Commercial Building Permit / Tenant Improvement in Taylor, Arizona

Required for new commercial/industrial construction, additions, repairs, and tenant improvements in the Town of Taylor, reviewed against the 2015 IBC as adopted and amended by the Town. The Building Permit Application supports 'TENNENT IMPROVEMENT' and 'CHANGE OF USE' as distinct Class/Permit selections, and the Town publishes a dedicated Commercial Plan Submittal Requirements handout and Commercial Kitchen Hood Worksheet.

Verified 2026-07-07 · Source

When you need this permit

  • Building permit required for new commercial/industrial buildings, additions, repairs, and tenant improvements
  • New commercial project plan submittals must include a code summary on the plan, per the Building Permit Application instructions
  • Governed by the 2015 IBC and Town of Taylor amendments; commercial kitchen work uses the Town's published Commercial Kitchen Hood Worksheet
  • Change of Occupancy / Change of Tenant uses dedicated Town forms distinct from the general Building Permit Application
  • Commercial Plan Submittal Requirements (Town-published checklist) governs required plan content for commercial projects

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Buildings, Additions or Repairs — Building Code Valuation Regional ModifierTown of Taylor Fee Schedule, effective April 5, 2025 (Commercial/Industrial Permits)
75%
Plan Review (Commercial/Industrial)Town of Taylor Fee Schedule, effective April 5, 2025
50% of the building permit fee
Fire Suppression System InspectionTown of Taylor Fee Schedule, effective April 5, 2025 (Building > Other Fees)
$500.00

Review timeline

Plan reviewTaylor’s published plan-review target
10–10 business days

How long did your Commercial Building Permit / Tenant Improvement permit actually take in Taylor?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing per stamped plans where required

  3. 3

    Rough Plumbing/Electrical/Mechanical

    Combined rough-in inspection before wall closure

  4. 4

    Fire Suppression System Inspection

    Required where a fire suppression system is installed ($500 fee)

  5. 5

    Final

    All work complete per approved plans; Certificate of Occupancy issued

See the full Taylor inspection guide — scheduling & re-inspection fees →

Tips

  • No dedicated pre-submittal meeting requirement (of the kind mandatory in larger Navajo County towns like Show Low) was found published by Taylor for commercial projects, but the Town's own Commercial Plan Submittal Requirements checklist should be obtained directly from the Building Department (928-536-7366) before submitting, since it was referenced but not independently retrievable as a standalone document in this research pass.
  • The Town's own Permits page 'up to two weeks' timeline is stated in the context of 'one- and two-family dwellings' specifically; no separate, longer commercial-specific review timeframe was found published — this file applies the same 10-business-day figure to commercial permits as the best-available governing timeframe, but larger/more complex commercial projects may reasonably take longer in practice per the Town's own caveat that timeframes 'can change, depending on the complexity of the project.'
  • Fire Suppression System Inspection ($500) is billed as a separate line item from the general building permit and plan review fees.

Frequently asked questions

Taylor requires a commercial building permit / tenant improvement for: Building permit required for new commercial/industrial buildings, additions, repairs, and tenant improvements; New commercial project plan submittals must include a code summary on the plan, per the Building Permit Application instructions; Governed by the 2015 IBC and Town of Taylor amendments; commercial kitchen work uses the Town's published Commercial Kitchen Hood Worksheet; Change of Occupancy / Change of Tenant uses dedicated Town forms distinct from the general Building Permit Application; Commercial Plan Submittal Requirements (Town-published checklist) governs required plan content for commercial projects. If your project isn't listed, confirm with Town of Taylor Building / Zoning Department (Development Services Department) at 928-536-7366 before starting work.

50% of the building permit fee, per the Town of Taylor Fee Schedule effective April 5, 2025. The building permit fee itself uses a 75% valuation regional modifier against the standard ICC/UBC fee table.

Taylor's published plan-review target for a commercial building permit / tenant improvement is 10–10 business days.

You'll need: Building Permit Application; Commercial Plan Submittal Requirements. Depending on your project, Taylor may also ask for: Change of Occupancy / Change of Tenant Form; Commercial Kitchen Hood Worksheet. See the required-documents checklist on this page for details on each.

Taylor requires 5 inspection(s) for a commercial building permit / tenant improvement, in order: Foundation, Framing, Rough Plumbing/Electrical/Mechanical, Fire Suppression System Inspection, Final. Schedule each through Town of Taylor Building / Zoning Department (Development Services Department) (928-536-7366).

Apply through Town of Taylor Building / Zoning Department (Development Services Department) at Taylor Town Hall, 425 Papermill Road (P.O. Box 158), Taylor, AZ 85939. Phone: 928-536-7366, email: geri@tayloraz.gov. Office hours: Town Hall is currently open Monday - Thursday, 7:30 a.m. - 5:30 p.m. (closed Fridays and all major holidays), per the Town's current live website. An older (2014) Town of Taylor 'Homeowner's Guide to Permits' handout lists Development Services Department hours as Monday - Friday, 8:30 a.m. - 5:00 p.m.; the Town Hall-wide 4-day/10-hour schedule on the current tayloraz.gov site is treated as the more current figure for permit-counter purposes. The single Building Official/Zoning Administrator position (reporting directly to the Town Manager as part of the executive leadership team, per the Town's 2024 AZBO job posting) administers both building permits and zoning/planning for the Town.. Official information: https://www.tayloraz.gov/departments/building/.

Taylor, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/town authority under state enabling statutes (A.R.S. Title 9). The Town of Taylor independently adopts and administers its own construction codes through its own Building/Zoning Department (Development Services Department) at Taylor Town Hall; it does not defer building permitting to Navajo County. Verified independence: Taylor maintains its own Municipal Code Chapter 15.05 (Building and Construction Codes), its own Fee Schedule (effective April 5, 2025), its own Building Permit Application, and a dedicated Building Official/Zoning Administrator position reporting to the Town Manager. The Town shares only Fire/EMS (Taylor-Snowflake Fire) and Police (Snowflake-Taylor Police Department) with the adjacent Town of Snowflake — building/zoning permitting is NOT a shared program between the two towns. Source: Town of Taylor Municipal Code § 15.05 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html); tayloraz.gov Building Department and Permits pages; Town of Taylor Fee Schedule effective 4/5/2025; Town of Taylor Building Official/Zoning Administrator job posting (AZBO, 2024).; 2015 International Building Code (IBC), published by the International Code Council, adopted by reference with Appendices C and I, as amended by the Town of Taylor (Taylor Municipal Code § 15.05). Source: Town of Taylor Municipal Code § 15.05.040 (codepublishing.com/AZ/Taylor/html/Taylor15/Taylor1505.html).; 2015 International Residential Code (IRC) for One- and Two-Family Dwellings, adopted by reference with Appendices A, B, H, M, N, R, and S, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Plumbing Code (IPC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Mechanical Code (IMC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fuel Gas Code (IFGC), adopted by reference with Appendices A, B, and C, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2009 International Energy Conservation Code (IECC) — notably one code family behind the Town's otherwise-2015 ICC set. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Existing Building Code (IEBC), adopted by reference, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2015 International Fire Code (IFC), adopted by reference as the Town's uniform fire code, as amended by the Town of Taylor. Source: Town of Taylor Municipal Code § 15.05.; 2014 National Electrical Code (NEC/NFPA 70), published by the National Fire Protection Association, adopted by reference, as amended by the Town of Taylor — one edition behind the otherwise-2015 ICC family set (the same one-cycle-behind pattern seen in other Navajo County towns, e.g. Show Low's 2017 NEC alongside 2018 ICC codes). Source: Town of Taylor Municipal Code § 15.05.; Residential fire sprinklers: IRC Section R313 is deleted in its entirety and replaced with a cross-reference directing compliance to Arizona Revised Statute § 9-807 (the state statute governing municipal authority to require or not require residential fire sprinklers) rather than the model code's own prescriptive sprinkler trigger. Source: Town of Taylor Municipal Code § 15.05 (IRC Chapter 3 amendment).; Manufactured homes, mobile homes, and factory-built buildings: construction/installation standards are regulated directly by the State of Arizona (Arizona Department of Housing, Office of Manufactured Housing (OMH); A.R.S. § 41-4001 et seq.). The Town of Taylor's own Building/Zoning Department governs on-site placement, foundation/tie-down, and zoning compliance, and imposes its own additional zoning-based requirements (see localAmendments). As of the Town's published guidance, Arizona no longer allows Owner-Builder permits for manufactured home installation — a licensed installer must apply for the permit. Source: Town of Taylor 'Manufactured Homes Requirements in Taylor AZ' handout (Taylor Building/Zoning Department); A.R.S. § 41-4001 et seq.. Local amendments apply — see the Taylor overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Taylor building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Taylor.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.