Mechanical/Plumbing Permit entry Owner-builderContractor
  • No Town of Taylor-specific EV charger application, checklist, or fee line distinct from the general Electrical-Mechanical-Plumbing trade-permit fee was found published as of 2026-07-20 — a genuine documentation gap, not an inferred figure

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical-Mechanical-Plumbing (combined trade permit category)Town of Taylor Fee Schedule, effective April 5, 2025 (Building > Other Fees) — same flat fee documented in this file's Electrical/Mechanical/Plumbing Permit entry; no EV-charger-specific or EVSE-specific line item is published separately.
$50.00
Green TagTown of Taylor Fee Schedule, effective April 5, 2025 — temporary power/final utility release tag, applicable to a new circuit the same as other electrical work.
$25.00
Re-InspectionTown of Taylor Fee Schedule, effective April 5, 2025.
$75.00

Review timeline

Plan reviewTaylor’s published plan-review target
10–10 business days

How long did your Electric Vehicle (EV) Charger / Charging Station Permit permit actually take in Taylor?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    EV charger circuit wiring verified before closure, per the same framework documented in this file's Electrical/Mechanical/Plumbing Permit entry.

  2. 2

    Final

    Charger installed and operational, code-compliant; Green Tag issued for utility release.

See the full Taylor inspection guide — scheduling & re-inspection fees →

Tips

  • Unlike Solar PV Systems, which has its own dedicated $200 fee line, EV chargers in Taylor are billed under the general $50 combined Electrical-Mechanical-Plumbing trade-permit fee — confirmed directly against the Town's current (April 2025) Fee Schedule, which lists no separate EV/EVSE line item.
  • A homeowner who owns and occupies the residence (not intended for sale/lease/rent) may self-perform the EV charger circuit installation and pull the permit directly, per the same owner-builder allowance documented in this file's Electrical/Mechanical/Plumbing Permit entry. Owner-builder

Frequently asked questions

Taylor requires an electric vehicle (ev) charger / charging station permit for: Building Permit Application submitted to the Town of Taylor Building/Zoning Department, checking 'ELECTRICAL' under Permit Type, per the same process documented in this file's Electrical/Mechanical/Plumbing Permit entry; Governed by the 2014 NEC as adopted and amended by the Town — see codesAdopted — which includes Article 625 (Electric Vehicle Charging System) requirements; Contractor must hold a valid Arizona ROC license, or a homeowner who owns and occupies the property may self-perform electrical work on their own residence (not intended for sale/lease/rent), per the same owner-builder allowance documented in this file's Electrical/Mechanical/Plumbing Permit entry; No Town of Taylor-specific EV charger application, checklist, or fee line distinct from the general Electrical-Mechanical-Plumbing trade-permit fee was found published as of 2026-07-20 — a genuine documentation gap, not an inferred figure. If your project isn't listed, confirm with Town of Taylor Building / Zoning Department (Development Services Department) at 928-536-7366 before starting work.

There is no dedicated EV charger fee line. It is billed as electrical work under the Town's general $50.00 combined Electrical-Mechanical-Plumbing trade-permit fee, per the Town of Taylor Fee Schedule effective April 5, 2025.

Taylor's published plan-review target for an electric vehicle (ev) charger / charging station permit is 10–10 business days.

You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

Taylor requires 2 inspection(s) for an electric vehicle (ev) charger / charging station permit, in order: Rough-In, Final. Schedule each through Town of Taylor Building / Zoning Department (Development Services Department) (928-536-7366).

Apply through Town of Taylor Building / Zoning Department (Development Services Department) at Taylor Town Hall, 425 Papermill Road (P.O. Box 158), Taylor, AZ 85939. Phone: 928-536-7366, email: geri@tayloraz.gov. Office hours: Town Hall is currently open Monday - Thursday, 7:30 a.m. - 5:30 p.m. (closed Fridays and all major holidays), per the Town's current live website. An older (2014) Town of Taylor 'Homeowner's Guide to Permits' handout lists Development Services Department hours as Monday - Friday, 8:30 a.m. - 5:00 p.m.; the Town Hall-wide 4-day/10-hour schedule on the current tayloraz.gov site is treated as the more current figure for permit-counter purposes. The single Building Official/Zoning Administrator position (reporting directly to the Town Manager as part of the executive leadership team, per the Town's 2024 AZBO job posting) administers both building permits and zoning/planning for the Town.. Official information: https://www.tayloraz.gov/departments/building/.

Taylor, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/town authority under state enabling statutes (A.R.S. Title 9). The Town of Taylor independently adopts and administers its own construction codes through its own Building/Zoning Department (Development Services Department) at Taylor Town Hall; it does not defer building permitting to Navajo County. Verified independence: Taylor maintains its own Municipal Code Chapter 15.05 (Building and Construction Codes), its own Fee Schedule (effective April 5, 2025), its own Building Permit Application, and a dedicated Building Official/Zoning Administrator position reporting to the Town Manager. The Town shares only Fire/EMS (Taylor-Snowflake Fire) and Police (Snowflake-Taylor Police Department) with the adjacent Town of Snowflake — building/zoning permitting is NOT a shared program between the two towns. Source: Town of Taylor Municipal Code § 15.05 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html); tayloraz.gov Building Department and Permits pages; Town of Taylor Fee Schedule effective 4/5/2025; Town of Taylor Building Official/Zoning Administrator job posting (AZBO, 2024).; 2015 International Building Code (IBC), published by the International Code Council, adopted by reference with Appendices C and I, as amended by the Town of Taylor (Taylor Municipal Code § 15.05). Source: Town of Taylor Municipal Code § 15.05.040 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html).; 2015 International Residential Code (IRC) for One- and Two-Family Dwellings, adopted by reference with Appendices A, B, H, M, N, R, and S, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Plumbing Code (IPC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Mechanical Code (IMC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fuel Gas Code (IFGC), adopted by reference with Appendices A, B, and C, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2009 International Energy Conservation Code (IECC) — notably one code family behind the Town's otherwise-2015 ICC set. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Existing Building Code (IEBC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fire Code (IFC), adopted by reference as the Town's uniform fire code, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2014 National Electrical Code (NEC/NFPA 70), published by the National Fire Protection Association, adopted by reference, as amended by the Town of Taylor — one edition behind the otherwise-2015 ICC family set (the same one-cycle-behind pattern seen in other Navajo County towns, e.g. Show Low's 2017 NEC alongside 2018 ICC codes). Source: Town of Taylor Municipal Code § 15.05.; Residential fire sprinklers: IRC Section R313 is deleted in its entirety and replaced with a cross-reference directing compliance to Arizona Revised Statute § 9-807 (the state statute governing municipal authority to require or not require residential fire sprinklers) rather than the model code's own prescriptive sprinkler trigger. Source: Town of Taylor Municipal Code § 15.05 (IRC Chapter 3 amendment).; Manufactured homes, mobile homes, and factory-built buildings: construction/installation standards are regulated directly by the State of Arizona (Arizona Department of Housing, Office of Manufactured Housing (OMH); A.R.S. § 41-4001 et seq.). The Town of Taylor's own Building/Zoning Department governs on-site placement, foundation/tie-down, and zoning compliance, and imposes its own additional zoning-based requirements (see localAmendments). As of the Town's published guidance, Arizona no longer allows Owner-Builder permits for manufactured home installation — a licensed installer must apply for the permit. Source: Town of Taylor 'Manufactured Homes Requirements in Taylor AZ' handout (Taylor Building/Zoning Department); A.R.S. § 41-4001 et seq.. Local amendments apply — see the Taylor overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.